1910Year Built
5Stories
K2Building Class
C5-5Zoning
4,537 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Multi-story retail building (2+) · Owner of record: JMW RESTAURANT CORP · 1,583 sf lot · 2.87 FAR built · Flood zone AE
Locations of Work
ArchitectureMechanical
Roof1p · 1 filing · 6 docs
Cellar1p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
VICTOR HUGO MARTINEZ, PE105/30/2025
SD DESIGN STUDIO LLC106/10/2020
PJM ARCHITECT, PC110/02/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JRL SKYLINE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MASTER FIRE MECH CORPGeneral Contractor303/21/2026
A & W CERTIFIED COOL SYSTGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NS ENGINEERING & CONSULTI3652105/30/2025
SD TESTING & INSPECTION S7010106/10/2020
PJM ARCHITECT PC1450110/02/2019
Building Lifecycle
All (22)Filed (3)Permit Issued (2)Signed Off (2)Violation (1)Special Inspection (14)
09/11/2025
Signed off — Alteration
INSTALLATION OF A NEW EXTERIOR EXHAUST DUCT AS PER PLANS, NO OTHER WORK TO BE DONE. NOT CHANGE IN USE, EGRESS OR OCCUPANCY.
M01220008-I1
06/12/2025
Permit issued — Mechanical Systems
M01220008-I1-MS
05/30/2025
Filed — Alteration
INSTALLATION OF A NEW EXTERIOR EXHAUST DUCT AS PER PLANS, NO OTHER WORK TO BE DONE. NOT CHANGE IN USE, EGRESS OR OCCUPANCY.
M01220008-I1
05/12/2025
Special inspection requirement — Post-installed Anchors
NARI MOTWANI
05/02/2025
Special inspection requirement — Final
VICTOR MARTINEZ
05/02/2025
Special inspection requirement — Mechanical Systems
NARI MOTWANI
06/10/2020
Filed — Alteration
PROPOSED TO TAKE NEW GAS TEST TO GET GAS TURN ON & INSTALL NEW (1) GAS HWH ON CELLAR.NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
M00351629-I1
05/25/2020
Special inspection requirement — Maintenance information
XIUCHENG LI
05/25/2020
Special inspection requirement — HVAC and service water heating system controls
XIUCHENG LI
05/25/2020
Special inspection requirement — HVAC and service water heating equipment
XIUCHENG LI
05/25/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIUCHENG LI
05/25/2020
Special inspection requirement — Energy Code Compliance Inspections
XIUCHENG LI
12/03/2019
Signed off — Alteration
M00230191-I1
11/19/2019
Permit issued — Mechanical Systems
M00230191-I1-MS
10/02/2019
Filed — Alteration
M00230191-I1
09/18/2019
Special inspection requirement — Mechanical Systems
Peter Mugavero
09/18/2019
Special inspection requirement — Final
Peter Mugavero
09/18/2019
Special inspection requirement — Energy Code Compliance Inspections
Peter Mugavero
09/18/2019
Special inspection requirement — HVAC and service water heating equipment
Peter Mugavero
09/18/2019
Special inspection requirement — HVAC and service water heating system controls
Peter Mugavero
09/18/2019
Special inspection requirement — HVAC insulation and sealing
Peter Mugavero
03/04/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offMASTER FIRE MECH CORP06/12/2025
DOB NOWMechanical SystemsSigned-offA & W CERTIFIED COOL SYST11/19/2019
BISOTISSUEDWINWAY DEVELOPMENT LLC09/08/2020
BISOTISSUEDCITIVIEW CONSTRUCTION INC03/20/2017
BISPLISSUEDSO PLUMBING & HEATING INC03/20/2017
BISOTISSUEDCEL SERVICES INC02/15/2017
BISFPISSUEDACTIVE FIRE EXTINGUISHER INC12/31/1991
BISFPISSUEDACTIVE FIRE EXTINGUSIHER CO INC03/20/1991
1 project · most recent 06/10/2020
Gas
FiledStatusContractorScope
06/10/2020——Gas
1 project · most recent 02/22/2022
FiledStatusContractorScope
02/22/2022CompleteMARTINEZ ELECTRICAL CONT1 meters, 1 new_meters
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
05/12/2025Post-installed AnchorsNARI MOTWANIspecial
05/02/2025FinalVICTOR MARTINEZprogress
05/02/2025Mechanical SystemsNARI MOTWANIspecial
05/25/2020Maintenance informationXIUCHENG LIenergy_progress
05/25/2020HVAC and service water heating system controls XIUCHENG LIenergy_progress
05/25/2020HVAC and service water heating equipment XIUCHENG LIenergy_progress
05/25/2020Fire-Resistant Penetrations and JointsXIUCHENG LIspecial
05/25/2020Energy Code Compliance InspectionsXIUCHENG LIprogress
09/18/2019Mechanical SystemsPeter Mugaverospecial
09/18/2019FinalPeter Mugaveroprogress
09/18/2019Energy Code Compliance InspectionsPeter Mugaveroprogress
09/18/2019HVAC and service water heating equipment Peter Mugaveroenergy_progress
09/18/2019HVAC and service water heating system controls Peter Mugaveroenergy_progress
09/18/2019HVAC insulation and sealing Peter Mugaveroenergy_progress
▾Documents — 59 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00351629-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/05/2026M00230191-I1Request digital key ↗
▸DOB NOWPlans/Sketch1
08/23/2026M01220008-I1Request digital key ↗
▸Applications & Permits8
▸BISWORK PERMIT APPLICATION5
09/08/2020140910370Open ↗
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION3
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
01/06/2017122986117Open ↗
▸Seals & Professional Certifications24
▸DOB NOWProgress Inspector Seal & Signature10
09/24/2026M00351629-I1Open ↗
09/24/2026M00351629-I1Open ↗
09/24/2026M00351629-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/24/2026M00351629-I1Open ↗
09/01/2026M01220008-I1Open ↗
09/01/2026M01220008-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026M00230191-I1Open ↗
08/13/2026M00351629-I1Open ↗
08/13/2026M01220008-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
01/06/2017122986117Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING1
03/18/2017140618437Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/06/2017122986117Open ↗
▸Environmental & Asbestos6
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
01/06/2017122986117Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/13/2026M00351629-I1Open ↗
08/13/2026M01220008-I1Open ↗
08/13/2026M00230191-I1Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
09/08/2020140910370Open ↗
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
01/06/2017122986117Open ↗
▸BISNYCECC ANALYSIS1
06/10/2020140910370Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
09/08/2020140910370Open ↗
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
01/06/2017122986117Open ↗
▸Filing & Intake Forms3
▸BISEFILING JOB APPLICATION COVER SHEET2
06/10/2020140910370Open ↗
03/18/2017140618437Open ↗
▸BISEFILING COVER SHEET1
01/06/2017122986117Open ↗