← Back
One story - permanent living quarter
242-06 136 AVENUE
QUEENS · Rosedale · BIN 4284437
💬 Discuss this project
1925Year Built
1.75Stories
A2Building Class
R2Zoning
1,405 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.35 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/25/2015$495K—ORROYO HOMES LLC → Private party$352/sf building
07/24/2015$268K—Private party → ORROYO HOMES LLC$190/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR106/14/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281106/14/2024
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
06/20/2024
Permit issued — Solar
Q01064991-I1-SL
06/14/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 16 Panels, 6.56 kW
Q01064991-I1
06/11/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
06/11/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
06/11/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
06/11/2024
Special inspection requirement — Final
Mina Makar
06/11/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR06/20/2024
1 project · most recent 06/11/2024
FiledStatusContractorScope
06/11/2024CompleteISLAND ELECTRIC CORP—
1 project · most recent 06/14/2024
FiledStatusContractorScope
06/14/2024Signed-offMOMENTUM SOLAR16 panels, 6.56 kw, 282 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
06/11/2024Fire-Resistant Penetrations and JointsMina Makarspecial
06/11/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
06/11/2024Energy Code Compliance InspectionsMina Makarprogress
06/11/2024FinalMina Makarprogress
06/11/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026Q01064991-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026Q01064991-I1Open ↗
08/23/2026Q01064991-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01064991-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026Q01064991-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01064991-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01064991-I1Open ↗