| Owner | Filings | Most Recent |
|---|---|---|
| OWNER OF 249 WAVERLY PLAC | 1 | 03/22/2026 |
| OWNER OF 249 WAVERLY P | 1 | 03/22/2026 |
| CLM PROPERTIES | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/08/2023 | $6.2M | — | — → — | $3,488/sf building |
| 07/14/2020 | $3.9M | — | Private party → Private party | $2,212/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SOLURI ARCHITECTURE | 5 | 06/20/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SOLURI ARCHITECTURE | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EVGC CORP | General Contractor | 5 | 07/08/2026 |
| AMERICAN STANDARD PLUMBING & | Fire Protection | 1 | 07/08/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| O'ROURKE ENGINEERING, LLC | 5873 | 1 | 10/02/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | EVGC CORP | 10/26/2023 |
| DOB NOW | Sprinklers | Signed-off | AMERICAN STANDARD PLUMBIN | 10/24/2023 |
| DOB NOW | General Construction | Permit Issued | EVGC CORP | 10/11/2023 |
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 07/21/2023 |
| DOB NOW | General Construction | Permit Issued | EVGC CORP | 06/13/2023 |
| BIS | SP | ISSUED | PRONTO PLUMBING CORP | 10/09/2002 |
| BIS | EQ | ISSUED | LAKHI GENERAL CONTRACTOR | 08/16/2000 |
| BIS | PL | ISSUED | P RONTO PLUMBING | 08/08/2000 |
| BIS | OT | ISSUED | 249 WAVERLY PARTNERS | 04/27/1999 |
| BIS | MH | ISSUED | CLM PROPERTIES,INC. | 05/27/1997 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/20/2024 | Signed-off | COBALT MECHANICAL INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2023 | Complete | REDLINE ELECTRIC INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/20/2024 | Permit Issued | EVGC CORP | Steel, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/30/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/17/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/16/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/12/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/20/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 11/02/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/27/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/19/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/22/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/11/2024 | Energy Code Compliance Inspections | Andre Soluri | progress |
| 05/17/2023 | Energy Code Compliance Inspections | Andre Soluri | progress |
| 05/17/2023 | Fire-Resistance Rated Construction | Andre Soluri | progress |
| 05/17/2023 | Interior lighting power | Andre Soluri | energy_progress |
| 05/17/2023 | Lighting in dwelling units | Andre Soluri | energy_progress |
| 05/17/2023 | Lighting controls | Andre Soluri | energy_progress |
| 05/11/2023 | Final | Andre Soluri | progress |