← Back
Elevator apt, fireproof without stores
The Monte Excelsior
245-10 GRND CNTRL PKWY SR S · Glen Oaks-Floral Park-New Hyde Park · BIN 4438379
💬 Discuss this project
1966Year Built
6Stories
D3Building Class
R6AZoning
263,883 sfGross Floor Area
240Units
LL97 CoveredRent Stabilized1 Open Violation ▸FISP: SAFEFDNY Report ↗
Elevator apt, fireproof without stores · Owner of record: GF GRAND CENTRAL LLC · 153,000 sf lot · 1.72 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingEquipmentGeneral
Roof2p · 2 filings · 7 docs
Floor 315p · 3 filings · 20 docs
Floor 2
Floor 1
Basement1p · 1 filing · 3 docs
Sub-Basement1 filing · 3 docs
Site & exterior6p · 3 filings · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BLDG MANAGEMENT CO., INC.2607/08/2026
JERRICK ASSOCIATES607/08/2026
T-MOBILE307/08/2026
GF GRAND CENTRAL LLC303/22/2026
BLDG MANAGEMENT CO INC RESIDENTI203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PVE ENGINEERING108/11/2023
KMB DESIGN GROUP, LLC212/06/2022
ZZ ARCHITECTURE PLLC506/28/2022
SCALAR ARCHITECTURE PC111/07/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
M M BUILDING EXPEDITING SERVICES1003/21/2026
CONSTRUCTION PERMIT SERVICES303/21/2026
AE DESIGN SOLUTION203/21/2026
NORTHEAST EXPEDITING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CITI SKYLINE ENT INCGeneral Contractor403/21/2026
TOTAL NY CONSTRUCTION CORPGeneral Contractor303/21/2026
JERRICK ASSOCIATES INCGeneral Contractor307/08/2026
ODYSSIA GLOBAL COMM. CORPGeneral Contractor203/21/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
SQUAN CONSTRUCTION SERVICGeneral Contractor107/08/2026
UB CONSTRUCTION INCGeneral Contractor107/08/2026
CHARLES M. DWYER ELECTLElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARTRIDGE VENTURE ENGINEE7690108/11/2023
KMB DESIGN GROUP, LLC513212/06/2022
JACK GREEN ASSOCIATES422506/28/2022
Building Lifecycle
All (111)Filed (9)Permit Issued (8)Signed Off (7)Facade (FISP) (12)Violation (56)Inspection (4)Objection (4)Special Inspection (11)
10/21/2025
Violation issued (HPD, closed)
C
12/16/2024
Violation issued (HPD, closed)
C
11/13/2024
Violation issued (HPD, closed)
C
11/13/2024
Violation issued (HPD, closed)
C
11/12/2024
Violation issued (HPD, closed)
C
11/12/2024
Violation issued (HPD, closed)
C
10/23/2024
Violation issued (HPD, closed)
C
10/23/2024
Violation issued (HPD, closed)
C
10/23/2024
Violation issued (HPD, closed)
C
10/23/2024
Violation issued (HPD, closed)
B
10/23/2024
Violation issued (HPD, closed)
C
10/18/2024
Violation issued (HPD, closed)
C
10/18/2024
Violation issued (HPD, closed)
C
08/07/2024
Cycle 9 facade report signed — SAFE
04/17/2024
Signed off — Alteration
EXTERIOR FACADE RESTORATION AS PER PLANS FILED HEREWITH. WORK INCLUDES CONCRETE BALCONY SPALL RPRS AND PARAPET RAILING INSTALLATION. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00903559-I1
04/05/2024
Violation issued (HPD, closed)
C
04/05/2024
Violation issued (HPD, closed)
C
04/05/2024
Violation issued (HPD, closed)
C
04/05/2024
Violation issued (HPD, closed)
C
02/21/2024
Cycle 9 facade report submitted
01/25/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
01/17/2024
Cycle 9 facade inspection completed
12/26/2023
Violation issued (HPD, closed)
C
12/15/2023
Violation issued (HPD, closed)
A
12/09/2023
Violation issued (HPD, closed)
C
12/04/2023
Violation issued (HPD, closed)
C
12/04/2023
Violation issued (HPD, closed)
C
11/25/2023
Violation issued (HPD, closed)
C
11/25/2023
Violation issued (HPD, closed)
C
11/25/2023
Violation issued (HPD, closed)
C
11/25/2023
Violation issued (HPD, closed)
C
11/25/2023
Violation issued (HPD, closed)
C
09/08/2023
Permit issued — Structural
Q00903559-I1-GC-CX
08/22/2023
Violation issued (HPD, open)
C
08/11/2023
Filed — Alteration
EXTERIOR FACADE RESTORATION AS PER PLANS FILED HEREWITH. WORK INCLUDES CONCRETE BALCONY SPALL RPRS AND PARAPET RAILING INSTALLATION. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00903559-I1
05/30/2023
Violation issued (HPD, closed)
C
05/30/2023
Violation issued (HPD, closed)
C
05/08/2023
Signed off — Alteration
DECOMMISSION OF EXISTING SPRINT-NEXTEL-CW TELECOM SITE. REMOVE 2 EQUIPMENT PLATFORMS, 11 ANTENNAS, 11 RRH , 2 GPS FROM ROOF. REMOVE CABLES FROM BASEMENT, FACADE & ROOF. NO CHANGE IN USE, EGRESS OR OCCUPANCY. ORIGINAL APP# 400773481.
