← Back
Over six families without stores
Galaxy City
2422-2426 LYVERE STREET · Westchester Square · BIN 2129786
💬 Discuss this project
2019Year Built
5Stories
C1Building Class
R6Zoning
24,809 sfGross Floor Area
32Units
Rent Stabilized6 Open Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: GALAXY CITY APARTMENTS INC · 10,395 sf lot · 2.39 FAR built · Flood zone X
Locations of Work
StructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Roof29p · 3 filings · 20 docs
Floor 528p · 3 filings · 20 docs
Floor 429p · 3 filings · 20 docs
Floor 329p · 3 filings · 20 docs
Floor 230p · 3 filings · 20 docs
Floor 136p · 5 filings · 20 docs
Cellar29p · 3 filings · 20 docs
Site & exterior20p · 3 filings · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GALAXY CITY APARTMENTS1807/08/2026
STEEL CONSTRUCTION1007/08/2026
GALAXY TOWERS APARTMENTS, INC.403/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/29/2019$725K—— → —$29/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MICHAEL DEPASQUALE, ARCHITECT802/06/2024
ENTHINK ENGINEERS LLC302/17/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACS ENVIRONMENTAL CONSTRUCTION1403/21/2026
PEREXPERTS GMAIL COM203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
STEEL CONSTRUCTION LLCGeneral Contractor407/08/2026
GLOBAL CONSTRUCTION MANAGGeneral Contractor303/21/2026
RESTORATION 365 LLCGeneral Contractor303/21/2026
LLOYD G DRUMMOND PLBG&GENFire Protection107/08/2026
2260 MAG CORPGeneral Contractor104/08/2026
RK HEATING & AIR CONDITIONINGGeneral Contractor104/08/2026
AI FANG WUElectrical103/21/2026
LLOYD G DRUMMOND PLBG&GENPlumbing107/08/2026
KWONG MING ELECTRIC INCElectrical103/22/2026
STEVEN DENNISONElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NEW LINE CONSTRUCTION7226302/06/2024
Building Lifecycle
All (92)Filed (11)Permit Issued (8)Signed Off (6)Violation (1)Inspection (13)Objection (44)Special Inspection (9)
08/14/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
07/25/2025
Violation issued (ECB, closed)
Elevators
01/23/2025
Signed off — Alteration
Construct a 10-foot-wide curb cut for NB 220712888
X00260694-I1
01/22/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
12/20/2024
Permit issued — Curb Cut
X00260694-I1-CC
04/09/2024
Signed off — Alteration
HEREBY SUBMITTING REVISED AS BUILT PLANS PAGES; PL-002.01, PL-003.01, P-004.01, PL-005.01, PL-006.01, PL-007.01 & PL-011.02
X00260356-I1
04/03/2024
Signed off — Alteration
Furnish and install fire sprinklers for NB 200712888
X00260321-I1
03/01/2024
Signed off — Alteration
PROPOSED DUCT WORK FOR NEW BUILDING IN CONJUNCTION WITH JOB NUMBER 220712888
X00325203-I1
02/22/2024
Objection resolved — Addressed
02/22/2024
Special inspection requirement — Sprinkler Systems
AUGUSTINE OKUNDAYE
02/14/2024
Objection raised — Scope
02/06/2024
Filed — Alteration
Furnish and install fire sprinklers for NB 200712888
X00260321-P1
02/02/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/01/2024
Special inspection requirement — Sprinkler Systems
AUGUSTINE OKUNDAYE
01/31/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/12/2024
Objection resolved — Addressed
01/11/2024
Objection raised — C/O of existing property requi
01/10/2024
Filed — Alteration
HEREBY SUBMITTING REVISED AS BUILT PLANS PAGES; PL-002.01, PL-003.01, P-004.01, PL-005.01, PL-006.01, PL-007.01 & PL-011.02
X00260356-P2
12/28/2023
Objection resolved — Addressed
12/07/2023
Objection resolved — Addressed
11/01/2023
Objection resolved — Addressed
11/01/2023
Objection resolved — Addressed
11/01/2023
Objection resolved — Addressed
10/27/2023
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
10/12/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/12/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/19/2023
Filed — Alteration
HEREBY SUBMITTING REVISED AS BUILT PLANS PAGES; PL-002.01, PL-003.01, P-004.01, PL-005.01, PL-006.01, PL-007.01 & PL-011.02
X00260356-P1
08/25/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/21/2023
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
X08012948-I1
08/21/2023
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
X00829643-I1
08/03/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/09/2023
Objection raised — Zoning
06/09/2023
Objection raised — Admin
06/09/2023
Objection raised — Zoning
06/09/2023
Objection raised — Scope
06/09/2023
Objection raised — Structural
06/08/2023
Filed — Alteration
Construct a 10-foot-wide curb cut for NB 220712888
X00260694-I1
05/25/2023
Permit issued — Mechanical Systems
X00325203-I1-MS
04/28/2023
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
04/13/2023
Permit issued — Sprinklers
X00260321-I1-EW-SP
02/24/2023
Permit issued — Plumbing
X00260356-I1-PL
02/20/2023
Permit issued — Supported Scaffold
X00829643-I1-SF
02/17/2023
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
X00829643-I1
