| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2026 | Permit Issued | RICHARD NEU | — |
| 11/08/2024 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 06/24/2020 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 09/06/2019 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 05/21/2019 | Complete | JOSEPH WEINSTEIN ELECTRIC | 5 meters, 5 new_meters |
| 02/19/2019 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2026 | Permit Issued | R&A CONSTR SERVICES INC | Sidewalk Shed |
| Owner | Filings | Most Recent |
|---|---|---|
| R A CONSTRUCTION SERVICES | 1 | 06/23/2026 |
| 241 WEST 100 ST. OWNERS CORP. | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/13/2022 | $2.9M | — | — → — | $633/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MCHENERY TESTING LAB | 1 | 04/22/2026 |
| NASIR J, KHANZADA LLC | 7 | 12/11/2024 |
| LONGO ARCHITECTS & ASSOCIATES, LLC | 1 | 06/07/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| NASIR J. KHANZADA LLC | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TAWAKAL CONTRACTING | General Contractor | 5 | 07/08/2026 |
| JOSEPH WEINSTEIN ELECTRIC | Electrical | 2 | 03/22/2026 |
| R&A CONSTR SERVICES INC | General Contractor | 1 | 06/23/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NASIR J. KHANZADA LLC | 1527 | 5 | 12/11/2024 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 06/17/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | R&A CONSTR SERVICES INC | 04/23/2026 |
| DOB NOW | Structural | Signed-off | TAWAKAL CONTRACTING | 05/06/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 09/11/2024 |
| DOB NOW | General Construction | Signed-off | TAWAKAL CONTRACTING | 09/11/2024 |
| DOB NOW | Foundation | Signed-off | TAWAKAL CONTRACTING | 09/11/2024 |
| BIS | — | ISSUED | TAWAKAL CONTRACTING | 08/29/2022 |
| BIS | — | ISSUED | TAWAKAL CONTRACTING | 08/26/2022 |
| BIS | PL | ISSUED | TRI STATE PLBG & HTG INC | 03/15/2022 |
| BIS | PL | ISSUED | TRI STATE PLBG & HTG INC | 03/25/2021 |
| BIS | — | ISSUED | TAWAKAL CONTRACTING | 02/11/2021 |
| BIS | — | ISSUED | TAWAKAL CONTRACTING | 01/22/2021 |
| BIS | — | ISSUED | TAWAKAL CONTRACTING | 02/06/2020 |
| BIS | — | ISSUED | ACTION MECHANICAL INC | 05/22/2019 |
| BIS | — | ISSUED | ACTION MECHANICAL INC | 04/15/2019 |
| BIS | PL | ISSUED | ZARA PLUMBING CORP | 04/15/2019 |
| BIS | — | ISSUED | ACTION MECHANICAL INC | 04/25/2018 |
| BIS | PL | ISSUED | ZARA PLUMBING CORP | 04/25/2018 |
| BIS | OT | ISSUED | PAUL ANSD SUZ SOLOMON | 12/11/2000 |
| BIS | — | ISSUED | SUZANNE SOLOMAN | 02/19/1997 |
| BIS | — | ISSUED | SUZANNE SOLOMAN | 11/02/1995 |
| BIS | PL | ISSUED | BALTER LEHIGH PLBG&HTG.CORP. | 09/08/1994 |
| BIS | — | ISSUED | SUZANNE SOLOMAN | 06/03/1993 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/02/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/05/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/02/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/26/2024 | Fire-Resistant Penetrations and Joints | Nasir Khanzada | special |
| 12/26/2024 | Energy Code Compliance Inspections | Nasir Khanzada | progress |
| 12/06/2024 | Energy Code Compliance Inspections | Nasir Khanzada | progress |
| 12/06/2024 | Fire-Resistant Penetrations and Joints | Nasir Khanzada | special |
| 12/04/2024 | Tenant Protection Plan Compliance | Nasir Khanzada | special |
| 11/14/2024 | Structural Steel - Details | Nasir Khanzada | special |
| 11/13/2024 | Structural Cold-Formed Steel | Nasir Khanzada | special |
| 11/05/2024 | Final | William Ryan | progress |
| 11/05/2024 | Fenestration and door U-factor and product ratings | William Ryan | energy_progress |
| 09/12/2024 | Final | Nasir Khanzada | progress |
| 09/12/2024 | Structural Stability – Alterations of existing buildings | Nasir Khanzada | special |