← Back
Elevator cooperative
240 EAST 35 STREET
MANHATTAN · Murray Hill-Kips Bay · BIN 1020163
💬 Discuss this project
1955Year Built
12Stories
D4Building Class
R8BZoning
91,745 sfGross Floor Area
121Units
LL97 CoveredRent Stabilized6 Open Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: 24035 OWNERS CORP · 12,343 sf lot · 7.43 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Roof2p · 2 filings · 12 docs
Floor 1118p · 1 filing · 20 docs
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Cellar5p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
AKAM ASSOCIATES4207/08/2026
24035 OWNER'S CORP.3903/22/2026
24035 OWNERS CORP/DOUGLAS103/22/2026
BOARD 240 E 35203/22/2026
BELLMARC REALTY 9 FLOOR103/22/2026
DYNAMIC BRIDGE LLC103/21/2026
DOUGLAS ELLIMAN PROPERTY MNGT203/21/2026
240 EAST 35TH STREET603/21/2026
240 E 35TH ST DOUG ELLIMAN PROP603/21/2026
ANDREWS BUILDING303/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MUNICIPAL BUILDING CONSULTANTS303/21/2026
MICHAEL ZENREICH ARCHITECT203/21/2026
GREEN LIGHT EXPEDITING LLC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BERNARD CLAREGeneral Contractor907/08/2026
JRR CONTRACTING INCGeneral Contractor404/09/2026
CC CONTROLLED PLBG CO.,INPlumbing407/08/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor303/21/2026
G.M.A. PLUMBING & HEATINGPlumbing307/08/2026
AMERICAN INDUSTRIES LLCGeneral Contractor203/21/2026
C C CONTROLLED COMBUSTIONGeneral Contractor107/08/2026
VERTCON BUILDERS LLCGeneral Contractor104/09/2026
CPH PIPELINE OF N Y INCElectrical103/21/2026
WORLDWIDE PLBG & HTG INCPlumbing107/08/2026
EMPIRE LIC ELECL CONTRSElectrical103/22/2026
INDY ELECTRIC CORP.Electrical103/22/2026
JEFFREY, DARRINElectrical103/21/2026
MICHAEL BAPTISTEElectrical103/21/2026
MIRINO, MICHAELElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ROBERT F. GERMAIN JR. PE5100701/27/2026
JASON M APTOWITZ CONSULTI5671210/13/2025
SHAHRISH SHUVO ENGINEERIN8524104/04/2025
GEORGE J. XERAKIAS, PE1658101/30/2025
FP ARCHITECTS PC2734710/16/2024
Building Lifecycle
All (173)Filed (22)Permit Issued (21)Signed Off (6)Facade (FISP) (18)Violation (60)Inspection (6)Objection (10)Special Inspection (30)
05/11/2026
Cycle 10 facade report submitted
05/11/2026
Cycle 10 facade report signed — SAFE
05/05/2026
Cycle 10 facade inspection completed
01/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
01/27/2026
Filed — Alteration
RECONNECT EXISTING LOW PRESSURE GAS LINE. NEW GAS TRAIN. STRAIGHT GAS ONLY AT THIS TIME. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01078486-P4
01/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
12/31/2025
Violation issued (ECB, closed)
Unknown
12/24/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/23/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01170098-I1
12/19/2025
Filed — Alteration
RECONNECT EXISTING LOW PRESSURE GAS LINE. NEW GAS TRAIN. STRAIGHT GAS ONLY AT THIS TIME. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01078486-P3
12/09/2025
Permit issued — Plumbing
M01078486-I1-PL
12/09/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
12/09/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/01/2025
Permit issued — Boiler Equipment
M01078486-S1-BE
11/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
11/14/2025
Filed — Alteration
RECONNECT EXISTING LOW PRESSURE GAS LINE. NEW GAS TRAIN. STRAIGHT GAS ONLY AT THIS TIME. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01078486-P2
11/14/2025
Filed — Alteration
RECONNECT EXISTING LOW PRESSURE GAS LINE. NEW GAS TRAIN. STRAIGHT GAS ONLY AT THIS TIME. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01078486-P1
11/07/2025
Signed off — Alteration
M01199167-I1
11/07/2025
Signed off — Alteration
Installation of suspended scaffold for facade repair & inspection.
