Predominantly retail with other uses
25 NAVY STREET
BROOKLYN · BIN 3421810
💬 Discuss this project
1955Year Built
4Stories
K4Building Class
M1-4Zoning
289,262 sfGross Floor Area
10Units
LL97 Covered2 Active Violations 0 unresolved · 2 paperwork only ▸FDNY Report ↗
Predominantly retail with other uses · Owner of record: NYC Department of Small Business Services · 286,189 sf lot · 1.01 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofBrooklyn Urban Retail Partners, LLCUnder Construction1p · 1 filing · 19 docs
Floor 2Brooklyn Urban Retail Partners, LLCUnder Construction12p · 2 filings · 19 docs
Floor 1Brooklyn Urban Retail Partners, LLCUnder Construction13p · 1 filing · 19 docs
Site & exteriorSidewalk shed installation3p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Brooklyn Urban Retail Partners2010/13/2026
E.C. Contracting203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
High Line Engineering209/22/2026
Geodesign109/22/2026
Severud Associates108/17/2026
Dattner Architects108/13/2026
Architecture by Domani210/23/2019
Baileys Engineering111/20/2017
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Domani Consulting203/21/2026
AE Design Solution203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Tri Borough ScaffoldingScaffold707/08/2026
ZDGGeneral Contractor303/22/2026
Steiner Building NYCGeneral Contractor209/16/2026
David GlickmanElectrical103/21/2026
Air Depot Commercial RefrigerationGeneral Contractor109/30/2026
Navid MaqamiElectrical103/21/2026
G.N.T. MechanicalFire Protection110/10/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
High Line Engineering2920209/22/2026
Delta Testing Labs687208/17/2026
Building Lifecycle
All (56)Filed (8)Permit Issued (9)Signed Off (1)Violation (17)Objection (3)Special Inspection (18)
10/13/2026
Objection raised — Other
10/09/2026
Permit issued — Sprinklers
B01442092-S3-EW-SP
09/29/2026
Permit issued — Mechanical Systems
B01442092-S4-MS
09/22/2026
Filed — Alteration
New shaft opening for new elevator that goes from 1st to 2nd floor. provide support for new elevator pit at 1st floor. New Slab infill at 2nd floor and new opening for stair A.
B01442092-S3
09/22/2026
Filed — Alteration
New shaft opening for new elevator that goes from 1st to 2nd floor. provide support for new elevator pit at 1st floor. New Slab infill at 2nd floor and new opening for stair A.
B01442092-S4
09/22/2026
Filed — Alteration
New shaft opening for new elevator that goes from 1st to 2nd floor. provide support for new elevator pit at 1st floor. New Slab infill at 2nd floor and new opening for stair A.
B01442092-S2
09/21/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
09/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
Ruslan Nagorny
09/17/2026
Special inspection requirement — Mechanical Systems
Ruslan Nagorny
09/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ruslan Nagorny
09/17/2026
Special inspection requirement — Final
Ruslan Nagorny
09/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Ruslan Nagorny
09/17/2026
Special inspection requirement — Shutoff dampers
Ruslan Nagorny
09/17/2026
Special inspection requirement — Maintenance information
Ruslan Nagorny
09/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
Ruslan Nagorny
09/17/2026
Special inspection requirement — Sprinkler Systems
Ruslan Nagorny
09/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ruslan Nagorny
09/15/2026
Permit issued — Structural
B01442092-S1-ST
09/15/2026
Permit issued — General Construction
B01442092-I1-GC
08/17/2026
Filed — Alteration
New shaft opening for new elevator that goes from 1st to 2nd floor. provide support for new elevator pit at 1st floor. New Slab infill at 2nd floor and new opening for stair A.
B01442092-S1
08/13/2026
Filed — Alteration
New shaft opening for new elevator that goes from 1st to 2nd floor. provide support for new elevator pit at 1st floor. New Slab infill at 2nd floor and new opening for stair A.
