← Back
BuildNYC
Office with commercial, 7-19 stories
Gantry Point
25-11 49TH AVENUE · BIN 4000746
💬 Discuss this project
2019Year Built
9Stories
O6Building Class
M1-4Zoning
193,197 sfGross Floor Area
1Units
LL97 Covered2 Active Violations ▸
Office with commercial, 7-19 stories · Owner of record: 25-11 49th Avenue · 92,105 sf lot · 2.1 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofSotheby - Gantry Point16p · 2 filings · 20 docs
Floor 5Cushman & Wakefield accessory banner installation2p · 1 filing · 2 docs
Floor 4Cushman & Wakefield accessory banner installation2p · 1 filing · 2 docs
Floor 3Sotheby - Gantry PointUnder Construction34p · 5 filings · 17 docs
Floor 2Sotheby - Gantry Point107p · 9 filings · 20 docs
Floor 1Sotheby - Gantry Point142p · 10 filings · 20 docs
Site & exteriorNormandy Realty23p · 9 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Sothebys8610/10/2026
Maple 49th Avenue Owner II3103/21/2026
Candid Litho Printing1903/21/2026
Normandy Realty1607/08/2026
25-11 Hunters Point Avenue703/21/2026
Columbia Property Trust607/08/2026
25-11 49th Avenue103/22/2026
Graphics Service Bureau103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/21/2022$82.5M—MAPLE 49TH AVENUE OWNER II, LLC, → 25-11 49TH AVENUE LLC$427/sf building
02/07/2018$39.7M—25-11 HUNTERS POINT, LLC → MAPLE 49TH AVENUE OWNER II, LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AMA Consulting Engineers810/09/2026
David Burns102/17/2026
Aeis308/06/2024
Gate211 Architecture103/12/2024
Ryan Soames Engineering911/14/2023
McNamara Salvia310/18/2023
Gregory Ralph, Architect310/17/2023
Pve Associates101/23/2023
Leon Skvirsky PE212/06/2021
Bohler Engineering NY401/22/2021
Jose L. Pena, P.E111/17/2019
Scalar Architecture106/21/2019
Paul Perdek, Prof. Engineering105/23/2019
Asif Jamil, RA309/19/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Codegreen2403/21/2026
Building Brothers403/21/2026
Rizzogroup403/21/2026
AE Design Solution403/21/2026
Bohler Engineering403/21/2026
KD Designs303/21/2026
Louis Striar203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Avison Young Project ManagementGeneral Contractor1707/08/2026
Spring ScaffoldingScaffold1407/08/2026
Suffolk Construction CompanyScaffold907/08/2026
Suffolk Construction CompanyGeneral Contractor507/08/2026
TPG ContractingGeneral Contractor307/08/2026
Archstone BuildersGeneral Contractor307/08/2026
DNP BuildersGeneral Contractor307/08/2026
Atlas-Acon Electric ServiceElectrical203/21/2026
Active SignsSign hanger207/08/2026
PJZ MaintenanceElectrical103/21/2026
Commercial Electric ContElectrical103/21/2026
Wasoff Plumbing & Utility CoPlumbing107/08/2026
Tru-Art Sign CoSign hanger107/08/2026
Aqueduct MechanicalFire Protection107/08/2026
Aqueduct MechanicalPlumbing107/08/2026
Drilon Plumbing & HeatingPlumbing107/08/2026
Five Boro AssociatesFire Protection107/08/2026
Mill Brook Fire ProtectionFire Protection107/08/2026
Solution Mechanical ContngPlumbing107/08/2026
Atn ElectricElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Codegreen510910/09/2026
Future Tech Consultants O589308/06/2024
CNS Inspection Services75661311/13/2023
McNamara/Salvia of New YO4970310/18/2023
Langan Engineering, Env, Surveyin1265101/10/2023
Building Lifecycle
All (256)Filed (41)Permit Issued (41)Signed Off (24)Violation (60)Inspection (12)Objection (48)Special Inspection (30)
10/09/2026
Filed — Alteration
Q01223071-P1
09/08/2026
Signed off — Alteration
Q01223061-I1
09/08/2026
Signed off — Alteration
Q01222021-I1
06/04/2026
Permit issued — General Construction
Q01222021-I1-GC
04/07/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/06/2026
Permit issued — Sprinklers
Q01223071-I1-EW-SP
02/25/2026
Permit issued — Plumbing
Q01223061-I1-PL
02/23/2026
Permit issued — General Construction
Q01222021-I1-GC
02/23/2026
Permit issued — Mechanical Systems
Q01223050-I1-MS
02/18/2026
Filed — Alteration
Q01223061-I1
02/18/2026
Filed — Alteration
Q01223071-I1
02/18/2026
Filed — Alteration
Q01223050-I1
02/17/2026
Filed — Alteration
Q01222021-I1
06/02/2025
Signed off — Alteration
Q00990997-I1
10/22/2024
Signed off — Alteration
SPRINKLER MODIFICATIONS ON 2ND FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00991080-I1
10/09/2024
