← Back
One story - permanent living quarter
244-48 136 ROAD
QUEENS · Rosedale · BIN 4284567
💬 Discuss this project
1945Year Built
1.5Stories
A2Building Class
R2Zoning
1,104 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.28 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC201/19/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272201/19/2024
Building Lifecycle
All (9)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (5)
04/01/2024
Signed off — Alteration
Q00982398-I1
01/29/2024
Permit issued — Solar
Q00982398-I1-SL
01/19/2024
Filed — Alteration
Q00982398-P1
01/18/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
01/18/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
01/18/2024
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
01/18/2024
Special inspection requirement — Final
Walid Abdulla
01/18/2024
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
01/08/2024
Filed — Alteration
Q00982398-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC01/29/2024
1 project · most recent 01/08/2024
FiledStatusContractorScope
01/08/2024CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/18/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
01/18/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
01/18/2024Energy Code Compliance InspectionsWalid Abdullaprogress
01/18/2024FinalWalid Abdullaprogress
01/18/2024Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/23/2026Q00982398-I1Request digital key ↗
08/23/2026Q00982398-P1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026Q00982398-P1Open ↗
08/28/2026Q00982398-P1Open ↗
08/28/2026Q00982398-P1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/23/2026Q00982398-P1Open ↗
08/23/2026Q00982398-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q00982398-P1Open ↗
08/28/2026Q00982398-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/23/2026Q00982398-P1Open ↗
08/23/2026Q00982398-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00982398-I1Open ↗