M01170835-I1
10/29/2025
Permit issued — Structural
M01291671-I1-GC-CX
10/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
10/13/2025
Filed — Alteration
GARAGE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01291671-I1
09/23/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
JASON APTOWITZ
09/23/2025
Special inspection requirement — Final
JASON APTOWITZ
09/23/2025
Special inspection requirement — Tenant Protection Plan Compliance
JASON APTOWITZ
09/11/2025
Permit issued — General Construction
M01065784-I1-GC
04/25/2025
Permit issued — General Construction
M01199167-I1-GC
04/04/2025
Filed — Alteration
M01199167-I1
03/29/2025
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01170098-P1
02/25/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/24/2025
Permit issued — General Construction
M01065784-I1-GC
02/14/2025
Permit issued — Suspended Scaffold
M01170835-I1-SC
02/07/2025
Signed off — Alteration
ALTERATION TYPE 2 TO ONE DWELLING UNIT (11-A) ON THE 11TH FLOOR OF AN EXISTING MASONRY 12 STORY MULTI-FAMILY BUILDING.
M00545727-S1
01/30/2025
Filed — Alteration
Installation of suspended scaffold for facade repair & inspection.
M01170835-I1
01/23/2025
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01170098-I1
01/23/2025
Permit issued — Sidewalk Shed
M01170098-I1-SH
01/23/2025
Special inspection requirement — Post-installed Anchors
George Xerakias
01/23/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
George Xerakias
11/18/2024
Permit issued — General Construction
M01078486-S2-GC
11/06/2024
Filed — Alteration
RECONNECT EXISTING LOW PRESSURE GAS LINE. NEW GAS TRAIN. STRAIGHT GAS ONLY AT THIS TIME. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
M01078486-S2
11/06/2024
Special inspection requirement — Lighting controls
FRANK PIZZURRO
11/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FRANK PIZZURRO
11/06/2024
Special inspection requirement — Masonry
FRANK PIZZURRO
11/06/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
FRANK PIZZURRO
11/06/2024
Special inspection requirement — Fire-Resistance Rated Construction
FRANK PIZZURRO
11/06/2024
Special inspection requirement — Energy Code Compliance Inspections
FRANK PIZZURRO
11/06/2024
Special inspection requirement — Maintenance information
FRANK PIZZURRO
11/06/2024
Special inspection requirement — Interior lighting power
FRANK PIZZURRO
10/28/2024
Permit issued — Boiler Equipment
M01078486-S1-BE
10/25/2024
Special inspection requirement — Tenant Protection Plan Compliance
Robert Germain Jr.
10/16/2024
Filed — Alteration
ALTERATION TYPE 2 TO ONE DWELLING UNIT (11-A) ON THE 11TH FLOOR OF AN EXISTING MASONRY 12 STORY MULTI-FAMILY BUILDING.
M00545727-P5
10/16/2024
Special inspection requirement — Chimneys and vents
Robert Germain Jr.
10/16/2024
Special inspection requirement — Final
Robert Germain Jr.
