💬 Discuss this project
1920Year Built
2.5Stories
S1Building Class
R4AZoning
3,350 sfGross Floor Area
2Units
Primarily 1 family with 1 store or office · 4,373 sf lot · 0.77 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 2Unit PHAUnder Construction5p · 1 filing · 20 docs
Floor 1Under Construction3p · 1 filing · 20 docs
CellarUnder Construction12p · 1 filing · 20 docs
BasementUnder Construction15p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/03/2016$1.8M—76TH STREET IRROVOCABLE TRUST → Private party$530/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Shenker Architect409/17/2026
Steel Core Engineering110/20/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Shenker Architects303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
New System ConstructionGeneral Contractor104/09/2026
U.A. BuildersGeneral Contractor109/07/2026
Amm General ContractingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Shenker Architect756309/17/2026
Steel Core Engineering PL1098110/20/2025
Building Lifecycle
All (49)Filed (5)Permit Issued (3)Inspection (3)Objection (8)Special Inspection (30)
10/13/2026
Objection raised — Other
10/13/2026
Objection raised — Other
10/13/2026
Objection raised — Other
10/13/2026
Objection raised — Other
10/13/2026
Objection raised — Other
10/13/2026
Objection raised — Other
09/17/2026
Filed — Alteration CO
PROPOSED INSTALLATION OF PLUMBING FIXTURES AS PER PLAN IN CONJUNCTION WITH GC APPLICATION #B01184779-I1.
B01184779-P2
09/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Lighting controls
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Metering
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Exterior lighting power
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Fenestration air leakage
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Interior lighting power
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Fenestration areas
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Air barrier - visual inspection
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Fire-Resistance Rated Construction
DMITRIY SHENKER
09/14/2026
Special inspection requirement — Energy Code Compliance Inspections
DMITRIY SHENKER
08/04/2026
Permit issued — Mechanical Systems
B01184779-S2-MS
04/21/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/17/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/06/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/06/2025
Permit issued — Plumbing
B01184779-S1-PL
10/20/2025
Filed — Alteration CO
PROPOSED INSTALLATION OF PLUMBING FIXTURES AS PER PLAN IN CONJUNCTION WITH GC APPLICATION #B01184779-I1.
B01184779-S2
10/19/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Alexander Sheyman
10/19/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alexander Sheyman
10/19/2025
Special inspection requirement — Mechanical Systems
Alexander Sheyman
10/19/2025
Special inspection requirement — Final
Alexander Sheyman
10/19/2025
Special inspection requirement — HVAC-R and service water heating equipment
Alexander Sheyman
10/19/2025
Special inspection requirement — HVAC-R and service water heating system controls
Alexander Sheyman
10/19/2025
Special inspection requirement — Permanent certificate
Alexander Sheyman
10/19/2025
Special inspection requirement — Maintenance information
Alexander Sheyman
09/24/2025
Filed — Alteration CO
PROPOSED INSTALLATION OF PLUMBING FIXTURES AS PER PLAN IN CONJUNCTION WITH GC APPLICATION #B01184779-I1.
B01184779-P1
09/24/2025
Special inspection requirement — HVAC-R and service water heating system controls
DMITRIY SHENKER
09/24/2025
Special inspection requirement — HVAC-R and service water heating equipment
DMITRIY SHENKER
09/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
DMITRIY SHENKER
09/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
DMITRIY SHENKER
09/24/2025
Special inspection requirement — Energy Code Compliance Inspections
DMITRIY SHENKER
09/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/23/2025
Special inspection requirement — Energy Code Compliance Inspections
09/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
09/23/2025
Special inspection requirement — HVAC-R and service water heating equipment
09/23/2025
Special inspection requirement — HVAC-R and service water heating system controls
07/09/2025
Permit issued — General Construction
B01184779-I1-GC
04/25/2025
Objection resolved — Addressed
04/11/2025
Special inspection requirement — Fire-Resistance Rated Construction
DMITRIY SHENKER
04/02/2025
Objection raised — Scope
03/31/2025
Filed — Alteration CO
PROPOSED INSTALLATION OF PLUMBING FIXTURES AS PER PLAN IN CONJUNCTION WITH GC APPLICATION #B01184779-I1.
