| Owner | Filings | Most Recent |
|---|---|---|
| CELEBRATION | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 2 | 11/06/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN SOLAR ELECTL CORP | Electrical | 1 | 03/22/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 2 | 11/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 09/16/2024 |
| BIS | — | ISSUED | CELEBRATION | 09/11/2002 |
| BIS | PL | ISSUED | DUO PLUMBING & HTG CORP. | 02/05/2002 |
| BIS | — | ISSUED | CELEBRATION & SKYLINE NEW HOMES | 01/28/2002 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/12/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2024 | Signed-off | SUNRUN INSTALLATION SVC | 14 panels, 5.74 kw, 295.9 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/07/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 11/07/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 11/07/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 11/07/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 11/07/2024 | Final | Walid Abdulla | progress |
| 10/31/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 10/31/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 10/31/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 10/31/2024 | Final | Walid Abdulla | progress |
| 10/31/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |