| Owner | Filings | Most Recent |
|---|---|---|
| HUNT B CONSTRUCTION | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/22/2024 | $1.3M | — | DUMONT 919 INC. → Private party | $532/sf building |
| 06/14/2022 | $652K | — | — → — | $272/sf building |
| 05/25/2016 | $470K | — | Private party → Private party | $196/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 08/08/2024 |
| TABRIZ GROUP ENTERPRISES | 2 | 11/28/2023 |
| TABRIZ DESIGN GROUP | 3 | 10/25/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| TABRIZ DESIGN GROUP | 4 | 03/21/2026 |
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HUNT B CONSTRUCTION INC | General Contractor | 13 | 07/08/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 2 | 03/21/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 08/08/2024 |
| TABRIZ GROUP ENTERPRISES | 3275 | 4 | 11/28/2023 |
| TRIANGLE INSPECTION & TES | 7495 | 2 | 10/25/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 08/13/2024 |
| DOB NOW | Foundation | Signed-off | HUNT B CONSTRUCTION INC | 12/19/2023 |
| DOB NOW | Earth Work | Signed-off | HUNT B CONSTRUCTION INC | 12/19/2023 |
| DOB NOW | Structural | Signed-off | HUNT B CONSTRUCTION INC | 12/19/2023 |
| DOB NOW | Plumbing | Signed-off | HORBRIDGE PLUMBING & HEAT | 04/19/2023 |
| DOB NOW | Construction Fence | Signed-off | HUNT B CONSTRUCTION INC | 03/29/2023 |
| DOB NOW | Foundation | Permit Issued | HUNT B CONSTRUCTION INC | 03/22/2023 |
| DOB NOW | Construction Fence | Signed-off | HUNT B CONSTRUCTION INC | 10/14/2022 |
| DOB NOW | Construction Fence | Signed-off | HUNT B CONSTRUCTION INC | 07/18/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/28/2023 | Signed-off | HUNT B CONSTRUCTION INC | Air Conditioning Systems, Ventilation Systems | Cooling Comfort Aire RSG1448S1P, GUH955A 6,000 BTU · Furnace ×4 Ventilation Delta Breeze SLM70 70 CFM · Exhaust Fan ×5 Glacier BCSQ130SS 300 CFM · Kitchen Exhaust ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/08/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 04/18/2023 | Complete | AYYUB ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/28/2023 | Signed-off | HUNT B CONSTRUCTION INC | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/16/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/29/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 12/29/2023 | Pass-Final Fence Non-Directive 14 | Pass | View ↗ |
| 12/20/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/23/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/23/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/23/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/23/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/23/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/05/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 08/05/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 08/05/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 08/05/2024 | Final | Walid Abdulla | progress |
| 08/05/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 12/08/2023 | Structural Stability – Alterations of existing buildings | BAKHTIAR SHAMLOO | special |
| 12/08/2023 | Fire-Resistant Penetrations and Joints | BAKHTIAR SHAMLOO | special |
| 12/08/2023 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 12/08/2023 | Masonry | BAKHTIAR SHAMLOO | special |
| 12/08/2023 | Concrete - Cast-In-Place | BAKHTIAR SHAMLOO | special |
| 12/08/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | BAKHTIAR SHAMLOO | special |
| 12/08/2023 | Excavations - Sheeting, Shoring, and Bracing | BAKHTIAR SHAMLOO | special |
| 12/08/2023 | Mechanical Systems | BAKHTIAR SHAMLOO | special |
| 12/08/2023 | Final | HARI SONI | progress |
| 12/08/2023 | Structural Wood Frame | BAKHTIAR SHAMLOO | progress |
| 12/08/2023 | Footing and Foundation | BAKHTIAR SHAMLOO | progress |
| 12/08/2023 | Energy Code Compliance Inspections | BAKHTIAR SHAMLOO | progress |
| 12/08/2023 | Fire-Resistance Rated Construction | BAKHTIAR SHAMLOO | progress |
| 12/08/2023 | Insulation placement and R values | BAKHTIAR SHAMLOO | energy_progress |
| 12/08/2023 | HVAC-R and service water heating system controls | BAKHTIAR SHAMLOO | energy_progress |
| 12/08/2023 | Air barrier - visual inspection | BAKHTIAR SHAMLOO | energy_progress |
| 12/08/2023 | Maintenance information | BAKHTIAR SHAMLOO | energy_progress |
| 12/08/2023 | Duct leakage testing, insulation and design | BAKHTIAR SHAMLOO | energy_progress |
| 12/08/2023 | HVAC-R and service water piping design and insulation | BAKHTIAR SHAMLOO | energy_progress |
| 12/08/2023 | HVAC-R and service water heating equipment | BAKHTIAR SHAMLOO | energy_progress |