| Firm | Filings | Most Recent |
|---|---|---|
| Permanen Engineering International | 5 | 06/24/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| KAS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JB Buzco Plumbing | Plumbing | 2 | 07/08/2026 |
| Molloy Electric | Electrical | 1 | 03/22/2026 |
| A.E.H. Builders | Scaffold | 1 | 07/08/2026 |
| A.E.H. Builders | General Contractor | 1 | 11/19/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | JB Buzco Plumbing | 01/23/2020 |
| DOB NOW | Plumbing | Signed-off | JB Buzco Plumbing | 12/12/2019 |
| DOB NOW | Construction Fence | Signed-off | A.E.H. Builders | 11/18/2019 |
| BIS | OT | ISSUED | N/A | 08/03/2020 |
| BIS | — | ISSUED | A.E.H. Builders | 11/19/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/17/2025 | Complete | Molloy Electric | — |
| 09/09/2025 | Cancelled | Molloy Electric | General Wiring |
| 12/09/2019 | Complete | Ridge Electric | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/24/2021 | Maintenance information | Ralph Giorgio | energy_progress |
| 06/23/2021 | Maintenance information | Ralph Giorgio | energy_progress |
| 01/22/2020 | Maintenance information | Ralph Giorgio | energy_progress |
| 11/01/2019 | Final | Ralph Giorgio | progress |