12/07/2022
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
X08012948-P1
10/05/2022
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
X08012948-I1
10/05/2022
Permit issued — Sidewalk Shed
X08012948-I1-SH
06/05/2022
Objection raised — Other
06/05/2022
Objection resolved — Addressed
06/01/2022
Objection raised — Admin
06/01/2022
Objection resolved — Addressed
06/01/2022
Objection raised — Scope
06/01/2022
Objection resolved — Addressed
06/01/2022
Objection raised — Mechanical
06/01/2022
Objection resolved — Addressed
06/01/2022
Objection raised — Inspections
06/01/2022
Objection resolved — Addressed
06/01/2022
Objection raised — Structural
06/01/2022
Objection resolved — Addressed
05/31/2022
Objection raised — Other
05/31/2022
Objection resolved — Addressed
Latest 60 of 92 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offGLOBAL CONSTRUCTION MANAG12/20/2024
DOB NOWMechanical SystemsSigned-offRK HEATING & AIR CONDITIO05/25/2023
DOB NOWSprinklersSigned-offLLOYD G. DRUMMOND04/13/2023
DOB NOWPlumbingSigned-offLLOYD G DRUMMOND PLBG&GEN02/24/2023
DOB NOWSupported ScaffoldSigned-offSTEEL CONSTRUCTION LLC02/20/2023
DOB NOWSidewalk ShedSigned-offSTEEL CONSTRUCTION LLC10/05/2022
DOB NOWConstruction FencePermit Issued2260 MAG CORP11/26/2021
DOB NOWConstruction FencePermit IssuedRESTORATION 365 LLC11/19/2019
BIS—ISSUEDGLOBAL CONSTRUCTION MANAG04/18/2023
BIS—ISSUEDGLOBAL CONSTRUCTION MANAG06/09/2022
BIS—ISSUEDGLOBAL CONSTRUCTION MANAG06/09/2022
BIS—RE-ISSUEDCUSTOMBUILT HOMES INC03/08/2022
BIS—ISSUEDCUSTOMBUILT HOMES INC03/08/2022
3 projects · most recent 02/02/2023
General Wiring
FiledStatusContractorScope
02/02/2023CompleteDENNISON ELECTRIC CORPGeneral Wiring
11/01/2022CompleteKWONG MING ELECTRIC INC—
10/11/2022CompleteRICHARD NEU—
1 project · most recent 10/28/2019
Fence
FiledStatusContractorScope
10/28/2019Permit Issued2260 MAG CORPFence
▾Field Inspections (DOB CAP) — 13
DateTypeResultReport
08/14/2025Fail-Final CND-Occupancy InspectionFailView ↗
01/22/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
02/02/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/31/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/27/2023Fail-Final CND-Occupancy InspectionFailView ↗
10/12/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/12/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/25/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/03/2023Pass-Final CND-Occupancy InspectionPassView ↗
04/28/2023Fail-Final CND-Occupancy InspectionFailView ↗
02/25/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/25/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/25/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
02/22/2024Sprinkler SystemsAUGUSTINE OKUNDAYEspecial
02/01/2024Sprinkler SystemsAUGUSTINE OKUNDAYEspecial
03/02/2020Mechanical SystemsAUGUSTINE OKUNDAYEspecial
03/02/2020FinalAUGUSTINE OKUNDAYEprogress
03/02/2020Energy Code Compliance InspectionsMICHAEL DEPASQUALEprogress
03/02/2020Fire-Resistance Rated ConstructionMICHAEL DEPASQUALEprogress
03/02/2020Maintenance informationMICHAEL DEPASQUALEenergy_progress
03/02/2020Shutoff dampersMICHAEL DEPASQUALEenergy_progress
03/02/2020Duct leakage testing MICHAEL DEPASQUALEenergy_progress
▾Documents — 184 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch3
08/23/2026X08012948-P1Request digital key ↗
08/23/2026X08012948-I1Request digital key ↗
08/23/2026X00829643-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing3
08/24/2026X00260356-P1Request digital key ↗
08/15/2026X00260356-I1Request digital key ↗
08/15/2026X00260356-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
08/15/2026X00260321-I1Request digital key ↗
08/15/2026X00260321-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/24/2026X00325203-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/14/2026X00251763-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Curb Cut1
08/23/2026X00260694-I1Request digital key ↗
▸Applications & Permits29
▸BISPLAN / WORK APPROVAL APPLICATION19
05/28/2024220727042Open ↗
03/18/2024220712888Open ↗
03/12/2024220712888Open ↗
Showing 3 of 19 on file for this type
▸BISWORK PERMIT APPLICATION6
04/19/2023220712888Open ↗
06/17/2022220712888Open ↗
06/17/2022220712888Open ↗
Showing 3 of 6 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION4
04/05/2021220712888Open ↗
04/05/2021220712888Open ↗
02/24/2021220712888Open ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records7
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
01/09/2024220719514Open ↗
10/22/2019220712888Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
02/24/2021220712888Open ↗
▸BISVERIFY TAX LOT1
03/07/2024220712888Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
03/07/2024220712888Open ↗
▸BISZONING DIAGRAM1
06/28/2021220712888Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