Signed off — Alteration
Q00990986-I1
08/07/2024
Special inspection requirement — Sprinkler Systems
Stephen Marchese
08/07/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Stephen Marchese
08/06/2024
Filed — Alteration
SPRINKLER MODIFICATIONS ON 2ND FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00991080-P1
08/02/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/26/2024
Special inspection requirement — Sprinkler Systems
Stephen Marchese
07/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Stephen Marchese
06/11/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/21/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/21/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/21/2024
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
05/09/2024
Permit issued — Mechanical Systems
Q00990997-I1-MS
05/02/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/11/2024
Filed — Alteration
Q00990997-I1
04/10/2024
Permit issued — Sprinklers
Q00991080-I1-EW-SP
03/29/2024
Filed — Alteration
SPRINKLER MODIFICATIONS ON 2ND FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00991080-I1
03/15/2024
Permit issued — General Construction
Q00990986-I1-GC
03/12/2024
Filed — Alteration
Q00990986-I1
01/16/2024
Special inspection requirement — Final
Stephen Marchese
12/19/2023
Signed off — Alteration
Boiler installation on first floor and mechanical roof as per plans filed herewith.
Q00335000-I1
11/27/2023
Signed off — Alteration
PLUMBING MODIFICATIONS TAKING PLACE ON THE 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00823077-I1
11/21/2023
Signed off — Alteration
MECHANICAL MODIFICATIONS TAKING PLACE ON THE 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00823073-I1
11/21/2023
Signed off — Alteration
SPRINKLER MODIFICATIONS TAKING PLACE ON THE 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00823119-I1
11/20/2023
Signed off — Alteration
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00825331-I1
11/17/2023
Signed off — Alteration
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE EGRESS, OR OCCUPANCY.
Q00823048-I1
11/16/2023
Special inspection requirement — Structural Steel - Details
John Nucatola
11/16/2023
Special inspection requirement — Final
John Nucatola
11/16/2023
Special inspection requirement — Construction Operations Influencing Adjacent Structures
John Nucatola
11/16/2023
Special inspection requirement — Structural Steel - High Strength Bolting
John Nucatola
11/16/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
John Nucatola
11/16/2023
Special inspection requirement — Structural Steel - Welding
John Nucatola
11/16/2023
Special inspection requirement — Concrete - Cast-In-Place
Bart Sullivan
11/16/2023
Special inspection requirement — Post-installed Anchors
John Nucatola
11/14/2023
Filed — Alteration
PLUMBING MODIFICATIONS TAKING PLACE ON THE 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00823077-P2
11/13/2023
Filed — Alteration
MECHANICAL MODIFICATIONS TAKING PLACE ON THE 1ST AND 2ND FLOORS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q00823073-P1
11/06/2023
Objection resolved — Addressed
11/06/2023
Special inspection requirement — Ventilation and air distribution system
John Nucatola
11/06/2023
Special inspection requirement — HVAC-R and service water heating equipment
John Nucatola
11/06/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
John Nucatola
11/06/2023
Special inspection requirement — Mechanical Systems
John Nucatola
11/06/2023
Special inspection requirement — Final
John Nucatola
11/06/2023
Special inspection requirement — Interior lighting power
John Nucatola
11/06/2023
Special inspection requirement — Exterior lighting power
John Nucatola
11/06/2023
Special inspection requirement — HVAC-R and service water heating system controls
John Nucatola
11/06/2023
Special inspection requirement — Maintenance information
John Nucatola
Latest 60 of 256 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offDNP Builders06/04/2026
DOB NOWSprinklersPermit IssuedFive Boro Associates03/06/2026
DOB NOWPlumbingSigned-offSolution Mechanical Contng02/25/2026
DOB NOWGeneral ConstructionSigned-offDNP Builders02/23/2026
DOB NOWMechanical SystemsPermit IssuedDNP Builders02/23/2026