B01442092-I1
08/12/2026
Special inspection requirement — Lighting controls
RICHARD GREENWALD
08/12/2026
Special inspection requirement — Energy Code Compliance Inspections
RICHARD GREENWALD
08/12/2026
Special inspection requirement — Interior lighting power
RICHARD GREENWALD
08/12/2026
Special inspection requirement — Fenestration areas
RICHARD GREENWALD
08/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
RICHARD GREENWALD
08/06/2026
Special inspection requirement — Final
RICHARD GREENWALD
08/31/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/31/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/21/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/21/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/21/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/21/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/21/2019
Signed off — Alteration
B00002679-I1
10/25/2019
Objection resolved — Addressed
10/24/2019
Objection raised — Structural
10/23/2019
Filed — No Work
B00242950-P1
10/17/2019
Filed — No Work
B00242950-I1
06/21/2019
Violation issued (ECB, closed)
Construction
06/21/2019
Violation issued (ECB, closed)
Construction
06/21/2019
Violation issued (ECB, closed)
Unknown
05/21/2019
Violation issued (ECB, closed)
Unknown
05/21/2019
Violation issued (ECB, closed)
Unknown
05/21/2019
Violation issued (ECB, closed)
Construction
05/21/2019
Violation issued (ECB, closed)
Unknown
05/21/2019
Violation issued (ECB, closed)
Unknown
05/21/2019
Violation issued (ECB, closed)
Unknown
05/21/2019
Violation issued (ECB, closed)
Unknown
04/01/2019
Permit issued — Sidewalk Shed
B00002679-I1-SH
11/27/2018
Permit issued — Sidewalk Shed
B00002679-I1-SH
09/08/2018
Violation issued (ECB, closed)
Construction
05/16/2018
Permit issued — Sidewalk Shed
B00002679-I1-SH
03/30/2018
Permit issued — Sidewalk Shed
B00002679-I1-SH
11/20/2017
Filed — Alteration
B00002679-I1
11/20/2017
Permit issued — Sidewalk Shed
B00002679-I1-SH
11/17/2017
Special inspection requirement — Final
PAUL BAILEY
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedG.N.T. Mechanical10/09/2026
DOB NOWMechanical SystemsPermit IssuedAir Depot Commercial Refrigeration09/29/2026
DOB NOWStructuralPermit IssuedSteiner Building NYC09/15/2026
DOB NOWGeneral ConstructionPermit IssuedSteiner Building NYC09/15/2026
DOB NOWSidewalk ShedSigned-offTri Borough Scaffolding04/01/2019
DOB NOWSidewalk ShedSigned-offTri Borough Scaffolding11/27/2018
DOB NOWSidewalk ShedSigned-offTri Borough Scaffolding05/16/2018
DOB NOWSidewalk ShedSigned-offTri Borough Scaffolding03/30/2018
DOB NOWSidewalk ShedSigned-offTri Borough Scaffolding11/20/2017
BIS—ISSUEDZDG11/27/2019
BISSDISSUEDSirina Fire Protection05/17/2019
BIS—ISSUEDZDG02/25/2019
BISEQISSUEDZDG09/04/2018
BISSDISSUEDSirina Fire Protection05/17/2018
BISPLISSUEDAspro Plumbing11/14/2017
BIS—ISSUEDZDG11/09/2017
BIS—ISSUEDZDG06/29/2017
1 project · most recent 09/22/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
09/22/2026Permit IssuedAir Depot Commercial RefrigerationAir Conditioning Systems
Cooling
Daikin RXYA96AAYDA 92,000 BTU · Vrf Outdoor ×1
1 project · most recent 09/22/2026
Sprinkler System
FiledStatusContractorScope
09/22/2026Permit IssuedG.N.T. MechanicalSprinkler System
1 project · most recent 09/22/2026
FiledStatusContractorScope
09/22/2026———
5 projects · most recent 09/05/2019
General Wiring
FiledStatusContractorScope
09/05/2019CompleteInter Connection ElectricGeneral Wiring
02/06/2019CancelledInter Connection ElectricGeneral Wiring
12/18/2018CompleteThyssenkrupp Elevator Co—
12/18/2018CompleteThyssenkrupp Elevator Co—
04/02/2018CompleteInter Connection Electric—
1 project · most recent 09/22/2026
FiledStatusContractorScope
09/22/2026Permit IssuedG.N.T. Mechanical2 scope_items
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
09/21/2026Excavations - Sheeting, Shoring, and Bracing—special
09/17/2026HVAC-R and service water heating equipmentRuslan Nagornyenergy_progress
09/17/2026Mechanical SystemsRuslan Nagornyspecial
09/17/2026Fire-Resistant Penetrations and JointsRuslan Nagornyspecial
09/17/2026FinalRuslan Nagornyprogress
09/17/2026HVAC-R and service water piping design and insulationRuslan Nagornyenergy_progress
09/17/2026Shutoff dampersRuslan Nagornyenergy_progress
09/17/2026Maintenance informationRuslan Nagornyenergy_progress
09/17/2026HVAC-R and service water heating system controlsRuslan Nagornyenergy_progress
09/17/2026Sprinkler SystemsRuslan Nagornyspecial
09/17/2026Fire-Resistant Penetrations and JointsRuslan Nagornyspecial
08/12/2026Lighting controlsRICHARD GREENWALDenergy_progress
08/12/2026Energy Code Compliance InspectionsRICHARD GREENWALDprogress
08/12/2026Interior lighting powerRICHARD GREENWALDenergy_progress
08/12/2026Fenestration areasRICHARD GREENWALDenergy_progress
08/12/2026Fire-Resistant Penetrations and JointsRICHARD GREENWALDspecial
08/06/2026FinalRICHARD GREENWALDprogress
11/17/2017FinalPAUL BAILEYprogress
▾Documents — 176 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch3
09/03/2026B00002679-I1Request digital key ↗
08/16/2026B01442092-I1Request digital key ↗
08/16/2026B01442092-S1Request digital key ↗
▸DOB NOWPlans/Sketch - Temporary Place of Assembly2