Q08031723-I1
05/05/2023
Violation issued (HPD, closed)
C
05/05/2023
Violation issued (HPD, closed)
C
03/31/2023
Violation issued (HPD, closed)
A
02/28/2023
Violation issued (HPD, closed)
A
02/28/2023
Violation issued (HPD, closed)
C
02/28/2023
Violation issued (HPD, closed)
A
01/17/2023
Permit issued — Antenna
Q08031723-I1-AN
12/12/2022
Objection raised — Zoning
12/12/2022
Objection resolved — Addressed
12/12/2022
Objection raised — Inspections
12/12/2022
Objection resolved — Addressed
12/06/2022
Filed — Alteration
DECOMMISSION OF EXISTING SPRINT-NEXTEL-CW TELECOM SITE. REMOVE 2 EQUIPMENT PLATFORMS, 11 ANTENNAS, 11 RRH , 2 GPS FROM ROOF. REMOVE CABLES FROM BASEMENT, FACADE & ROOF. NO CHANGE IN USE, EGRESS OR OCCUPANCY. ORIGINAL APP# 400773481.
Q08031723-I1
07/25/2022
Signed off — Alteration
Plumbing work at existing apartments. Replace existing plumbing fixtures on existing roughing.
Q00650159-I1
07/06/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/06/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/30/2022
Signed off — Alteration
INTERIOR RENOVATION OF EXISTING APTS 3H & 3J. NEW PARTITIONS, LIGHT FIXTURES & FINISHES AS PER DRAWINGS. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00650154-I1
06/29/2022
Special inspection requirement — Lighting in dwelling units
Ziv Zamir
06/29/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
JACK GREEN
06/29/2022
Special inspection requirement — Fire-Resistance Rated Construction
Ziv Zamir
06/29/2022
Special inspection requirement — Energy Code Compliance Inspections
Ziv Zamir
06/29/2022
Special inspection requirement — Final
Ziv Zamir
06/28/2022
Filed — Alteration
Plumbing work at existing apartments. Replace existing plumbing fixtures on existing roughing.
