| Owner | Filings | Most Recent |
|---|---|---|
| ASTORIAZ 88 LLC | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/02/2020 | $2.2M | — | Private party → ASTORIAZ 88 LLC | $555/sf building |
| 02/14/2014 | $700K | — | Private party → AMPIERA STEINWAY CORP. | $174/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| YOUN DESIGN CORP. | 1 | 05/03/2025 |
| MOSTAFA | 4 | 07/31/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| RP DEVELOPMENT GROUP | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JOHN EVAN CONTRACTING COR | General Contractor | 15 | 03/21/2026 |
| MHM CONSTRUCTION NYC INC | General Contractor | 1 | 07/08/2026 |
| CAPE PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 4 | 07/31/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | JOHN EVAN CONTRACTING COR | 04/28/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN EVAN CONTRACTING COR | 03/15/2024 |
| DOB NOW | General Construction | Permit Issued | JOHN EVAN CONTRACTING COR | 03/15/2024 |
| DOB NOW | Plumbing | Permit Issued | CAPE PLUMBING INC | 09/28/2023 |
| DOB NOW | General Construction | Permit Issued | JOHN EVAN CONTRACTING COR | 09/28/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN EVAN CONTRACTING COR | 09/28/2023 |
| DOB NOW | General Construction | Permit Issued | MHM CONSTRUCTION NYC INC | 02/14/2023 |
| BIS | OT | ISSUED | SUNERGY SOLUTION INC | 01/08/2016 |
| BIS | PL | ISSUED | PETER PLUMBING ASSOC. INC. | 06/19/2015 |
| BIS | MH | ISSUED | SUNERGY SOLUTION INC | 06/15/2015 |
| BIS | EQ | ISSUED | SUNERGY SOLUTION INC | 06/15/2015 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/31/2023 | Permit Issued | JOHN EVAN CONTRACTING COR | Heating and Air Conditioning Systems, Others | Heat / Cool Cooper & Hunter CH-24MSPHWM-230VI 24,000 BTU · Ductwork ×6 MODEL: CH-48MSPH230VO 4 tons · Split System ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/03/2025 | Complete | JONG HYUN KIM | — |
| 03/12/2024 | Permit Issued | STABILITY ELEC ENTERP INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/27/2022 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 12/14/2022 | Fire-Resistance Rated Construction | Younes Abouyaala | progress |
| 11/23/2022 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 11/23/2022 | Tenant Protection Plan Compliance | Younes Abouyaala | special |
| 11/23/2022 | Energy Code Compliance Inspections | Younes Abouyaala | progress |