B01184779-I1
03/31/2025
Filed — Alteration CO
PROPOSED INSTALLATION OF PLUMBING FIXTURES AS PER PLAN IN CONJUNCTION WITH GC APPLICATION #B01184779-I1.
B01184779-S1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedU.A. Builders08/04/2026
DOB NOWPlumbingSigned-offAmm General Contracting11/06/2025
DOB NOWGeneral ConstructionPermit IssuedNew System Construction07/09/2025
1 project · most recent 09/17/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
09/17/2026Permit IssuedU.A. BuildersHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MXZ-3D24NLHZ 23,600 BTU · Heat Pump Outdoor ×12
1 project · most recent 09/17/2026
Gas Water/Sanitary
FiledStatusContractorScope
09/17/2026Signed-offAmm General ContractingGas, Water/Sanitary
1 project · most recent 06/26/2026
General Wiring
FiledStatusContractorScope
06/26/2026CompleteBlu Electrical ServicesGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
04/21/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/17/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/06/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
09/14/2026Fire-Resistant Penetrations and JointsDMITRIY SHENKERspecial
09/14/2026Lighting controlsDMITRIY SHENKERenergy_progress
09/14/2026MeteringDMITRIY SHENKERenergy_progress
09/14/2026Fenestration and door U-factor and product ratingsDMITRIY SHENKERenergy_progress
09/14/2026Exterior lighting powerDMITRIY SHENKERenergy_progress
09/14/2026Fenestration air leakageDMITRIY SHENKERenergy_progress
09/14/2026Interior lighting powerDMITRIY SHENKERenergy_progress
09/14/2026Fenestration areasDMITRIY SHENKERenergy_progress
09/14/2026Air barrier - visual inspectionDMITRIY SHENKERenergy_progress
09/14/2026Fire-Resistance Rated ConstructionDMITRIY SHENKERprogress
09/14/2026Energy Code Compliance InspectionsDMITRIY SHENKERprogress
10/19/2025HVAC-R and service water piping design and insulationAlexander Sheymanenergy_progress
10/19/2025Fire-Resistant Penetrations and JointsAlexander Sheymanspecial
10/19/2025Mechanical SystemsAlexander Sheymanspecial
10/19/2025FinalAlexander Sheymanprogress
10/19/2025HVAC-R and service water heating equipmentAlexander Sheymanenergy_progress
10/19/2025HVAC-R and service water heating system controlsAlexander Sheymanenergy_progress
10/19/2025Permanent certificateAlexander Sheymanenergy_progress
10/19/2025Maintenance informationAlexander Sheymanenergy_progress
09/24/2025HVAC-R and service water heating system controlsDMITRIY SHENKERenergy_progress
09/24/2025HVAC-R and service water heating equipmentDMITRIY SHENKERenergy_progress
09/24/2025HVAC-R and service water piping design and insulationDMITRIY SHENKERenergy_progress
09/24/2025Fire-Resistant Penetrations and JointsDMITRIY SHENKERspecial
09/24/2025Energy Code Compliance InspectionsDMITRIY SHENKERprogress
09/23/2025Fire-Resistant Penetrations and Joints—special
Latest 25 of 40.
▾Documents — 32 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/20/2026B01184779-P1Request digital key ↗
08/20/2026B01184779-S1Request digital key ↗
08/20/2026B01184779-S2Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications19
▸DOB NOWProgress Inspector Seal & Signature10
10/04/2026B01184779-P2Open ↗
10/04/2026B01184779-P2Open ↗
10/04/2026B01184779-P2Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
10/04/2026B01184779-P2Open ↗
08/20/2026B01184779-S1Open ↗
08/20/2026B01184779-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
10/04/2026B01184779-P2Open ↗
08/25/2026B01184779-I1Open ↗
08/24/2026B01184779-S2Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
10/04/2026B01184779-P2Open ↗
08/14/2026B01184779-I1Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
10/04/2026B01184779-P2Open ↗
08/20/2026B01184779-S1Open ↗
08/20/2026B01184779-P1Open ↗
Showing 3 of 5 on file for this type
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
10/04/2026B01184779-P2Open ↗
08/14/2026B01184779-I1Open ↗