DOB NOWMechanical SystemsSigned-offArchstone Builders05/09/2024
DOB NOWSprinklersSigned-offLeguci Piping & Heating04/10/2024
DOB NOWGeneral ConstructionSigned-offArchstone Builders03/15/2024
DOB NOWMechanical SystemsSigned-offAvison Young Project Management07/07/2023
DOB NOWGeneral ConstructionSigned-offAvison Young Project Management07/07/2023
DOB NOWFoundationPermit IssuedAvison Young Project Management07/06/2023
DOB NOWMechanical SystemsSigned-offAvison Young Project Management07/06/2023
DOB NOWStructuralSigned-offAvison Young Project Management05/30/2023
DOB NOWSprinklersSigned-offAqueduct Mechanical04/19/2023
DOB NOWPlumbingSigned-offAqueduct Mechanical04/18/2023
DOB NOWMechanical SystemsSigned-offAvison Young Project Management03/24/2023
DOB NOWGeneral ConstructionSigned-offAvison Young Project Management03/21/2023
DOB NOWFoundationPermit IssuedAvison Young Project Management03/16/2023
DOB NOWMechanical SystemsSigned-offAvison Young Project Management01/27/2023
DOB NOWStructuralSigned-offTPG Contracting10/26/2022
DOB NOWStructuralSigned-offTPG Contracting10/11/2022
DOB NOWSignSigned-offActive Signs02/04/2022
DOB NOWSignSigned-offActive Signs02/04/2022
DOB NOWCurb CutSigned-offSuffolk Construction Company07/29/2021
DOB NOWCurb CutSigned-offSuffolk Construction Company07/29/2021
DOB NOWCurb CutSigned-offSuffolk Construction Company07/28/2021
DOB NOWConstruction FenceSigned-offSpring Scaffolding03/04/2021
DOB NOWSidewalk ShedSigned-offSpring Scaffolding03/03/2021
DOB NOWConstruction FenceSigned-offSuffolk Construction Company01/12/2021
DOB NOWBoiler EquipmentSigned-offDrilon Plumbing & Heating11/16/2020
DOB NOWPlumbingSigned-offWasoff Plumbing & Utility Co07/22/2020
DOB NOWSidewalk ShedSigned-offSpring Scaffolding05/12/2020
DOB NOWConstruction FenceSigned-offSpring Scaffolding04/21/2020
DOB NOWSignSigned-offTru-Art Sign Co11/18/2019
DOB NOWConstruction FenceSigned-offSuffolk Construction Company09/13/2019
DOB NOWConstruction FenceSigned-offSpring Scaffolding06/21/2019
DOB NOWSidewalk ShedSigned-offSpring Scaffolding05/24/2019
DOB NOWConstruction FenceSigned-offSuffolk Construction Company03/08/2019
DOB NOWConstruction FenceSigned-offSuffolk Construction Company12/28/2018
DOB NOWConstruction FenceSigned-offSuffolk Construction Company03/22/2018
+ 47 more permits on file
9 projects · most recent 06/08/2026
General Wiring Lighting
FiledStatusContractorScope
06/08/2026CompleteLne ElectricalGeneral Wiring, Lighting
03/09/2026Permit IssuedHylan Datacom & ElectricalGeneral Wiring
03/26/2024CompleteM.C. Electrical NYGeneral Wiring
04/19/2023CompleteMikoma ElectricGeneral Wiring
02/07/2023CompleteStar Electrical Contractors—
02/17/2021Permit IssuedNet Power ElectricGeneral Wiring
08/27/2019CompleteJam Electrical—
05/13/2019CompleteTop Shelf Electric—
03/29/2018Permit IssuedJohn Michael Electrical Contg—
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
04/07/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/11/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/21/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/21/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/21/2024Certified Sprinkler - SP - RoughingCertifiedView ↗
10/24/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/22/2023Fail-Final PL - Up to 9 Requested FloorsFailView ↗
09/20/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/14/2023No Access-Final PL - Up to 9 Requested FloorsNo AccessView ↗
07/13/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/07/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/05/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 82
DateRequirementInspectorRole
08/07/2024Sprinkler SystemsStephen Marchesespecial
08/07/2024Fire-Resistant Penetrations and JointsStephen Marchesespecial
07/26/2024Sprinkler SystemsStephen Marchesespecial
07/26/2024Fire-Resistant Penetrations and JointsStephen Marchesespecial
01/16/2024FinalStephen Marcheseprogress
11/16/2023Post-installed AnchorsJohn Nucatolaspecial
11/16/2023Construction Operations Influencing Adjacent StructuresJohn Nucatolaspecial
11/16/2023Structural Steel - DetailsJohn Nucatolaspecial
11/16/2023Structural Steel - WeldingJohn Nucatolaspecial
11/16/2023Structural Steel - High Strength BoltingJohn Nucatolaspecial
