| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2023 | Signed-off | WASOFF PLBG & UTILITY CO | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/20/2023 | Permit Issued | R.A. PHILLIPS ELEC'L CONT | General Wiring |
| 01/03/2022 | Complete | MAGNA ELECTRIC CORP | — |
| 10/27/2021 | Complete | G. POULAKIS ELEC'L CONTR' | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| 327 PARK AVE SOUTH REALTY CORP | 34 | 07/08/2026 |
| PLATINUM SERVICES NY | 6 | 07/08/2026 |
| LE LUXE BEAUTIQUE LLC | 9 | 03/22/2026 |
| 25-73 STEINWAY | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KCE CONSULTING ENGINEERING PLLC | 2 | 08/03/2023 |
| GERALD CALIENDO ARCHITECTS | 9 | 12/28/2021 |
| ASHRAF CORP | 1 | 03/30/2021 |
| RAS PE CONSULTING ENGINEERS | 1 | 11/23/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| KP CONSULTING ENGINEER | 4 | 03/21/2026 |
| GERALD J CALIENDO ARCHITECT P C | 18 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PLATINUM SERVICES NY LLC | General Contractor | 4 | 07/08/2026 |
| PM MECHANICAL GROUP CORP | General Contractor | 4 | 07/08/2026 |
| CN PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| LUIGI CALIENDO & SONS,INC | General Contractor | 2 | 07/08/2026 |
| WASOFF PLUMBING & UTILITY CO | General Contractor | 2 | 03/21/2026 |
| MJ GENERAL MECHANICAL LLC | Plumbing | 1 | 07/08/2026 |
| WASOFF PLBG & UTILITY CO | Plumbing | 1 | 07/08/2026 |
| WATERMARK PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| R G M SIGNS | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| IP CONCRETE TESTING AND I | 6252 | 2 | 08/03/2023 |
| DY SPECIAL INSPECTION LLC | 7210 | 1 | 12/28/2021 |
| PROMISE CONSULTANTS | 1412 | 6 | 09/10/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | WASOFF PLBG & UTILITY CO | 08/18/2023 |
| DOB NOW | General Construction | Signed-off | WASOFF PLUMBING & UTILITY | 08/11/2023 |
| DOB NOW | Sign | Signed-off | R.G.M. SIGNS INC | 04/13/2022 |
| DOB NOW | Plumbing | Signed-off | MJ GENERAL MECHANICAL LLC | 01/11/2022 |
| DOB NOW | Plumbing | Signed-off | WATERMARK PLUMBING CORP | 10/13/2021 |
| DOB NOW | Structural | Signed-off | LUIGI CALIENDO & SONS,INC | 09/28/2021 |
| DOB NOW | Construction Fence | Signed-off | LUIGI CALIENDO & SONS,INC | 09/28/2021 |
| DOB NOW | Plumbing | Signed-off | CN PLUMBING INC | 08/13/2021 |
| DOB NOW | Mechanical Systems | Signed-off | PM MECHANICAL GROUP CORP | 04/28/2021 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 03/31/2021 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 03/31/2021 |
| DOB NOW | Mechanical Systems | Signed-off | PM MECHANICAL GROUP CORP | 02/19/2021 |
| DOB NOW | Plumbing | Signed-off | CN PLUMBING INC | 11/17/2020 |
| BIS | — | ISSUED | LUIGI CALIENDO & SONS,INC | 11/22/2021 |
| BIS | — | ISSUED | LUIGI CALIENDO & SONS,INC | 03/12/2021 |
| BIS | OT | ISSUED | LUIGI CALIENDO & SONS,INC | 11/30/2020 |
| BIS | OT | ISSUED | LUIGI CALIENDO & SONS,INC | 09/23/2020 |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/13/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/13/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/29/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/18/2022 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 01/20/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/07/2021 | Pass-Final Fence Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/03/2023 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 08/02/2023 | Tenant Protection Plan Compliance | INDARDEO PARBHUNATH | special |
| 03/30/2023 | Interior lighting power | INDARDEO PARBHUNATH | energy_progress |
| 03/30/2023 | Lighting controls | INDARDEO PARBHUNATH | energy_progress |
| 03/28/2023 | Final | NAVEEN KUMAR | progress |
| 03/28/2023 | Fire-Resistance Rated Construction | INDARDEO PARBHUNATH | progress |
| 03/28/2023 | Energy Code Compliance Inspections | INDARDEO PARBHUNATH | progress |
| 03/28/2023 | Tenant Protection Plan Compliance | INDARDEO PARBHUNATH | special |
| 03/28/2023 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 12/27/2021 | Fire-Resistant Penetrations and Joints | THOMAS TUNG | special |
| 09/15/2021 | Maintenance information | JUNG Y SHIN | energy_progress |
| 09/15/2021 | Fire-Resistant Penetrations and Joints | JUNG Y SHIN | special |
| 09/15/2021 | Energy Code Compliance Inspections | JUNG Y SHIN | progress |
| 09/09/2021 | Fire-Resistant Penetrations and Joints | JUNG Y SHIN | special |
| 09/09/2021 | Maintenance information | JUNG Y SHIN | energy_progress |
| 09/09/2021 | Energy Code Compliance Inspections | JUNG Y SHIN | progress |
| 08/24/2021 | Fire-Resistant Penetrations and Joints | JUNG Y SHIN | special |
| 08/24/2021 | Energy Code Compliance Inspections | JUNG Y SHIN | progress |
| 08/24/2021 | Maintenance information | JUNG Y SHIN | energy_progress |
| 08/02/2021 | Energy Code Compliance Inspections | JUNG Y SHIN | progress |
| 08/02/2021 | Maintenance information | JUNG Y SHIN | energy_progress |
| 08/02/2021 | Fire-Resistant Penetrations and Joints | JUNG Y SHIN | special |
| 05/29/2020 | Fire-Resistant Penetrations and Joints | — | special |
| 05/29/2020 | Maintenance information | — | energy_progress |
| 05/29/2020 | Energy Code Compliance Inspections | — | progress |