← Back
Two family brick
25-63 34 STREET
QUEENS · BIN 4009341
💬 Discuss this project
1920Year Built
2Stories
B1Building Class
R6BZoning
2,408 sfGross Floor Area
2Units
Two family brick · 2,500 sf lot · 0.96 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanical
Roof1p · 1 filing · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 31p · 1 filing · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 12p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/25/2025$1.5M—Private party → Private party$623/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PIRO STUDIO LLC509/04/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DI DIO ARCHITECTURE, PC1003/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KENDALL ENGINEERING PC4154309/04/2025
Building Lifecycle
All (62)Filed (5)Objection (42)Special Inspection (15)
04/03/2026
Special inspection requirement — Exterior lighting power
PIETRO ROSATO
04/03/2026
Special inspection requirement — Air barrier continuity plan testing
PIETRO ROSATO
04/03/2026
Special inspection requirement — Fenestration areas
PIETRO ROSATO
03/03/2026
Objection raised — Cost
02/27/2026
Objection resolved — Addressed
02/26/2026
Objection resolved — Addressed
02/18/2026
Objection resolved — Addressed
02/18/2026
Objection resolved — Addressed
12/01/2025
Objection raised — Cost
11/26/2025
Objection resolved — Addressed
11/26/2025
Objection resolved — Addressed
11/26/2025
Objection resolved — Addressed
11/26/2025
Objection resolved — Addressed
11/18/2025
Objection resolved — Addressed
10/23/2025
Objection resolved — Addressed
10/23/2025
Objection resolved — Resolved
10/23/2025
Objection resolved — Addressed
10/23/2025
Objection resolved — Resolved
10/23/2025
Objection resolved — Resolved
10/23/2025
Objection resolved — Resolved
10/23/2025
Objection resolved — Resolved
10/23/2025
Objection resolved — Addressed
10/23/2025
Objection resolved — Addressed
10/01/2025
Objection raised — Structural
10/01/2025
Objection raised — Structural
10/01/2025
Objection raised — Inspections
09/30/2025
Objection raised — Structural
09/29/2025
Objection raised — Zoning
09/29/2025
Objection raised — Zoning
09/29/2025
Objection raised — Inspections
09/29/2025
Objection raised — Cost
09/26/2025
Objection raised — Structural
09/25/2025
Objection raised — Fire_Protection
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Cost
09/25/2025
Objection raised — Scope
09/25/2025
Objection raised — Scope
09/25/2025
Objection raised — Other
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Inspections
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/04/2025
Filed — Alteration CO
Q01252018-S1
09/04/2025
Filed — Alteration CO
Q01252018-S3
09/03/2025
Filed — Alteration CO
Q01252018-S4
09/02/2025
Filed — Alteration CO
Q01252018-S2
07/26/2025
Filed — Alteration CO
Q01252018-I1
07/26/2025
Special inspection requirement — Post-installed Anchors
KEVIN KENDALL
07/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KEVIN KENDALL
07/16/2025
Special inspection requirement — Air barrier - visual inspection
PIETRO ROSATO
07/16/2025
Special inspection requirement — Lighting in dwelling units
PIETRO ROSATO
07/16/2025
Special inspection requirement — Energy Code Compliance Inspections
PIETRO ROSATO
07/16/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
PIETRO ROSATO
07/16/2025
Special inspection requirement — Fenestration air leakage
PIETRO ROSATO
07/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
PIETRO ROSATO
07/16/2025
Special inspection requirement — Fire-Resistance Rated Construction
PIETRO ROSATO
07/16/2025
Special inspection requirement — Insulation placement and R values
PIETRO ROSATO
Latest 60 of 62 events.
Nothing on file for this building.
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
04/03/2026Exterior lighting powerPIETRO ROSATOenergy_progress
04/03/2026Air barrier continuity plan testingPIETRO ROSATOenergy_progress
04/03/2026Fenestration areasPIETRO ROSATOenergy_progress
07/26/2025Post-installed AnchorsKEVIN KENDALLspecial
07/26/2025Fire-Resistant Penetrations and JointsKEVIN KENDALLspecial
07/16/2025Air barrier - visual inspectionPIETRO ROSATOenergy_progress
07/16/2025Lighting in dwelling unitsPIETRO ROSATOenergy_progress
07/16/2025Energy Code Compliance InspectionsPIETRO ROSATOprogress
07/16/2025Fenestration and door U-factor and product ratingsPIETRO ROSATOenergy_progress
07/16/2025Fenestration air leakagePIETRO ROSATOenergy_progress
07/16/2025Fire-Resistant Penetrations and JointsPIETRO ROSATOspecial
07/16/2025Fire-Resistance Rated ConstructionPIETRO ROSATOprogress
07/16/2025Insulation placement and R valuesPIETRO ROSATOenergy_progress
07/14/2025Structural Stability – Alterations of existing buildings—special
07/07/2025Sprinkler SystemsKEVIN KENDALLspecial
▾Documents — 34 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/19/2026Q01252018-S3Request digital key ↗
08/19/2026Q01252018-S4Request digital key ↗
08/19/2026Q01252018-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/19/2026Q01252018-I1Open ↗
08/13/2026Q01252018-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01252018-I1Open ↗
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature7
08/29/2026Q01252018-I1Open ↗
08/29/2026Q01252018-I1Open ↗
08/29/2026Q01252018-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/19/2026Q01252018-S1Open ↗
08/19/2026Q01252018-S4Open ↗
08/19/2026Q01252018-S3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/29/2026Q01252018-I1Open ↗
08/26/2026Q01252018-S4Open ↗
08/26/2026Q01252018-S4Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/19/2026Q01252018-I1Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/19/2026Q01252018-S4Open ↗
08/19/2026Q01252018-S3Open ↗
08/19/2026Q01252018-S2Open ↗
Showing 3 of 5 on file for this type
▸Other Documents4
▸DOB NOWPlot Diagram1
08/13/2026Q01252018-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/19/2026Q01252018-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01252018-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01252018-I1Open ↗