| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK UNIVERSITY | 59 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MATIZ ARCHITECTURE AND DESIGN | 2 | 05/28/2026 |
| POLISE CONSULTING ENGINEER | 3 | 06/24/2025 |
| RIMKUS | 1 | 06/23/2023 |
| POLISE CONSULTING ENGINEERS DPC | 2 | 06/14/2023 |
| NICOLAS BARATTO ARCHITECT P.C. | 2 | 06/13/2023 |
| 360 ENGINEERING P.C. | 1 | 06/02/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| BURNHAM NATIONWIDE INC | 9 | 03/21/2026 |
| YAO W GUO ARCHITECT, PC | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DPH PLUMBING & HTG CORP | Plumbing | 4 | 07/08/2026 |
| SPK/LEWIS CONSTRUCTION LL | General Contractor | 4 | 06/28/2026 |
| BROSNA CONSTRUCTION CORPO | General Contractor | 3 | 07/08/2026 |
| MADZY, JOHN | Electrical | 1 | 03/21/2026 |
| MARANGELLI, GAETANO | Electrical | 1 | 03/21/2026 |
| MARSON CONTRACTING CO,INC | Electrical | 1 | 03/21/2026 |
| MORONEY, THOMAS | Electrical | 1 | 03/21/2026 |
| MOSKOWITZ STUART | Electrical | 1 | 03/21/2026 |
| NIKOLL DUSHI | Electrical | 1 | 03/21/2026 |
| STUART MOSKOWITZ | Electrical | 1 | 03/21/2026 |
| TUOHY, PATRICK | Electrical | 1 | 03/21/2026 |
| ANESIS SERVICES CORP | Fire Protection | 1 | 07/08/2026 |
| BEDROCK MECHANICAL INC | Fire Protection | 1 | 07/08/2026 |
| PSI PARTNERS, LLC | Fire Protection | 1 | 07/08/2026 |
| EDIFICE DESIGN INC | General Contractor | 1 | 07/08/2026 |
| PJP INSTALLERS INC | General Contractor | 1 | 07/08/2026 |
| HUDSON PLMBING & MCH, LLC | Plumbing | 1 | 07/08/2026 |
| CONDUCTOR ELECL SVCS INC | Electrical | 1 | 03/22/2026 |
| HYDROKINETIC PLBG & HTG I | Plumbing | 1 | 07/08/2026 |
| DONOVAN, TIMOTHY | Electrical | 1 | 03/21/2026 |
| J.G GENERAL WELDING | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RYAN SPECIAL ENGINEERING | 2018 | 5 | 05/28/2026 |
| FRAMEWORK ENGINEERING PC | 8217 | 1 | 06/23/2023 |
| RIMKUS NEW YORK, PLLC | 8123 | 1 | 06/23/2023 |
| SKYLINE ENGINEERING, PLLC | 267 | 4 | 06/14/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | SPK/LEWIS CONSTRUCTION LL | 06/22/2026 |
| DOB NOW | General Construction | Permit Issued | SPK/LEWIS CONSTRUCTION LL | 06/22/2026 |
| DOB NOW | Sprinklers | Permit Issued | BEDROCK MECHANICAL INC | 06/05/2026 |
| DOB NOW | Sprinklers | Permit Issued | MORA FIRE PROTECTION LLC | 07/01/2025 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 07/01/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | SPK/LEWIS CONSTRUCTION LL | 06/30/2025 |
| DOB NOW | General Construction | Permit Issued | SPK/LEWIS CONSTRUCTION LL | 06/30/2025 |
| DOB NOW | General Construction | Signed-off | EDIFICE DESIGN INC | 07/17/2023 |
| DOB NOW | Sprinklers | Signed-off | THOMAS FAY | 06/26/2023 |
| DOB NOW | General Construction | Signed-off | BROSNA CONSTRUCTION CORPO | 06/26/2023 |
| DOB NOW | Plumbing | Signed-off | HYDROKINETIC PLBG & HTG I | 06/24/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 06/05/2023 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 06/18/2022 |
| DOB NOW | General Construction | Signed-off | BROSNA CONSTRUCTION CORPO | 06/17/2022 |
| BIS | PL | ISSUED | PROTO P & H SERVICES CORP | 09/30/2016 |
| BIS | OT | ISSUED | IDEAL INTERIORS GROUP LLC | 09/15/2016 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 07/14/2016 |
| BIS | OT | ISSUED | SKANSKA USA BUILDING, INC | 06/15/2016 |
| BIS | SP | ISSUED | PACE PLUMBING CORP | 06/02/2016 |
| BIS | SP | ISSUED | PACE PLUMBING CORP | 04/18/2016 |
| BIS | MH | ISSUED | PRP MECHANICAL CONTRACTOR INC. | 09/17/2013 |
| BIS | OT | ISSUED | LRP CONSTRUCTION CORP | 01/14/2013 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 08/30/2012 |
| BIS | EQ | ISSUED | SKYLINE RESTORATION INC | 06/19/2012 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 06/18/2012 |
| BIS | EQ | ISSUED | SKYLINE RESTORATION INC | 03/16/2012 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 01/17/2012 |
| BIS | OT | ISSUED | NEW YORK FLAG AND POLE CO | 01/11/2012 |