02/24/2021220712888Open ↗
▸Seals & Professional Certifications25
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/24/2026X00260321-I1Open ↗
08/24/2026X00260356-I1Open ↗
08/24/2026X00260356-P2Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
08/26/2026X00325203-I1Open ↗
08/26/2026X00325203-I1Open ↗
08/26/2026X00325203-I1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
03/08/2022220712888Open ↗
02/26/2020220727042Open ↗
08/19/2019220712888Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/02/2026X00260321-P1Open ↗
09/01/2026X00260321-I1Open ↗
08/26/2026X00325203-I1Open ↗
▸Trade Schedules & Equipment3
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
03/07/2024220712888Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
03/07/2024220712888Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
03/08/2024220712888Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST3
02/24/2021220712888Open ↗
11/08/2019220719514Open ↗
08/19/2019220712888Open ↗
▸BISSTREET TREE SIGNOFF2
12/11/2024220712888Open ↗
11/26/2024220719514Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN2
03/08/2022220712888Open ↗
11/26/2021220712888Open ↗
▸Energy Compliance23
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
11/07/2023220712888Open ↗
12/22/2022220712888Open ↗
11/26/2021220712888Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
03/08/2022220712888Open ↗
03/08/2022220712888Open ↗
02/26/2020220727042Open ↗
Showing 3 of 4 on file for this type
▸BISAIR SEALING AND INSULATION - VISUAL1
03/07/2024220712888Open ↗
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
01/05/2024220712888Open ↗
▸BISINTERIOR LIGHTING POWER1
03/07/2024220712888Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
03/07/2024220712888Open ↗
▸BISFENESTRATION AREAS1
03/07/2024220712888Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
03/07/2024220712888Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
03/07/2024220712888Open ↗
▸BISLIGHTING IN DWELLING UNITS1
03/07/2024220712888Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
04/08/2024220712888Open ↗
▸BISELECTRIC MOTORS1
03/07/2024220712888Open ↗
▸BISLIGHTING CONTROLS1
03/07/2024220712888Open ↗
▸BIS* HVAC INSULATION AND SEALING1
03/07/2024220712888Open ↗
▸BISAIR SEALING AND INSULATION - TESTING1
04/10/2024220712888Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00325203-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026X00325203-I1Open ↗
▸Inspections & Test Reports18
▸BISTECHNICAL REPORT: RESPONSIBILITY3
12/22/2022220712888Open ↗
11/26/2021220712888Open ↗
06/28/2021220712888Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX3
03/08/2022220712888Open ↗
03/08/2022220712888Open ↗
11/30/2021220712888Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION2
02/24/2021220712888Open ↗
08/19/2019220712888Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
03/08/2022220712888Open ↗
11/26/2021220712888Open ↗
▸BISDEMOLITION (DM) JOB SIGNOFF2
03/07/2024220712888Open ↗
11/30/2021220712888Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
04/08/2024220712888Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
04/08/2024220712888Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
04/08/2024220712888Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
04/08/2024220712888Open ↗
▸BISMASONRY1
04/08/2024220712888Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
04/08/2024220712888Open ↗
▸Approvals, Objections & Sign-offs13
▸BISSCHEDULE A - OCCUPANCY / USE10
03/12/2024220712888Open ↗
02/22/2024220712888Open ↗
07/21/2023220712888Open ↗
Showing 3 of 10 on file for this type
▸BISSUPERSEDING LETTER1
06/17/2022220712888Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
04/08/2024220712888Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
08/03/2023220712888Open ↗
▸Cost, Insurance & Ownership5
▸BISPROJECT-SPECIFIC GL INSURANCE3
04/19/2023220712888Open ↗
06/17/2022220712888Open ↗
03/08/2022220712888Open ↗
▸BISCOST AFFIDAVIT1
02/26/2020220727042Open ↗
▸BISBPP: ENGINEERS AFFIDAVIT1
01/09/2024220719514Open ↗
▸Filing & Intake Forms17
▸BISADDITIONAL INFORMATION13
02/06/2025220712888Open ↗
04/18/2024220712888Open ↗
03/19/2024220712888Open ↗
Showing 3 of 13 on file for this type
▸BISEFILING COVER SHEET3
02/26/2020220727042Open ↗
11/08/2019220719514Open ↗
08/19/2019220712888Open ↗
▸BISAI1 OBJECTIONS RESPONSE1
—220712888Open ↗
▸Other Documents8
▸BISSITE SURVEY: INITIAL1
—220712888Open ↗
▸BISSHUTOFF DAMPERS1
03/07/2024220712888Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
01/09/2024220719514Open ↗
▸BISUNDERPINNING (2014)1
04/08/2024220712888Open ↗
▸BISSTRUCTURAL COLD-FORMED STEEL1
04/08/2024220712888Open ↗
▸BISMAINTENANCE INFORMATION1
03/07/2024220712888Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
01/04/2024220719514Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
03/07/2024220712888Open ↗