| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2025 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/31/2025 | Permit Issued | HIGH QUALITY ELEC.OF NYC | — |
| 05/23/2025 | Complete | COBRA ELECTRICAL NYC LLC | — |
| 06/22/2022 | Permit Issued | ROBERT CHIMENTI | 51 meters, 1 new_meters |
| 06/21/2022 | Permit Issued | SAFETECH ELECL CONTNG COR | General Wiring |
| 11/08/2021 | Permit Issued | E & M ELECTRICAL NY CORP | General Wiring |
| 05/12/2021 | Permit Issued | MOMERN ELECT'L CONTRS INC | General Wiring |
| 04/21/2021 | Complete | GSA ELECTRIC CORP. | General Wiring |
| 01/11/2021 | Complete | GEMINI ELECTRIC CO., INC. | General Wiring |
| 11/16/2020 | Complete | MOMERN ELECT'L CONTRS INC | General Wiring |
| 07/16/2020 | Complete | TOP SHELF ELECTRIC CORP | — |
| 11/26/2018 | Complete | P & Z ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/22/2023 | Permit Issued | PLATINUM SERVICES NY LLC | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/17/2025 | Permit Issued | TRIBUTE RESTORATION INC | Suspended Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/17/2025 | Permit Issued | TRIBUTE RESTORATION INC | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| PLATINUM SERVICES NY | 5 | 07/08/2026 |
| KINGS GROUP NY | 5 | 04/09/2026 |
| 240 W 75 ST CORP | 2 | 03/22/2026 |
| 240 WEST 75 STREET | 13 | 03/22/2026 |
| 240 WEST 75TH ST.CORP | 1 | 03/22/2026 |
| 240 WEST 75TH STREET | 33 | 03/21/2026 |
| 240 WEST 75TH ST APARTMENT | 6 | 03/21/2026 |
| TUDOR REALTY SERVICES | 6 | 03/21/2026 |
| 240 W 75TH ST | 3 | 03/21/2026 |
| 240 3 75TH | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| S&J Engineers PLLC | 1 | 10/30/2025 |
| LONG ISLAND ENGINEERING & ARCHITECT | 2 | 08/27/2025 |
| SUPERSTRUCTURES ENG. + ARCH. | 1 | 06/19/2025 |
| ASHRAF CORP | 1 | 03/22/2023 |
| KIMBERLY PECK ARCHITECT | 2 | 03/15/2023 |
| W.D.ROSS, R.A., P.C | 4 | 02/04/2022 |
| LAB ARCHITECTURE, PLLC | 2 | 09/22/2021 |
| YELLOW HOUSE ARCHITECTS, PLLC | 2 | 12/07/2020 |
| URBAN INTEGRATIONS | 1 | 07/24/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| KMA DESIGNS LLC | 2 | 03/21/2026 |
| PS ENGINEERS | 2 | 03/21/2026 |
| SUPERSTRUCTURES ENG + ARCH | 1 | 03/21/2026 |
| TK ARCDESIGN | 8 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| DOMANI CONSULTING | 2 | 03/21/2026 |
| UNITED SAFETY CONSULTANTS | 1 | 03/21/2026 |
| AE DESIGN SOLUTION | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MK CONSTRUCTION GROUP | General Contractor | 4 | 07/08/2026 |
| TMS PLMBG & HTG CORP | Plumbing | 3 | 07/08/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| KINGS GROUP NY CORP | General Contractor | 2 | 04/09/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 2 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 2 | 07/08/2026 |
| TRIBUTE RESTORATION INC | General Contractor | 2 | 09/09/2026 |
| SILVERMAN ROBERT | Electrical | 1 | 03/21/2026 |
| AP PLUMBING & HVAC LLC | Plumbing | 1 | 07/08/2026 |
| DILAURO, JOHN | Electrical | 1 | 03/21/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| COLON, RAYMOND | Electrical | 1 | 03/21/2026 |
| ALEXANDER EUGENE | Electrical | 1 | 03/21/2026 |
| EREGITANO, J | Electrical | 1 | 03/21/2026 |
| JARAMILLO, OSCAR | Electrical | 1 | 03/21/2026 |
| MILLENNIUM ELEVATOR GROUP | Electrical | 1 | 03/21/2026 |
| ROBERT SILVERMAN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FRANCISCO D. PEREZ PE | 3306 | 1 | 07/17/2025 |
| OUTSOURCE SPECIAL INSPECT | 2827 | 1 | 06/19/2025 |
| LEO Y LEE ASSOCIATES | 2481 | 1 | 11/18/2024 |
| W.D.ROSS, R.A., P.C | 3758 | 4 | 02/04/2022 |
| OOA | 7015 | 2 | 09/30/2021 |
| LAB ARCHITECTURE, PLLC | 3653 | 2 | 09/22/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | TRIBUTE RESTORATION INC | 09/08/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | KINGS GROUP NY CORP | 10/30/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | KINGS GROUP NY CORP | 10/30/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | TRIBUTE RESTORATION INC | 10/02/2025 |
| DOB NOW | Structural | Permit Issued | TRIBUTE RESTORATION INC | 09/08/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | TRIBUTE RESTORATION INC | 07/18/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | DNA CONTRACTING LLC | 12/04/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | PLATINUM SERVICES NY LLC | 03/07/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | PLATINUM SERVICES NY LLC | 03/22/2023 |
| DOB NOW | Plumbing | Signed-off | TMS PLMBG & HTG CORP | 02/28/2023 |
| DOB NOW | Plumbing | Signed-off | TMS PLMBG & HTG CORP | 02/15/2022 |
| DOB NOW | General Construction | Signed-off | MK CONSTRUCTION GROUP | 01/03/2022 |
| DOB NOW | Plumbing | Signed-off | CROSSFIELD PLBG.&HTG | 10/06/2021 |
| DOB NOW | General Construction | Signed-off | MK CONSTRUCTION GROUP | 10/05/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 03/05/2021 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 02/10/2021 |
| DOB NOW | Plumbing | Signed-off | TMS PLMBG & HTG CORP | 01/22/2021 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 12/22/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 07/24/2020 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 02/06/2020 |
| BIS | OT | ISSUED | KBRNY, INC | 04/19/2021 |
| BIS | OT | ISSUED | SALAMONE IMPROVEMENTS INC | 01/08/2021 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 07/16/2020 |
| BIS | OT | ISSUED | JD INTERIORS INC | 07/06/2020 |
| BIS | OT | ISSUED | JD INTERIORS INC | 01/30/2020 |
| BIS | OT | ISSUED | EMG INDUSTRIAL CHIMNEY IN | 02/01/2019 |
| BIS | MH | ISSUED | NUTECH INTERIORS INC | 11/15/2018 |
| BIS | OT | ISSUED | A & I GENERAL CONTRACTORS | 02/23/2018 |
| BIS | PL | ISSUED | APOLLO PLBG & HTG INC | 01/23/2018 |
| BIS | OT | ISSUED | A & I GENERAL CONTRACTORS | 01/19/2018 |
| BIS | PL | ISSUED | ZFM INC | 03/30/2017 |
| BIS | OT | ISSUED | ZEFI MECHANICAL INC | 03/30/2017 |
| BIS | PL | ISSUED | AMC PLBG, HTG & CLNG, INC | 06/15/2016 |
| BIS | OT | ISSUED | EUDA CONSTRUCTION & | 06/08/2016 |
| BIS | MH | ISSUED | EUDA CONSTRUCTION & | 06/08/2016 |
| BIS | OT | ISSUED | EUDA CONSTRUCTION & | 06/08/2016 |
| BIS | OT | ISSUED | PRESERV BLD RESTOR MGT IN | 06/07/2016 |
| BIS | EQ | ISSUED | EVEREST SCAFFOLDING INC | 01/19/2016 |
| BIS | SP | ISSUED | J. CAIAZZO PLBG & HTG CORP | 03/11/2015 |
| BIS | PL | ISSUED | DONATO INC | 06/06/2014 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/01/2025 | Tenant Protection Plan Compliance | — | special |
| 08/01/2025 | Final | — | progress |
| 08/01/2025 | Tenant Protection Plan Compliance | — | special |
| 05/05/2025 | Structural Stability – Alterations of existing buildings | JONAR MADRIAGA | special |
| 05/05/2025 | Tenant Protection Plan Compliance | JONAR MADRIAGA | special |
| 05/05/2025 | Masonry | JONAR MADRIAGA | special |
| 05/05/2025 | Post-installed Anchors | JONAR MADRIAGA | special |
| 05/05/2025 | Structural Steel - Details | JONAR MADRIAGA | special |
| 05/05/2025 | Structural Steel - Welding | JONAR MADRIAGA | special |
| 05/05/2025 | Final | David May | progress |
| 05/05/2025 | Insulation placement and R values | JONAR MADRIAGA | energy_progress |
| 02/07/2022 | Energy Code Compliance Inspections | WILLIAM ROSS | progress |
| 02/07/2022 | Fire-Resistant Penetrations and Joints | WILLIAM ROSS | special |
| 01/27/2022 | Fire-Resistant Penetrations and Joints | WILLIAM ROSS | special |
| 01/27/2022 | Energy Code Compliance Inspections | WILLIAM ROSS | progress |
| 10/06/2021 | Fire-Resistant Penetrations and Joints | Leslie Barnett | special |
| 10/04/2021 | Post-installed Anchors | Okey Oraedu | special |
| 10/04/2021 | Energy Code Compliance Inspections | WILLIAM ROSS | progress |
| 10/04/2021 | Fire-Resistance Rated Construction | WILLIAM ROSS | progress |
| 10/04/2021 | Interior lighting power | WILLIAM ROSS | energy_progress |
| 10/04/2021 | Fire-Resistant Penetrations and Joints | WILLIAM ROSS | special |
| 09/28/2021 | Fire-Resistance Rated Construction | WILLIAM ROSS | progress |
| 09/28/2021 | Post-installed Anchors | Okey Oraedu | special |
| 09/28/2021 | Energy Code Compliance Inspections | WILLIAM ROSS | progress |
| 09/28/2021 | Fire-Resistant Penetrations and Joints | WILLIAM ROSS | special |