Q00650159-P1
Latest 60 of 111 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offTOTAL NY CONSTRUCTION COR09/08/2023
DOB NOWAntennaSigned-offSQUAN CONSTRUCTION SERVIC01/17/2023
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR03/09/2022
DOB NOWGeneral ConstructionSigned-offCITI SKYLINE ENT INC02/24/2022
DOB NOWGeneral ConstructionSigned-offUB CONSTRUCTION INC10/12/2021
DOB NOWSidewalk ShedSigned-offGE 2A CONSTRUCTION11/13/2019
DOB NOWSidewalk ShedSigned-offGE 2A CONSTRUCTION11/08/2018
DOB NOWAntennaSigned-offODYSSIA GLOBAL COMM. CORP07/12/2018
BISOTISSUEDJERRICK ASSOCIATES INC03/25/2019
BISOTISSUEDJERRICK ASSOCIATES INC11/13/2018
BISPLISSUEDAURA PLUMBING INC07/25/2018
BISMHISSUEDODYSSIA GLOBAL COMM. CORP07/23/2018
BISOTISSUEDSQUAN CONSTRUCTION SERVIC11/09/2017
BISOTISSUEDSQUAN CONSTRUCTION SERVIC06/16/2017
2 projects · most recent 11/07/2018
FiledStatusContractorScope
11/07/2018CompleteBOROWIDE ELECT'L CONTR'S—
03/16/2018CompleteCHARLES M. DWYER ELECTL21 meters, 1 new_meters
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
01/25/2024Pass-Final General Construction Non-Directive 14PassView ↗
07/06/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/06/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/27/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
06/29/2022Lighting in dwelling unitsZiv Zamirenergy_progress
06/29/2022Fire-Resistant Penetrations and JointsJACK GREENspecial
06/29/2022Fire-Resistance Rated ConstructionZiv Zamirprogress
06/29/2022Energy Code Compliance InspectionsZiv Zamirprogress
06/29/2022FinalZiv Zamirprogress
06/28/2022Lighting in dwelling unitsZiv Zamirenergy_progress
06/28/2022Fire-Resistant Penetrations and JointsJACK GREENspecial
06/28/2022Energy Code Compliance InspectionsZiv Zamirprogress
06/28/2022FinalZiv Zamirprogress
06/28/2022Fire-Resistance Rated ConstructionZiv Zamirprogress
11/05/2018FinalJULIO SALCEDO-FERNANDEZprogress
▾Documents — 106 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/29/2026Q00000559-I1Request digital key ↗
08/28/2026Q00096274-I1Request digital key ↗
08/27/2026Q00566171-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits14
▸BISPLAN / WORK APPROVAL APPLICATION9
03/20/2020421696953Open ↗
11/30/2018421576627Open ↗
11/28/2018421696953Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION5
11/26/2018421696953Open ↗
08/03/2018421576627Open ↗
07/27/2018421576627Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications28
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/27/2026Q00566171-I1Open ↗
08/26/2026Q00650159-I1Open ↗
08/26/2026Q00650159-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
08/27/2026Q00096274-I1Open ↗
08/27/2026Q00650154-P1Open ↗
08/27/2026Q00650154-P1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
04/18/2019421576627Open ↗
11/28/2018421696953Open ↗
08/03/2018421576627Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026Q00650154-P1Open ↗
08/26/2026Q00650154-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
11/28/2018421696953Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
09/22/2015440242373Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
11/28/2018421696953Open ↗
▸Trade Schedules & Equipment2
▸BISFA - FDNY APPROVAL : FD-FAA1
05/25/2017440242373Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
11/17/2017421576627Open ↗
▸Safety & Tenant Protection3
▸BISTenant Protection Plan and Notes3
11/28/2018421696953Open ↗
11/17/2017421576627Open ↗
04/14/2017440242373Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/27/2026Q00566171-I1Open ↗
08/26/2026Q00650159-P1Open ↗
08/26/2026Q00650159-I1Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
11/28/2018421696953Open ↗
11/17/2017421576627Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
04/18/2019421576627Open ↗
11/28/2018421696953Open ↗
08/03/2018421576627Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
06/23/2020421696953Open ↗
04/18/2019421576627Open ↗
06/21/2018440242373Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
06/23/2020421696953Open ↗
09/22/2015440242373Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00566171-I1Open ↗
08/13/2026Q00650154-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
06/23/2020421696953Open ↗
09/22/2015440242373Open ↗
▸Approvals, Objections & Sign-offs5
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
06/23/2020421696953Open ↗
05/02/2019421576627Open ↗
07/12/2018440242373Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION1
07/31/2018421576627Open ↗
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT10
06/23/2020421696953Open ↗
03/20/2020421696953Open ↗
04/18/2019421576627Open ↗
Showing 3 of 10 on file for this type
▸Filing & Intake Forms12
▸BISADDITIONAL INFORMATION7
06/22/2020421696953Open ↗
06/10/2020421696953Open ↗
11/30/2018421576627Open ↗
Showing 3 of 7 on file for this type
▸BISEFILING COVER SHEET2
11/28/2018421696953Open ↗
11/17/2017421576627Open ↗
▸BISBOROUGH INTAKE FORM2
06/21/2018440242373Open ↗
03/26/2018440242373Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
09/22/2015440242373Open ↗