← Back
Zoned residential, not Manhattan
25 ABBEY COURT
BROOKLYN · BIN 3248704
💬 Discuss this project
0Year Built
—Stories
V0Building Class
R4-1Zoning
0 sfGross Floor Area
0Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Zoned residential, not Manhattan · Owner of record: CITY OF NEW YORK · 1,800 sf lot · 0 FAR built · Flood zone AE
Locations of Work
Plumbing
Floor 31p · 1 filing · 17 docs
Floor 21p · 1 filing · 17 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DHANDY103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/26/2018$427K—Private party → PROJECT REBUILD, INC.— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AVID DESIGNS, INC101/26/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
D HANDY INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AVID DESIGNS, INC.453101/26/2022
Building Lifecycle
All (28)Filed (2)Permit Issued (1)Signed Off (1)Violation (1)Special Inspection (23)
06/27/2024
Special inspection requirement — Permanent certificate
11/27/2023
Special inspection requirement — Air barrier — testing
Jeffrey Geary
09/20/2022
Special inspection requirement — Lowest Floor Elevation
01/26/2022
Filed — New Building
NEW SINGLE-FAMILY Dwelling TO REPLACE EXISTING DAMAGED BEYOND REPAIR BY SUPER STORM SANDY, AFFORDABLE HOUSING
B00653797-I1
12/27/2021
Special inspection requirement — Structural Cold-Formed Steel
Jeffrey Geary
12/27/2021
Special inspection requirement — Subgrade Inspections
Jeffrey Geary
12/27/2021
Special inspection requirement — Final
James Carroll
12/27/2021
Special inspection requirement — Footing and Foundation
Jeffrey Geary
12/27/2021
Special inspection requirement — Electric vehicle service equipment requirements
Jeffrey Geary
12/27/2021
Special inspection requirement — HVAC-R and service water heating system controls
Jeffrey Geary
12/27/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
Jeffrey Geary
12/27/2021
Special inspection requirement — Mechanical Systems
Jeffrey Geary
12/27/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Jeffrey Geary
12/27/2021
Special inspection requirement — Air barrier - visual inspection
Jeffrey Geary
12/27/2021
Special inspection requirement — Insulation placement and R values
Jeffrey Geary
12/27/2021
Special inspection requirement — Fenestration air leakage
Jeffrey Geary
12/27/2021
Special inspection requirement — Fenestration areas
Jeffrey Geary
12/27/2021
Special inspection requirement — Maintenance information
Jeffrey Geary
12/27/2021
Special inspection requirement — Ventilation and air distribution system
Jeffrey Geary
12/27/2021
Special inspection requirement — HVAC-R and service water heating equipment
Jeffrey Geary
12/27/2021
Special inspection requirement — Shutoff dampers
Jeffrey Geary
12/27/2021
Special inspection requirement — Interior lighting power
Jeffrey Geary
12/27/2021
Special inspection requirement — Concrete - Cast-In-Place
Jeffrey Geary
12/27/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jeffrey Geary
07/23/2021
Signed off — Alteration
B00377823-I1
02/04/2021
Violation issued (ECB, closed)
Construction
08/27/2020
Permit issued — Construction Fence
B00377823-I1-FN
08/20/2020
Filed — Alteration
B00377823-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offD HANDY INC08/27/2020
BIS—ISSUEDD HANDY INC04/01/2021
1 project · most recent 01/26/2022
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
01/26/2022——Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Fujitsu asu18rlf 34 BTU · Split System ×1
Heating
Fujitsu asu18rlf 34 BTU · Split System ×1
Ventilation
Fantech SER150 145 CFM · Erv ×1
1 project · most recent 01/26/2022
Plumbing-Sprinkler Water/Sanitary
FiledStatusContractorScope
01/26/2022——Plumbing-Sprinkler, Water/Sanitary
1 project · most recent 01/26/2022
Wood
FiledStatusContractorScope
01/26/2022——Wood
▾Special Inspection Requirements (DOB NOW) — 23
DateRequirementInspectorRole
06/27/2024Permanent certificate—energy_progress
11/27/2023Air barrier — testing Jeffrey Gearyenergy_progress
09/20/2022Lowest Floor Elevation—progress
12/27/2021Structural Cold-Formed SteelJeffrey Gearyspecial
12/27/2021Subgrade InspectionsJeffrey Gearyspecial
12/27/2021FinalJames Carrollprogress
12/27/2021Footing and FoundationJeffrey Gearyprogress
12/27/2021Electric vehicle service equipment requirementsJeffrey Gearyenergy_progress
12/27/2021HVAC-R and service water heating system controlsJeffrey Gearyenergy_progress
12/27/2021Fenestration and door U-factor and product ratingsJeffrey Gearyenergy_progress
12/27/2021Mechanical SystemsJeffrey Gearyspecial
12/27/2021HVAC-R and service water piping design and insulationJeffrey Gearyenergy_progress
12/27/2021Air barrier - visual inspectionJeffrey Gearyenergy_progress
12/27/2021Insulation placement and R valuesJeffrey Gearyenergy_progress
12/27/2021Fenestration air leakageJeffrey Gearyenergy_progress
12/27/2021Fenestration areasJeffrey Gearyenergy_progress
12/27/2021Maintenance informationJeffrey Gearyenergy_progress
12/27/2021Ventilation and air distribution systemJeffrey Gearyenergy_progress
12/27/2021HVAC-R and service water heating equipmentJeffrey Gearyenergy_progress
12/27/2021Shutoff dampersJeffrey Gearyenergy_progress
12/27/2021Interior lighting powerJeffrey Gearyenergy_progress
12/27/2021Concrete - Cast-In-PlaceJeffrey Gearyspecial
12/27/2021Fire-Resistant Penetrations and JointsJeffrey Gearyspecial
▾Documents — 31 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch2
08/31/2026B00653797-I1Request digital key ↗
08/31/2026B00653797-S1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00377823-I1Request digital key ↗
▸Applications & Permits2
▸BISBPP-5 - Authorization to the Department of Transportation1
09/13/2023340868314Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
09/13/2023340868314Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B00653797-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00653797-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B00653797-I1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWProgress Inspector Seal & Signature5
08/27/2026B00653797-I1Open ↗
08/27/2026B00653797-I1Open ↗
08/27/2026B00653797-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/27/2026B00653797-I1Open ↗
08/27/2026B00653797-I1Open ↗
08/27/2026B00653797-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/31/2026B00653797-I1Open ↗
08/31/2026B00653797-S1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
09/13/2023340868314Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/13/2023340868314Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B00653797-I1Open ↗
▸Safety & Tenant Protection2
▸BISBPP: STREET TREES SITE PLAN1
09/13/2023340868314Open ↗
▸DOB NOWStreet Tree Checklist1
08/31/2026B00653797-I1Open ↗
▸Inspections & Test Reports1
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
09/13/2023340868314Open ↗
▸Approvals, Objections & Sign-offs4
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
09/13/2023340868314Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)1
09/13/2023340868314Open ↗
▸BISNYS DEC TIDAL WETLANDS APPROVAL1
09/13/2023340868314Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/13/2026B00377823-I1Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
09/13/2023340868314Open ↗
▸Other Documents2
▸DOB NOWProperty Ownership Certification1
08/31/2026B00653797-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B00653797-I1Open ↗