09/02/2026B00242950-I1Request digital key ↗
08/15/2026B00242950-P1Request digital key ↗
▸Applications & Permits33
▸BISPLAN / WORK APPROVAL APPLICATION17
02/25/2021321183633Open ↗
05/28/2019321637387Open ↗
05/03/2019321183633Open ↗
Showing 3 of 17 on file for this type
▸BISWORK PERMIT APPLICATION13
11/27/2019321183633Open ↗
10/10/2019321183633Open ↗
05/20/2019321713927Open ↗
Showing 3 of 13 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
10/08/2019321713927Open ↗
04/08/2019321713927Open ↗
03/20/2019321637387Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISEASEMENT AND RESTRICTIVE DECLARATIONS - SUPPPORTING DOCUMENTATION3
04/14/2017321183633Open ↗
04/14/2017321183633Open ↗
04/14/2017321183633Open ↗
▸BISZONING DIAGRAM1
04/14/2017321183633Open ↗
▸BISFLOOD ZONE DESIGN CERTIFICATION1
08/31/2018340629957Open ↗
▸BISVERIFY TAX LOT1
03/16/2022321183633Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
08/24/2021321183633Open ↗
▸Seals & Professional Certifications31
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
12/26/2019321183633Open ↗
11/20/2019321713927Open ↗
10/12/2019340629957Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
10/01/2026B01442092-S4Open ↗
10/01/2026B01442092-S3Open ↗
10/01/2026B01442092-S2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
10/01/2026B01442092-S4Open ↗
10/01/2026B01442092-S4Open ↗
09/01/2026B01442092-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
10/01/2026B01442092-S4Open ↗
10/01/2026B01442092-S4Open ↗
09/01/2026B01442092-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
08/31/2018340629957Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
08/31/2018340629957Open ↗
▸Trade Schedules & Equipment7
▸BISFA - FDNY APPROVAL : FD-FAA2
12/26/2019321637387Open ↗
09/27/2019321637387Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
08/24/2021321183633Open ↗
▸BISEQUIPMENT USE PERMITS1
08/24/2021321183633Open ↗
▸BISSCHEDULE B - PLUMBING1
05/03/2019321183633Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/31/2018321713927Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
04/08/2019321713927Open ↗
▸Safety & Tenant Protection6
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE2
06/28/2017321183633Open ↗
06/28/2017321183633Open ↗
▸BISSTREET TREE CHECKLIST2
03/17/2022321183633Open ↗
02/25/2019321183633Open ↗
▸BISSTREET TREE SIGNOFF1
03/03/2022321183633Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
06/28/2017321183633Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
12/26/2019321183633Open ↗
11/09/2017321183633Open ↗
11/09/2017321183633Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
06/14/2021321183633Open ↗
08/05/2016321183633Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
08/24/2021321183633Open ↗
▸Inspections & Test Reports22
▸BISTECHNICAL REPORT: RESPONSIBILITY8
06/14/2021321183633Open ↗
06/14/2021321183633Open ↗
06/07/2019321183633Open ↗
Showing 3 of 8 on file for this type
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT6
04/10/2019321183633Open ↗
04/10/2019321183633Open ↗
04/10/2019321183633Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
12/26/2019321183633Open ↗
06/28/2017321183633Open ↗
▸BISTECHNICAL REPORT: PILE DRIVING1
12/26/2019321183633Open ↗
▸BISHYDRO FLOW TEST LETTER1
04/24/2018321713927Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
11/01/2016321183633Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
07/03/2017321183633Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
04/24/2018321713927Open ↗
▸BISDEMOLITION (DM) JOB SIGNOFF1
03/03/2022321183633Open ↗
▸Approvals, Objections & Sign-offs26
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST12
02/08/2021321183633Open ↗
11/12/2020321183633Open ↗
08/14/2020321183633Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
10/01/2026B01442092-S2Open ↗
10/01/2026B01442092-S4Open ↗
10/01/2026B01442092-S3Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
10/10/2019321183633Open ↗
04/24/2018321713927Open ↗
04/14/2017321183633Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
02/25/2021321183633Open ↗
04/12/2017321183633Open ↗
02/28/2017321183633Open ↗
▸BISSUPERSEDING LETTER1
11/27/2019321183633Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPER1
03/05/2021321183633Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT7
02/18/2020321637387Open ↗
02/14/2020321713927Open ↗
11/18/2019321637387Open ↗
Showing 3 of 7 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
07/03/2017321183633Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
07/03/2017321183633Open ↗
▸Filing & Intake Forms21
▸BISBOROUGH INTAKE FORM10
03/10/2020321637387Open ↗
02/18/2020321637387Open ↗
02/14/2020321713927Open ↗
Showing 3 of 10 on file for this type
▸BISADDITIONAL INFORMATION6
03/05/2021321183633Open ↗
10/12/2019340629957Open ↗
10/02/2019340629957Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET4
02/06/2018321713927Open ↗
08/16/2017321637387Open ↗
07/25/2016321183633Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
08/31/2018340629957Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM1
08/05/2016321183633Open ↗
▸BISFEMA ELEVATION CERT (086-0-33)/ FLOODPROOFING CERT (086-0-34)1
03/05/2021321183633Open ↗