11/16/2023Structural Stability – Alterations of existing buildingsJohn Nucatolaspecial
11/16/2023Concrete - Cast-In-PlaceBart Sullivanspecial
11/16/2023FinalJohn Nucatolaprogress
11/06/2023HVAC-R and service water heating equipmentJohn Nucatolaenergy_progress
11/06/2023Ventilation and air distribution systemJohn Nucatolaenergy_progress
11/06/2023Lighting controlsJohn Nucatolaenergy_progress
11/06/2023Maintenance informationJohn Nucatolaenergy_progress
11/06/2023HVAC-R and service water heating system controlsJohn Nucatolaenergy_progress
11/06/2023Exterior lighting powerJohn Nucatolaenergy_progress
11/06/2023FinalJohn Nucatolaprogress
11/06/2023Mechanical SystemsJohn Nucatolaspecial
11/06/2023HVAC-R and service water piping design and insulationJohn Nucatolaenergy_progress
11/06/2023Interior lighting powerJohn Nucatolaenergy_progress
10/20/2023Sprayed fire-resistant materialsJohn Nucatolaspecial
10/20/2023FinalJohn Nucatolaprogress
Latest 25 of 82.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Sotheby - Gantry PointOfficeEntire building
Project Q01223050 Alteration · Permit Entire · 02/18/2026
Project Q01223061 Alteration · LOC Issued · 02/18/2026
Project Q01223071 Alteration · Permit Entire · 02/18/2026
Project Q01222021 Alteration · LOC Issued · 02/17/2026
Project Q00990997 Alteration · LOC Issued · 04/11/2024
Project Q00991080 Alteration · LOC Issued · 03/29/2024
Project Q00990986 Alteration · LOC Issued · 03/12/2024
Project Q00823048 Alteration · LOC Issued · 03/17/2023
Project Q00823073 Alteration · LOC Issued · 03/08/2023
Project Q00823077 Alteration · LOC Issued · 03/08/2023
Project Q00823119 Alteration · LOC Issued · 03/08/2023
Project Q00825331 Alteration · LOC Issued · 03/06/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 765 on file (BIS + DOB NOW)
▸Plans & Drawings40
▸DOB NOWPlans/Sketch32
08/28/2026Q00021970-P1Request digital key ↗
08/28/2026Q00021970-P2Request digital key ↗
08/28/2026Q00021970-I1Request digital key ↗
Showing 3 of 32 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment4
08/27/2026Q00335000-I1Request digital key ↗
08/15/2026Q00335000-P3Request digital key ↗
08/15/2026Q00335000-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/28/2026Q00167975-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/28/2026Q00216781-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sign1
08/28/2026Q00251163-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/28/2026Q00167988-I1Request digital key ↗
▸Applications & Permits168
▸BISPLAN / WORK APPROVAL APPLICATION125
02/24/2026420663801Open ↗
05/01/2024420663801Open ↗
04/04/2024420663801Open ↗
Showing 3 of 125 on file for this type
▸BISWORK PERMIT APPLICATION39
11/04/2020440637438Open ↗
10/19/2020420663801Open ↗
11/27/2019421543921Open ↗
Showing 3 of 39 on file for this type
▸BISApplication Withdrawal/Address Change Form OP-1132
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
01/14/2021420663801Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
09/25/2020421630970Open ↗
▸Zoning, Tax Lot & Property Records4
▸BISZONING DIAGRAM2
09/22/2023420663801Open ↗
Showing 1 of 2 on file for this type
▸BISZONING EXHIBIT I: CERTIFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications169
▸DOB NOWDPL-1: Design Professional Seal & Signature40
08/28/2026Q00021970-I1Open ↗
08/28/2026Q00167988-I1Open ↗
08/28/2026Q00251163-I1Open ↗
Showing 3 of 40 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION39
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 39 on file for this type
▸DOB NOWProgress Inspector Seal & Signature24
09/23/2026Q00335000-I1Open ↗
09/17/2026Q00335000-P2Open ↗
09/17/2026Q00335000-P2Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature24
09/23/2026Q00335000-I1Open ↗
09/17/2026Q00335000-P2Open ↗
09/03/2026Q08054170-I1Open ↗
Showing 3 of 24 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT12
10/28/2020440637438Open ↗
11/05/2019440573158Open ↗
Showing 2 of 12 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION7
10/28/2020440637438Open ↗
11/05/2019440573158Open ↗
Showing 2 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY7
10/28/2020440637438Open ↗
11/05/2019440573158Open ↗
