← Back
Predominantly retail with other uses
248 WEST BROADWAY
MANHATTAN · BIN 1002172
💬 Discuss this project
1915Year Built
8Stories
K4Building Class
C6-2AZoning
35,057 sfGross Floor Area
8Units
LL97 Covered27 Open Violations 23 unresolved · 4 paperwork only ▸FISP: SWARMPFDNY Report ↗
Predominantly retail with other uses · Owner of record: 250 W BWAY RLTY CORP · 3,964 sf lot · 8.84 FAR built · Flood zone X500
Locations of Work
ArchitectureMechanicalPlumbing
Roof1p · 1 filing · 3 docs
Floor 61p · 1 filing · 8 docs
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Cellar2p · 2 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
250 W BWAY RLTY CORP103/22/2026
250 WEST BROADWAY REALTY CORP.5903/22/2026
MGR103/22/2026
250 BROADWAY REALTY CORP.103/22/2026
INFINTY CONTACTING INC103/22/2026
102 106 WARREN ST CP203/22/2026
JOVIL CONTRACTING303/21/2026
250 BWEST BROADWAY REALTY403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SCHERER DESIGN GROUP106/28/2024
NIKOLAI KATZ ARCHITECT108/30/2023
BAZINI ENGINEERING, P.C.207/24/2023
CBRE HEERY, INC.105/30/2023
ROYAL ENGINEERING, P.C202/12/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CONSTRUCTION PERMIT SERVICES103/21/2026
A1 EXPEDITING SERVICE CORP.103/21/2026
J A EXPEDITING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PHOENIX SUTTON STR INCGeneral Contractor707/08/2026
P.H. WORKS INCPlumbing607/08/2026
GANNON CONTRACTING LLCGeneral Contractor203/21/2026
JACO MECHANICAL INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SCHERER DESIGN GROUP7921106/28/2024
NIKOLAI KATZ ARCHITECT3482108/30/2023
BAZINI ENGINEERING, P.C.1808207/24/2023
ETI CONSULTANTS LLC7694105/30/2023
Building Lifecycle
All (112)Filed (7)Permit Issued (13)Signed Off (4)Facade (FISP) (16)Violation (60)Inspection (4)Objection (2)Special Inspection (6)
11/17/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
11/17/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/29/2025
Inspection — No Access-Final PL - Up to 3 Requested Floors
No Access
View inspection ↗
10/28/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
07/23/2025
Permit issued — Boiler Equipment
M00856039-I1-BE
07/23/2025
Permit issued — Plumbing
M00856056-I1-PL
09/09/2024
Signed off — Alteration
Removal and installation of interior non-bearing partitions and related finishes as per plans filed herewith. No change in use, egress or occupancy.
M00835562-I1
07/29/2024
Permit issued — Boiler Equipment
M00856039-I1-BE
07/26/2024
Permit issued — Plumbing
M00856056-I1-PL
07/15/2024
Objection resolved — Addressed
07/12/2024
Objection raised — Scope
06/28/2024
Filed — Alteration
Replace two existing air handlers in equipment shelter on roof. Replace related condensers on the roof. No change in use, egress, or occupancy.
M01040255-I1
12/19/2023
Signed off — Alteration
M00913544-I1
09/12/2023
Permit issued — Mechanical Systems
M00913544-I1-MS
08/30/2023
Filed — Alteration
M00913544-I1
08/23/2023
Permit issued — General Construction
M00835562-I1-GC
07/28/2023
Permit issued — Plumbing
M00856056-I1-PL
07/27/2023
Permit issued — Boiler Equipment
M00856039-I1-BE
07/24/2023
Filed — Alteration
CONNECT TO EXISTING GAS PIPING FOR REPLACEMENT BOILER AND GAS BURNER AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00856056-I1
07/24/2023
Filed — Alteration
M00856039-I1
07/12/2023
Special inspection requirement — HVAC-R and service water heating equipment
Joseph Bazini
05/30/2023
Filed — Alteration
Removal and installation of interior non-bearing partitions and related finishes as per plans filed herewith. No change in use, egress or occupancy.
M00835562-I1
05/13/2023
Special inspection requirement — Tenant Protection Plan Compliance
ANTHONY MUSUMECI
04/06/2023
Special inspection requirement — Tenant Protection Plan Compliance
Joseph Bazini
04/06/2023
Special inspection requirement — Tenant Protection Plan Compliance
Joseph Bazini
03/16/2023
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
ANTHONY MUSUMECI
02/27/2023
Special inspection requirement — Final
LINDA KANOSKI
02/02/2023
Cycle 9 facade report submitted
02/02/2023
Cycle 9 facade report signed — SWARMP
12/15/2022
Cycle 9 facade inspection completed
03/23/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/23/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/06/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/06/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/05/2019
Signed off — Alteration
M00018817-I1
11/13/2018
Cycle 8 facade report signed — SAFE
11/09/2018
Cycle 8 facade inspection completed
10/29/2018
Permit issued — Sidewalk Shed
M00018817-I1-SH
10/15/2018
Signed off — Alteration
INSTALLATION OF TEMPORARY 90' HIGH PIPE SCAFFOLD (OFF SHED) FOR FACADE REPAIR WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY,PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.
