← Back
Miscellaneous two family
2407 DEAN STREET
BROOKLYN · BIN 3038801
💬 Discuss this project
1901Year Built
3Stories
B9Building Class
R6Zoning
2,082 sfGross Floor Area
2Units
4 Open Violations ▸FDNY Report ↗
Miscellaneous two family · 2,143 sf lot · 0.97 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof5p · 1 filing · 7 docs
Floor 24p · 1 filing · 7 docs
Floor 14p · 1 filing · 7 docs
Cellar5p · 1 filing · 7 docs
Sub-Basement4p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
5D ARCHITECTURE & ENGINEERING PLLC.311/01/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
5D ARCHITECT AND ENGINEERGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RENANT ANTREN9494211/01/2025
Building Lifecycle
All (17)Filed (3)Permit Issued (2)Violation (4)Objection (6)Special Inspection (2)
05/06/2026
Permit issued — General Construction
B01192936-S1-GC
05/06/2026
Permit issued — General Construction
B01192936-I1-GC
11/08/2025
Objection resolved — Addressed
11/08/2025
Objection resolved — Addressed
11/05/2025
Objection raised — Plumbing
11/05/2025
Objection raised — Cost
11/01/2025
Filed — Alteration
Installation of New 2-HR Fire Rated Party Walls at Exposures 2 & 4 to be supported by the Temporary Shoring to resolve, "Full Stop Work Order".
B01192936-S1
11/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANTHONY RENEAUD
05/01/2025
Objection resolved — Addressed
04/30/2025
Objection raised — Other
04/29/2025
Filed — Alteration
Installation of New 2-HR Fire Rated Party Walls at Exposures 2 & 4 to be supported by the Temporary Shoring to resolve, "Full Stop Work Order".
B01192936-P1
03/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
03/13/2025
Filed — Alteration
Installation of New 2-HR Fire Rated Party Walls at Exposures 2 & 4 to be supported by the Temporary Shoring to resolve, "Full Stop Work Order".
B01192936-I1
11/15/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/28/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/27/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/27/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit Issued5D ARCHITECT AND ENGINEER05/06/2026
DOB NOWGeneral ConstructionPermit Issued5D ARCHITECT AND ENGINEER05/06/2026
1 project · most recent 11/01/2025
FiledStatusContractorScope
11/01/2025Permit Issued5D ARCHITECT AND ENGINEER1 scope_items
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
11/01/2025Fire-Resistant Penetrations and JointsANTHONY RENEAUDspecial
03/17/2025Structural Stability – Alterations of existing buildings—special
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/20/2026B01192936-S1Request digital key ↗
08/20/2026B01192936-I1Request digital key ↗
08/14/2026B01192936-P1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/20/2026B01192936-I1Open ↗
08/13/2026B01192936-S1Open ↗
08/13/2026B01192936-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026B01192936-S1Open ↗