| BIS | EQ | ISSUED | SKYLINE RESTORATION INC | 07/21/2011 |
| BIS | OT | ISSUED | SKANSKA USA BUILDING, INC | 12/03/2010 |
| BIS | OT | ISSUED | SKANSKA USA BUILDING, INC | 12/03/2010 |
| BIS | PL | ISSUED | LAB PLBG & HTG CO INC | 06/09/2006 |
| BIS | PL | ISSUED | PAR PLUMBING CO., INC | 11/10/2005 |
| BIS | OT | ISSUED | GODSIL CONSTRUC. INC | 10/25/2005 |
| BIS | PL | ISSUED | NEPTUNE MECHANICAL | 05/24/2002 |
| BIS | OT | ISSUED | ON-PAR CONTRACTING | 05/01/2002 |
| BIS | OT | ISSUED | ON-PAR CONTRACTING | 05/01/2002 |
| BIS | SP | ISSUED | DYNAMIC PLBNG & SPRKR COR | 03/26/2002 |
| BIS | MH | ISSUED | MKG CONSTRUCTION | 03/08/2002 |
| BIS | OT | ISSUED | MKG CONSTRUCTION | 03/08/2002 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | BEDROCK MECHANICAL INC | 32 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Signed-off | DPH PLUMBING & HTG CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2025 | Permit Issued | A.S.K. ELECTRICAL CORP | General Wiring |
| 05/19/2025 | Complete | CAPUTEK ELEC'L SERVICES, | — |
| 04/10/2025 | Permit Issued | LINTECH ELECTRIC, INC | 6 meters, 4 new_meters |
| 10/18/2023 | Complete | CONDUCTOR ELECL SVCS INC | General Wiring |
| 07/15/2023 | Complete | WCK ELECTRIC CORP. | — |
| 07/12/2022 | Complete | CONDUCTOR ELECL SVCS INC | — |
| 07/12/2022 | Complete | CONDUCTOR ELECL SVCS INC | — |
| 06/29/2022 | Complete | CONDUCTOR ELECL SVCS INC | — |
| 04/06/2022 | Complete | MHO'S ELECTRIC CORP | General Wiring |
| 07/28/2020 | Permit Issued | COMMERCE ELECL CONTRG COR | — |
| 03/26/2020 | Complete | MHO'S ELECTRIC CORP | — |
| 02/08/2019 | Permit Issued | MATROS AUTOMATED ELEC'L C | — |
| 09/19/2018 | Complete | RIGID ELECTRIC, INC. | Boiler Controls |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | SPK/LEWIS CONSTRUCTION LL | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/09/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/11/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/08/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/26/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/29/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/25/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/24/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/24/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/16/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/16/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/20/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/02/2026 | Tenant Protection Plan Compliance | William Ryan | special |
| 06/02/2026 | Final | William Ryan | progress |
| 06/02/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 03/10/2026 | Final | William Ryan | progress |
| 03/10/2026 | Tenant Protection Plan Compliance | William Ryan | special |
| 03/10/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 06/10/2025 | Tenant Protection Plan Compliance | William Ryan | special |
| 06/10/2025 | Tenant Protection Plan Compliance | William Ryan | special |
| 05/30/2025 | Mechanical Systems | William Ryan | special |
| 05/30/2025 | Final | William Ryan | progress |
| 05/30/2025 | Sprinkler Systems | William Ryan | special |
| 05/15/2023 | Post-installed Anchors | Matthew Wavro | special |
| 05/15/2023 | Tenant Protection Plan Compliance | Matthew Wavro | special |
| 05/15/2023 | Fire-Resistant Penetrations and Joints | Matthew Wavro | special |
| 05/15/2023 | Final | Nicolas Baratto | progress |
| 05/15/2023 | Energy Code Compliance Inspections | Nicolas Baratto | progress |
| 05/24/2022 | Fire-Resistant Penetrations and Joints | Matthew Wavro | special |
| 05/24/2022 | Fire-Resistant Penetrations and Joints | Matthew Wavro | special |
| 05/24/2022 | Lighting in dwelling units | Matthew Wavro | energy_progress |
| 05/24/2022 | Energy Code Compliance Inspections | Matthew Wavro | progress |
| 05/24/2022 | Final | Matthew Wavro | progress |