M00018821-I1
10/03/2018
Violation issued (ECB, closed)
Construction
09/27/2018
Cycle 8 facade report submitted
03/23/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/23/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/16/2018
Permit issued — Sidewalk Shed
M00018817-I1-SH
03/14/2018
Permit issued — Supported Scaffold
M00018821-I1-SF
02/15/2018
Cycle 8 facade report submitted
02/15/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/14/2018
Cycle 8 facade inspection completed
02/14/2018
Cycle 8 facade report signed — UNSAFE
02/13/2018
Permit issued — Supported Scaffold
M00018821-I1-SF
02/13/2018
Permit issued — Sidewalk Shed
M00018817-I1-SH
02/12/2018
Filed — Alteration
M00018817-I1
02/12/2018
Filed — Alteration
INSTALLATION OF TEMPORARY 90' HIGH PIPE SCAFFOLD (OFF SHED) FOR FACADE REPAIR WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY,PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.
M00018821-I1
01/26/2018
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/26/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/17/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/17/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
01/03/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/03/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Latest 60 of 112 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offP.H. WORKS INC07/23/2025
DOB NOWPlumbingSigned-offP.H. WORKS INC07/23/2025
DOB NOWBoiler EquipmentSigned-offP.H. WORKS INC07/29/2024
DOB NOWPlumbingSigned-offP.H. WORKS INC07/26/2024
DOB NOWMechanical SystemsSigned-offJACO MECHANICAL09/12/2023
DOB NOWGeneral ConstructionSigned-offGANNON CONTRACTING LLC08/23/2023
DOB NOWPlumbingSigned-offP.H. WORKS INC07/28/2023
DOB NOWBoiler EquipmentSigned-offP.H. WORKS INC07/27/2023
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC10/29/2018
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC03/16/2018
DOB NOWSupported ScaffoldSigned-offPHOENIX SUTTON STR INC03/14/2018
DOB NOWSupported ScaffoldSigned-offPHOENIX SUTTON STR INC02/13/2018
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC02/13/2018
BISMHISSUEDGT DEVELOPMENT LLC07/29/2019
BISSPISSUEDUNLIMITED PLG SOLUTIONS08/08/2018
BISMHISSUEDA.W. & S. CONSTRUCTION CO06/28/2018
BISPLISSUEDLCS PLUMBING&CONSULT INC05/14/2018
BISOTISSUEDJRR CONTRACTING INC03/28/2018
BISOTISSUEDA.W. & S. CONSTRUCTION CO02/15/2018
BISOTISSUEDCEL TECH ELECTRIC INC01/09/2015
BISOTISSUEDCEL TECH ELECTRIC INC10/30/2014
BISOTISSUEDCEL TECH ELECTRIC INC08/08/2013
BISOTISSUEDDAVRIAL ENTERPRISES INC10/09/2012
BISOTISSUEDPROFILE CONTRACTING INC06/17/2010
BISMHISSUEDPROFILE CONTRACTING INC06/17/2010
BISOTISSUEDPROFILE CONTRACTING INC05/29/2009
BISMHISSUEDPROFILE CONTRACTING INC05/29/2009
BISSPISSUEDA.R.L. PLMBNG & HTG LLC05/14/2009
BISMHISSUEDARETE DEVELOPMENT INC05/13/2009
BISPLISSUEDDEWATER PLBG & HTG, LLC12/08/2008
BISOTISSUEDPROFILE CONTRACTING INC11/18/2008
BISMHISSUEDPROFILE CONTRACTING INC11/18/2008
BISOTISSUEDJRS BOILER INC07/03/2008
BISPLISSUEDD.D.S. MECH PBG&HTG CORP06/03/2008
BISOTISSUEDINTERBORO SIGN & MAINTENANCE11/29/2007
BISOTISSUEDVILES CONTRACTING CORP09/24/2007
BISEQISSUEDJOVIL CONTRACTING CORP09/21/2007
BISPLISSUEDWARD MECHANICAL B09/07/2007
BISBLISSUEDWARD MECHANICAL B09/07/2007
BISOTISSUEDVILES CONTRACTING CORP08/30/2007
+ 21 more permits on file
1 project · most recent 06/28/2024
Air Conditioning Systems
FiledStatusContractorScope
06/28/2024——Air Conditioning Systems
1 project · most recent 07/24/2023
Gas
FiledStatusContractorScope
07/24/2023Signed-offP.H. WORKS INCGas
4 projects · most recent 06/26/2026
General Wiring
FiledStatusContractorScope
06/26/2026Permit IssuedSCHWARTZ ELEC. CONTR'S INGeneral Wiring
01/09/2019Permit IssuedCENTENNIAL ELEVATOR INDUSGeneral Wiring
04/13/2018CompleteQUEUE ELEC'L CONTRS, INCGeneral Wiring
02/09/2018CompleteELPO ELECTRICAL CONTG INC—
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
11/17/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/17/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/29/2025No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
10/28/2025Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
07/12/2023HVAC-R and service water heating equipmentJoseph Bazinienergy_progress
05/13/2023Tenant Protection Plan ComplianceANTHONY MUSUMECIspecial
04/06/2023Tenant Protection Plan ComplianceJoseph Bazinispecial
04/06/2023Tenant Protection Plan ComplianceJoseph Bazinispecial
03/16/2023Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)ANTHONY MUSUMECIspecial
02/27/2023FinalLINDA KANOSKIprogress
▾Documents — 201 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