10/16/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
10/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FRANK PIZZURRO
10/14/2024
Special inspection requirement — Fire-Resistance Rated Construction
FRANK PIZZURRO
10/14/2024
Special inspection requirement — Lighting controls
FRANK PIZZURRO
10/14/2024
Special inspection requirement — Maintenance information
FRANK PIZZURRO
10/14/2024
Special inspection requirement — Interior lighting power
FRANK PIZZURRO
10/14/2024
Special inspection requirement — Energy Code Compliance Inspections
FRANK PIZZURRO
Latest 60 of 173 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCC CONTROLLED PLBG CO.,IN12/09/2025
DOB NOWBoiler EquipmentSigned-offCC CONTROLLED PLBG CO.,IN12/01/2025
DOB NOWStructuralSigned-offJRR CONTRACTING INC10/29/2025
DOB NOWGeneral ConstructionSigned-offJRR CONTRACTING INC09/11/2025
DOB NOWGeneral ConstructionSigned-offVERTCON BUILDERS LLC04/25/2025
DOB NOWGeneral ConstructionSigned-offJRR CONTRACTING INC02/24/2025
DOB NOWSuspended ScaffoldSigned-offJRR CONTRACTING INC02/14/2025
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC01/23/2025
DOB NOWGeneral ConstructionPermit IssuedC C CONTROLLED COMBUSTION11/18/2024
DOB NOWBoiler EquipmentSigned-offCC CONTROLLED PLBG CO.,IN10/28/2024
DOB NOWPlumbingSigned-offCC CONTROLLED PLBG CO.,IN10/02/2024
DOB NOWPlumbingSigned-offG.M.A. PLUMBING & HEATING06/25/2024
DOB NOWGeneral ConstructionPermit IssuedBERNARD CLARE10/23/2023
DOB NOWGeneral ConstructionPermit IssuedBERNARD CLARE08/01/2023
DOB NOWPlumbingSigned-offG.M.A. PLUMBING & HEATING06/21/2023
DOB NOWGeneral ConstructionPermit IssuedBERNARD CLARE10/17/2022
DOB NOWGeneral ConstructionPermit IssuedBERNARD CLARE07/29/2022
DOB NOWGeneral ConstructionPermit IssuedBERNARD CLARE04/15/2022
DOB NOWPlumbingSigned-offG.M.A. PLUMBING & HEATING03/29/2022
DOB NOWGeneral ConstructionSigned-offJP GC AND CONSTRUCTION08/10/2021
DOB NOWPlumbingSigned-offWORLDWIDE PLBG & HTG INC06/23/2021
BISPLISSUEDMCMANUS MECH MAINT P&H INC10/07/2022
BISOTISSUEDSKYLINE WINDOWS LLC11/24/2020
BISOTISSUEDSKYLINE WINDOWS LLC10/19/2020
BISOTISSUEDPANORAMA WINDOWS LTD02/13/2020
BISOTISSUEDAMERICAN INDUSTRIES LLC03/01/2019
BISPLISSUEDEVERYDAY MECHANICAL CORP01/23/2019
BISOTISSUEDAMERICAN INDUSTRIES LLC01/17/2019
BISEQISSUEDDYNAMIC INSTALLATION CORP.03/05/2018
BISOTISSUEDAM BUILDING RESTORATION*09/11/2017
BISEQISSUEDDYNAMIC INSTALLATION CORP.03/28/2017
BISPLISSUEDARIANA CONTRACTING INC01/10/2017
BISOTISSUEDCENTRAL BUILDERS DEVELOPMENT12/15/2016
BISOTISSUEDGOLDEN SAW CONSTRUCTION C11/11/2016
BISOTISSUEDASA BUILDING MAINT INC10/26/2016
BISOTISSUEDNORTHEASTERN PROPERTY02/12/2016
BISPLISSUEDEVERYDAY MECHANICAL CORP03/30/2015
BISOTISSUEDAMERICAN INDUSTRIES LLC03/23/2015
BISPLISSUEDPATRIOT PLBG & HTG INC12/15/2014
BISOTISSUEDCOUNTER INTELLIGENCE INC12/08/2014
+ 31 more permits on file
2 projects · most recent 01/27/2026
Gas Water/Sanitary
FiledStatusContractorScope
01/27/2026Signed-offCC CONTROLLED PLBG CO.,INGas
10/16/2024Signed-offG.M.A. PLUMBING & HEATINGGas, Water/Sanitary
7 projects · most recent 06/17/2025
General Wiring
FiledStatusContractorScope
06/17/2025CompleteEMPIRE LIC ELECL CONTRS—
01/28/2025CompleteBOROWIDE ELECT'L CONTR'S—
05/29/2024Permit IssuedL.J.F. & SONS ELECL CONTSGeneral Wiring
01/25/2022CompleteINDY ELECTRIC CORP.General Wiring
02/11/2020CompleteGLENDALE ELECTL CONTNG INGeneral Wiring
07/09/2019CompleteS.A.L. ELECTRIC CO INC.—
08/23/2018CompleteRESPONSE ELECTRIC INC.General Wiring
1 project · most recent 10/13/2025
Concrete
FiledStatusContractorScope
10/13/2025Signed-offJRR CONTRACTING INCConcrete
1 project · most recent 10/13/2025
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
10/13/2025Signed-offJRR CONTRACTING INCTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
12/24/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/09/2025Pass-Final Boiler Equipment InspectionPassView ↗
12/09/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/25/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/24/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/22/2021Pass-Final PL - More than 10 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 39
DateRequirementInspectorRole
01/29/2026Fire-Resistant Penetrations and JointsRobert Germain Jr.special
01/08/2026Fire-Resistant Penetrations and JointsRobert Germain Jr.special
11/17/2025Fire-Resistant Penetrations and JointsRobert Germain Jr.special
10/28/2025Fire-Resistant Penetrations and JointsRobert Germain Jr.special
09/23/2025Structural Stability – Alterations of existing buildingsJASON APTOWITZspecial
09/23/2025FinalJASON APTOWITZprogress
09/23/2025Tenant Protection Plan ComplianceJASON APTOWITZspecial
01/23/2025Post-installed AnchorsGeorge Xerakiasspecial
01/23/2025Alternative Materials - OTCR Buildings Bulletin NumberGeorge Xerakiasspecial
11/06/2024Lighting controlsFRANK PIZZURROenergy_progress
11/06/2024Fire-Resistant Penetrations and JointsFRANK PIZZURROspecial
11/06/2024MasonryFRANK PIZZURROspecial
11/06/2024Structural Stability – Alterations of existing buildingsFRANK PIZZURROspecial
11/06/2024Fire-Resistance Rated ConstructionFRANK PIZZURROprogress
11/06/2024Energy Code Compliance InspectionsFRANK PIZZURROprogress
11/06/2024Maintenance informationFRANK PIZZURROenergy_progress
11/06/2024Interior lighting powerFRANK PIZZURROenergy_progress
10/25/2024Tenant Protection Plan ComplianceRobert Germain Jr.special
10/16/2024Chimneys and ventsRobert Germain Jr.special
10/16/2024FinalRobert Germain Jr.progress
10/16/2024Fire-Resistant Penetrations and JointsRobert Germain Jr.special
10/14/2024Fire-Resistant Penetrations and JointsFRANK PIZZURROspecial
10/14/2024Fire-Resistance Rated ConstructionFRANK PIZZURROprogress
10/14/2024Lighting controlsFRANK PIZZURROenergy_progress
10/14/2024Maintenance informationFRANK PIZZURROenergy_progress
Latest 25 of 39.
▾Documents — 515 on file (BIS + DOB NOW)
▸Plans & Drawings22
▸DOB NOWPlans/Sketch22
09/04/2026M00485219-I1Request digital key ↗
09/04/2026M00485236-I1Request digital key ↗
08/27/2026M00545727-P4Request digital key ↗
Showing 3 of 22 on file for this type
▸Applications & Permits89
▸BISPLAN / WORK APPROVAL APPLICATION51
01/22/2023100481480Open ↗
09/29/2022102018950Open ↗
09/22/2022102018950Open ↗
Showing 3 of 51 on file for this type
▸BISWORK PERMIT APPLICATION36
10/07/2022102018950Open ↗
10/19/2020140935870Open ↗
02/14/2020123413779Open ↗
Showing 3 of 36 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications126
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION40
09/27/2019140815526Open ↗
07/22/2019123064469Open ↗
06/24/2019140815526Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature22
09/04/2026M00485219-I1Open ↗
08/27/2026M00545727-P5Open ↗
08/27/2026M00545727-P4Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature21
09/27/2026M00545727-P4Open ↗
09/02/2026M00545727-I1Open ↗
09/02/2026M00545727-I1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
09/27/2026M00545727-P4Open ↗
09/27/2026M00545727-P4Open ↗
09/02/2026M00545727-I1Open ↗
Showing 3 of 13 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST10
03/30/2018123413779Open ↗
04/05/2017123052374Open ↗
09/29/2016122892520Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT9
03/30/2018123413779Open ↗
04/05/2017123052374Open ↗
09/29/2016122892520Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISAPPLICANT OWNER SIGNATURE3
09/10/2020140935870Open ↗
11/16/2018140815526Open ↗
Showing 2 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
09/19/2016140535311Open ↗
Showing 1 of 2 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
09/19/2016140535311Open ↗
Showing 1 of 2 on file for this type
