| Owner | Filings | Most Recent |
|---|---|---|
| COMPASS CONSTRUCTION | 66 | 09/29/2026 |
| OWNERS REP | 6 | 07/08/2026 |
| COMPAS CONSTRUCTION OF NY CO INC. | 26 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/14/2023 | $3.5M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| MCHENERY TESTING LAB | 2 | 06/29/2026 |
| NDKAZALAS ARCHITECTURE P.C. | 3 | 05/19/2026 |
| SOLOMON ROSENZWEIG P.E P.C. | 12 | 05/06/2026 |
| SIDERIS KEFALAS ENGINEERS PC | 3 | 02/12/2026 |
| RIGID STRUCTURAL DESIGN, LLC | 1 | 09/13/2024 |
| H & O ENGINEERING, DPC | 1 | 12/21/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| NDKAZALAS ARCHITECTURE | 10 | 03/21/2026 |
| Rigid Structural Design, LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| COMPASS CONSTRUCTION OF N | General Contractor | 51 | 07/08/2026 |
| BERKOWITS REALTY LLC | General Contractor | 9 | 09/29/2026 |
| NEW AMERICAN CONSTRUCTION INC | General Contractor | 5 | 09/19/2026 |
| GWT ENTERPRISES INC | General Contractor | 3 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SOLOMON ROSENZWEIG P.E. P | 1801 | 13 | 05/19/2026 |
| REGIONAL TESTING CORP. | 394 | 1 | 10/11/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | BERKOWITS REALTY LLC | 09/28/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | NEW AMERICAN CONSTRUCTION INC | 09/18/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | NEW AMERICAN CONSTRUCTION INC | 09/16/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | NEW AMERICAN CONSTRUCTION INC | 09/15/2026 |
| DOB NOW | Foundation | Permit Issued | BERKOWITS REALTY LLC | 08/26/2026 |
| DOB NOW | Foundation | Permit Issued | BERKOWITS REALTY LLC | 08/13/2026 |
| DOB NOW | Sprinklers | Permit Issued | CREATIVE PLUMBING IN | 08/06/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | NEW AMERICAN CONSTRUCTION INC | 06/30/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | NEW AMERICAN CONSTRUCTION INC | 06/30/2026 |
| DOB NOW | General Construction | Permit Issued | BERKOWITS REALTY LLC | 06/23/2026 |
| DOB NOW | Structural | Permit Issued | BERKOWITS REALTY LLC | 06/22/2026 |
| DOB NOW | General Construction | Permit Issued | BERKOWITS REALTY LLC | 06/18/2026 |
| DOB NOW | Foundation | Permit Issued | BERKOWITS REALTY LLC | 06/18/2026 |
| DOB NOW | Support of Excavation | Permit Issued | BERKOWITS REALTY LLC | 06/18/2026 |
| DOB NOW | Construction Fence | Permit Issued | BERKOWITS REALTY LLC | 06/17/2026 |
| DOB NOW | General Construction | Permit Issued | COMPASS CONSTRUCTION OF N | 02/20/2026 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/13/2026 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/12/2026 |
| DOB NOW | Support of Excavation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/12/2026 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/12/2026 |
| DOB NOW | Structural | Permit Issued | COMPASS CONSTRUCTION OF N | 02/12/2026 |
| DOB NOW | Construction Fence | Permit Issued | COMPASS CONSTRUCTION OF N | 02/11/2026 |
| DOB NOW | Construction Fence | Permit Issued | COMPASS CONSTRUCTION OF N | 02/06/2026 |
| DOB NOW | General Construction | Permit Issued | COMPASS CONSTRUCTION OF N | 02/02/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | GWT ENTERPRISES INC | 11/20/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | GWT ENTERPRISES INC | 09/18/2025 |
| DOB NOW | Construction Fence | Permit Issued | COMPASS CONSTRUCTION OF N | 02/27/2025 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/27/2025 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/26/2025 |
| DOB NOW | Structural | Permit Issued | COMPASS CONSTRUCTION OF N | 02/25/2025 |
| DOB NOW | Support of Excavation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/25/2025 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 02/25/2025 |
| DOB NOW | General Construction | Permit Issued | COMPASS CONSTRUCTION OF N | 02/20/2025 |
| DOB NOW | General Construction | Permit Issued | COMPASS CONSTRUCTION OF N | 01/13/2025 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 01/13/2025 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 01/13/2025 |
| DOB NOW | Structural | Permit Issued | COMPASS CONSTRUCTION OF N | 01/13/2025 |
| DOB NOW | Construction Fence | Permit Issued | COMPASS CONSTRUCTION OF N | 01/13/2025 |
| DOB NOW | Foundation | Permit Issued | COMPASS CONSTRUCTION OF N | 01/13/2025 |
| DOB NOW | Support of Excavation | Permit Issued | COMPASS CONSTRUCTION OF N | 01/13/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/19/2026 | Permit Issued | BERKOWITS REALTY LLC | Air Conditioning Systems, Ventilation Systems | Cooling Islandaire EZLA09L231Z46AB 9,600 BTU · Ptac ×82 EZLA16L331Z46AB 15,400 BTU · Ptac ×32 EZLA12L231Z46AB 12,000 BTU · Ptac ×12 Ventilation Addison PROH084B1A2 1,150 CFM · Erv ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | — | — | 274 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | Permit Issued | METFLOW MECHANICAL LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | Permit Issued | BERKOWITS REALTY LLC | Concrete |
| 02/03/2022 | Permit Issued | BERKOWITS REALTY LLC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2026 | Permit Issued | NEW AMERICAN CONSTRUCTION | Sidewalk Shed |
| 05/17/2022 | — | — | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/27/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/23/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/10/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/17/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/10/2026 | Post-installed Anchors | Solomon Rosenzweig | special |
| 08/10/2026 | Concrete - Cast-In-Place | Solomon Rosenzweig | special |
| 08/10/2026 | Excavations - Sheeting, Shoring, and Bracing | Solomon Rosenzweig | special |
| 08/10/2026 | Subsurface Investigations (Borings/Test Pits) | STEPHEN LAWNICZAK | special |
| 08/10/2026 | Subgrade Inspections | Solomon Rosenzweig | special |
| 08/10/2026 | Structural Steel - Welding | Solomon Rosenzweig | special |
| 08/10/2026 | Structural Stability – Alterations of existing buildings | Solomon Rosenzweig | special |
| 05/18/2026 | Fenestration areas | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Metering | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Permanent certificate | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Insulation placement and R values | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Lighting in dwelling units | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Lighting controls | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Fenestration and door U-factor and product ratings | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Exterior lighting power | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Maintenance information | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Wall Panels, Curtain Walls, and Veneers | Solomon Rosenzweig | special |
| 05/18/2026 | Mastic and Intumescent Fire-resistant Coatings | Solomon Rosenzweig | special |
| 05/18/2026 | Masonry | Solomon Rosenzweig | special |
| 05/18/2026 | Fire-Resistant Penetrations and Joints | Solomon Rosenzweig | special |
| 05/18/2026 | Exterior Insulation and Finish Systems (EIFS) | Solomon Rosenzweig | special |
| 05/18/2026 | Fenestration air leakage | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Air barrier continuity plan testing | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Air barrier — testing | Solomon Rosenzweig | energy_progress |
| 05/18/2026 | Electrical motors and elevators | Solomon Rosenzweig | energy_progress |