09/06/2026M00018817-I1Request digital key ↗
09/06/2026M00018821-I1Request digital key ↗
08/31/2026M00835562-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits34
▸BISWORK PERMIT APPLICATION23
07/29/2019123706445Open ↗
08/08/2018123256449Open ↗
05/15/2018123256449Open ↗
Showing 3 of 23 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION11
07/03/2019123706445Open ↗
09/14/2018123256449Open ↗
11/21/2017123256449Open ↗
Showing 3 of 11 on file for this type
▸Seals & Professional Certifications39
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION22
08/16/2019123706445Open ↗
08/16/2019123706445Open ↗
02/22/2019123256449Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
09/06/2026M00018817-I1Open ↗
09/06/2026M00018821-I1Open ↗
08/31/2026M00835562-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026M00856039-I1Open ↗
09/01/2026M00856056-I1Open ↗
08/26/2026M00835562-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
07/03/2019123706445Open ↗
06/27/2008110225916Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026M00856039-I1Open ↗
08/26/2026M00835562-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/03/2019123706445Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
06/27/2008110225916Open ↗
▸Trade Schedules & Equipment18
▸BISSELF-CERT PLUMBING NOTICE6
07/30/2009110329154Open ↗
07/01/2009110329154Open ↗
05/22/2009110329154Open ↗
Showing 3 of 6 on file for this type
▸BISEQUIPMENT USE PERMITS4
08/07/2019123706445Open ↗
08/07/2019123706445Open ↗
04/09/2019123256449Open ↗
Showing 3 of 4 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT3
08/07/2019123706445Open ↗
07/03/2019123706445Open ↗
04/09/2019123256449Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
09/14/2018123256449Open ↗
11/21/2017123256449Open ↗
▸BISSCHEDULE B - PLUMBING2
08/29/2008110329154Open ↗
04/14/2008110129780Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
07/10/2009110329154Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes4
07/03/2019123706445Open ↗
12/20/2017123256449Open ↗
11/22/2017123256449Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos22
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
02/28/2012120987931Open ↗
08/29/2008110329154Open ↗
06/27/2008110225916Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/31/2026M00835562-I1Open ↗
08/29/2026M00856056-I1Open ↗
08/29/2026M00913544-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWOER: Notice to Proceed5
09/06/2026M00018821-I1Open ↗
08/13/2026M00835562-I1Open ↗
08/13/2026M00018817-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
11/22/2017123256449Open ↗
09/05/2017123110365Open ↗
07/01/2013121690544Open ↗
▸DOB NOWOER: Notice of Satisfaction3
09/06/2026M00018821-I1Open ↗
08/13/2026M00835562-I1Open ↗
08/13/2026M00018817-I1Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
11/09/2017123110365Open ↗
▸Energy Compliance18
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS12
08/16/2019123706445Open ↗
07/29/2019123706445Open ↗
07/03/2019123706445Open ↗
Showing 3 of 12 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
02/22/2019123256449Open ↗
10/12/2018123256449Open ↗
10/04/2018123256449Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections1
07/01/2013121690544Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: PILE DRIVING1
02/22/2019123256449Open ↗
▸Approvals, Objections & Sign-offs21
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST10
08/16/2019123706445Open ↗
02/22/2019123256449Open ↗
02/22/2019123256449Open ↗
Showing 3 of 10 on file for this type
▸BISADMINISTRATIVE OBJECTIONS6
07/01/2013121690544Open ↗
02/28/2012120987931Open ↗
08/29/2008110329154Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
08/16/2019123706445Open ↗
02/22/2019123256449Open ↗
09/28/2018123110365Open ↗
Showing 3 of 5 on file for this type
▸Cost, Insurance & Ownership18
▸BISCOST AFFIDAVIT18
08/16/2019123706445Open ↗
07/03/2019123706445Open ↗
02/22/2019123256449Open ↗
Showing 3 of 18 on file for this type
▸Filing & Intake Forms15
▸BISBOROUGH INTAKE FORM6
08/16/2019123706445Open ↗
02/22/2019123256449Open ↗
09/28/2018123110365Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET6
11/21/2017123256449Open ↗
09/05/2017123110365Open ↗
07/01/2013121690544Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION3
10/25/2018123256449Open ↗
09/19/2018123256449Open ↗
11/03/2014121690544Open ↗
▸Other Documents4
▸BISCOMMUNITY BOARD NOTIFICATION1
02/22/2019123256449Open ↗
▸BISENVIRONMENTAL1
06/11/2012120987931Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
08/07/2019123706445Open ↗
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
08/13/2026M00018817-I1Open ↗