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment32
▸BISSCHEDULE B - PLUMBING14
09/29/2022102018950Open ↗
09/22/2022102018950Open ↗
09/15/2022102018950Open ↗
Showing 3 of 14 on file for this type
▸BISSELF-CERT PLUMBING NOTICE13
10/05/2015122262826Open ↗
06/24/2015122262826Open ↗
Showing 2 of 13 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
03/19/2019140815526Open ↗
01/11/2017122861242Open ↗
08/17/2016122861242Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection13
▸BISTenant Protection Plan and Notes10
09/10/2020140935870Open ↗
11/16/2018140815526Open ↗
03/30/2018123413779Open ↗
Showing 3 of 10 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSTREET TREE CHECKLIST1
09/10/2020140935870Open ↗
▸Environmental & Asbestos32
▸BISASBESTOS: CERTIFICATION (DEP ACP5)15
08/12/2020140935870Open ↗
01/14/2019140815526Open ↗
11/16/2018140815526Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/20/2026M01078486-S1Open ↗
08/20/2026M01078486-I1Open ↗
08/20/2026M01078486-P4Open ↗
Showing 3 of 9 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Energy Compliance53
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS24
09/27/2019140815526Open ↗
07/22/2019123064469Open ↗
06/24/2019140815526Open ↗
Showing 3 of 24 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS12
07/08/2020123413779Open ↗
09/27/2019140815526Open ↗
07/22/2019123064469Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY6
02/26/2021140935870Open ↗
08/12/2020140935870Open ↗
07/08/2020123413779Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.3
08/13/2026M00545727-S1Open ↗
08/13/2026M00545727-I1Open ↗
08/13/2026M00485219-I1Open ↗
▸BISNYCECC ANALYSIS2
09/19/2016140535311Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
09/19/2016140535311Open ↗
Showing 1 of 2 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
02/26/2021140935870Open ↗
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports18
▸BISTECHNICAL REPORT: RESPONSIBILITY16
12/15/2022102018950Open ↗
08/15/2022102018950Open ↗
08/11/2022102018950Open ↗
Showing 3 of 16 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
12/15/2022102018950Open ↗
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
12/19/2022102018950Open ↗
▸Approvals, Objections & Sign-offs28
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST17
02/26/2021140935870Open ↗
07/08/2020123413779Open ↗
09/27/2019140815526Open ↗
Showing 3 of 17 on file for this type
▸BISADMINISTRATIVE OBJECTIONS9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISSUPERSEDING LETTER2
10/07/2022102018950Open ↗
Showing 1 of 2 on file for this type
▸Cost, Insurance & Ownership41
▸BISCOST AFFIDAVIT35
08/12/2020140935870Open ↗
07/08/2020123413779Open ↗
07/22/2019123064469Open ↗
Showing 3 of 35 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT5
12/21/2016122861242Open ↗
02/17/2016122492016Open ↗
Showing 2 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
02/26/2021140935870Open ↗
▸Filing & Intake Forms41
▸BISEFILING COVER SHEET17
03/30/2018123413779Open ↗
04/05/2017123052374Open ↗
04/05/2017123064469Open ↗
Showing 3 of 17 on file for this type
▸BISADDITIONAL INFORMATION11
04/01/2019140815526Open ↗
03/19/2019140815526Open ↗
03/15/2019140815526Open ↗
Showing 3 of 11 on file for this type
▸BISBOROUGH INTAKE FORM7
10/15/2019123064469Open ↗
10/07/2019123064469Open ↗
09/27/2019140815526Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
11/16/2018140815526Open ↗
09/19/2016140535311Open ↗
Showing 2 of 6 on file for this type
▸Other Documents20
▸DOB NOWDHCR Document14
08/13/2026M00545727-P5Open ↗
08/13/2026M00545727-I1Open ↗
08/13/2026M00545727-P4Open ↗
Showing 3 of 14 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BIS* FIRE STOPS 27-3451
12/15/2022102018950Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01170835-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M01170835-I1Open ↗