MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
NEW SPRINKLER RISERS, HEADS, DELUGE VALVE & DRY SYSTEM VALVE FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
INSTALLATION OF NEW DOMESTIC WATER SERVICE AND SANITARY/STORM HOUSE TRAPS, SEWAGE EJECTOR, ELEVATOR SUMP PUMP & ALL ASSOCIATED PIPING AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Bulkhead2p · 1 filing · 20 docs
ArchitecturePlumbing
GENERAL CONSTRUCTION WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
26 documents · 2 drawing sheets
Floor 620p · 10 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
INSTALLATION OF NEW SPRINKLER INFRASTRUCTURE ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
NEW SPRINKLER RISERS, HEADS, DELUGE VALVE & DRY SYSTEM VALVE FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 554p · 12 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
INSTALLATION OF NEW SPRINKLER INFRASTRUCTURE ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
INSTALLATION OF NEW DOMESTIC WATER SERVICE AND SANITARY/STORM HOUSE TRAPS, SEWAGE EJECTOR, ELEVATOR SUMP PUMP & ALL ASSOCIATED PIPING AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 456p · 11 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
INSTALLATION OF NEW SPRINKLER INFRASTRUCTURE ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
INSTALLATION OF NEW DOMESTIC WATER SERVICE AND SANITARY/STORM HOUSE TRAPS, SEWAGE EJECTOR, ELEVATOR SUMP PUMP & ALL ASSOCIATED PIPING AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 354p · 11 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
INSTALLATION OF NEW SPRINKLER INFRASTRUCTURE ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
INSTALLATION OF NEW DOMESTIC WATER SERVICE AND SANITARY/STORM HOUSE TRAPS, SEWAGE EJECTOR, ELEVATOR SUMP PUMP & ALL ASSOCIATED PIPING AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 254p · 12 filings · 20 docs
ArchitectureCivilDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
INSTALLATION OF NEW SPRINKLER INFRASTRUCTURE ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
INSTALLATION OF NEW DOMESTIC WATER SERVICE AND SANITARY/STORM HOUSE TRAPS, SEWAGE EJECTOR, ELEVATOR SUMP PUMP & ALL ASSOCIATED PIPING AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 160p · 11 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
INSTALLATION OF NEW SPRINKLER INFRASTRUCTURE ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
INSTALLATION OF NEW DOMESTIC WATER SERVICE AND SANITARY/STORM HOUSE TRAPS, SEWAGE EJECTOR, ELEVATOR SUMP PUMP & ALL ASSOCIATED PIPING AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 8 filings on this floor.
Cellar55p · 10 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction
INSTALLATION OF NEW SPRINKLER INFRASTRUCTURE ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
MECHANICAL WORK FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
13 documents · 1 drawing sheet
NEW SPRINKLER RISERS, HEADS, DELUGE VALVE & DRY SYSTEM VALVE FOR TENANT FIT OUT AS PER PLANS FILED HEREWITH ASSOCIATED WITH MAIN ALT-1 APPLICATION FOR NYPD BOMB SQUAD. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.