Showing 2 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment44
▸BISSCHEDULE B - PLUMBING24
06/15/2021420663801Open ↗
06/10/2021420663801Open ↗
11/17/2020420663801Open ↗
Showing 3 of 24 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSELF-CERT PLUMBING NOTICE6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISEQUIPMENT USE PERMITS3
11/23/2021420663801Open ↗
Showing 1 of 3 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT3
11/23/2021420663801Open ↗
Showing 1 of 3 on file for this type
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTENANT PROTECTION PLAN AND NOTES1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTREET TREES SITE PLAN1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos44
▸DOB NOWDEP ACP-5: Asbestos Assessment Report25
08/25/2026Q00809140-I1Open ↗
08/25/2026Q00823073-I1Open ↗
08/25/2026Q00823119-I1Open ↗
Showing 3 of 25 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
10/28/2020440637438Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026Q00335000-I1Open ↗
▸Energy Compliance30
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY12
08/27/2021440637438Open ↗
08/03/2021420663801Open ↗
06/15/2021420663801Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
08/27/2021440637438Open ↗
08/03/2021420663801Open ↗
08/03/2021420663801Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
10/28/2020440637438Open ↗
Showing 1 of 2 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026Q00335000-I1Open ↗
▸Inspections & Test Reports60
▸BISTECHNICAL REPORT: RESPONSIBILITY39
08/27/2021440637438Open ↗
08/27/2021440637438Open ↗
08/03/2021420663801Open ↗
Showing 3 of 39 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX10
11/21/2019420663801Open ↗
11/15/2019420663801Open ↗
Showing 2 of 10 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
08/13/2021420663801Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSUBSURFACE / SOILS INVESTIGATION (BORINGS/TEST PITS)1
08/03/2021420663801Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
08/13/2021420663801Open ↗
▸BISTECHNICAL REPORT: PHOTOLUMINESCENCE1
11/23/2021420663801Open ↗
▸BISDEP Hydrant Flow Test Letter1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWSOIL REPORT1
08/13/2026Q08054170-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q08054170-I1Open ↗
▸Approvals, Objections & Sign-offs48
▸BISSCHEDULE A - OCCUPANCY / USE19
04/04/2024420663801Open ↗
09/06/2023420663801Open ↗
09/01/2023420663801Open ↗
Showing 3 of 19 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST12
08/27/2021440637438Open ↗
07/22/2021421365454Open ↗
07/22/2021421572159Open ↗
Showing 3 of 12 on file for this type
▸BISADMINISTRATIVE OBJECTIONS8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION6
01/19/2021421630970Open ↗
10/19/2020420663801Open ↗
Showing 2 of 6 on file for this type
▸BISSUPERSEDING LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership41
▸BISCOST AFFIDAVIT34
08/27/2021440637438Open ↗
07/16/2021421543921Open ↗
06/03/2021440538786Open ↗
Showing 3 of 34 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE5
10/19/2020420663801Open ↗
Showing 1 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
07/02/2021421365454Open ↗
07/02/2021421572159Open ↗
▸Filing & Intake Forms82
▸BISADDITIONAL INFORMATION39
05/06/2024420663801Open ↗
09/22/2023420663801Open ↗
07/12/2023420663801Open ↗
Showing 3 of 39 on file for this type
▸BISEFILING COVER SHEET24
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 24 on file for this type
▸BISBOROUGH INTAKE FORM11
11/29/2019421543921Open ↗
Showing 1 of 11 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET8
10/28/2020440637438Open ↗
11/05/2019440573158Open ↗
Showing 2 of 8 on file for this type
▸Other Documents17
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION11
11/25/2020420663801Open ↗
11/25/2020420663801Open ↗
11/24/2020420663801Open ↗
Showing 3 of 11 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
07/16/2021421543921Open ↗
Showing 1 of 2 on file for this type
▸BISLUMINOUS EGRESS PATH MARKINGS1
11/23/2021420663801Open ↗
▸BISEMERGENCY & STANDBY POWER SYSTEMS (GENERATORS)1
11/23/2021420663801Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026Q08001235-I1Open ↗
▸DOB NOWTR5H Test Report1
08/13/2026Q08054170-I1Open ↗