| Owner | Filings | Most Recent |
|---|---|---|
| ATALANTA CONDOMINIUM | 41 | 07/08/2026 |
| BROWN HARRIS STEVENS | 12 | 07/08/2026 |
| PRATT CONSTRUCTION | 10 | 07/08/2026 |
| ANDREWS BUILDING | 49 | 03/22/2026 |
| ANDREW BOILDING CORP | 1 | 03/22/2026 |
| NORTH MOORE TOWNER LLC | 71 | 03/22/2026 |
| 25 NORTH MOORE ASSOC. | 8 | 03/22/2026 |
| 25 NORTH MOORE ASSOCIA | 1 | 03/22/2026 |
| OWNER OF PRESIMSES | 1 | 03/22/2026 |
| TO THE OWNER OF:25 NORTH | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| P.A. COLLINS PE | 11 | 09/29/2025 |
| WEDDLE & GILMORE ARCHITECTS, PLLC | 4 | 06/13/2024 |
| STUDIO OFFICINA ARCHITECTURE PLLC | 2 | 04/26/2024 |
| TOHFAZ UDDIN PE PC | 2 | 03/04/2024 |
| ABS ENGINEERING, PLLC | 2 | 11/21/2023 |
| PARAGON ENGINEERING CONSULTANTS | 2 | 07/20/2023 |
| E4P CONSULTING ENGINEERING PLLC | 1 | 06/22/2023 |
| ROBERT ROBINOWITZ DESIGN | 1 | 05/30/2023 |
| OPENSHOP ARCHITECTURE | 3 | 03/24/2023 |
| D'ANTONIO CONSULTING ENGINEERS | 4 | 01/06/2023 |
| NICOLAS BARATTO ARCHITECT P.C. | 1 | 01/05/2023 |
| JACK GREEN ASSOCIATES | 1 | 01/04/2023 |
| DHD ARCHITECTURE DESIGN PLLC | 1 | 05/04/2022 |
| DANIEL HEIGHES WISMER ARCHITECT PC | 2 | 10/13/2021 |
| ENGINEERING PROFESSIONAL SERVICE P. | 1 | 08/09/2021 |
| HARPER ARCHITECTURE, PC | 1 | 05/18/2021 |
| ASHRAF CORP | 1 | 04/08/2021 |
| GREEN DESIGN | 1 | 10/16/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| CODE | 34 | 03/21/2026 |
| DVA Advisors | 2 | 03/21/2026 |
| Rigid Structural Design, LLC | 1 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 2 | 03/21/2026 |
| BURNHAM NATIONWIDE INC | 6 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 5 | 03/21/2026 |
| AGOUTI CONSTRUCTION CONSULTING | 4 | 03/21/2026 |
| BOUTIQKEY | 6 | 03/21/2026 |
| LLOYD NOEL BUILDING CONSULTANT | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| REGELE BUILDERS, INC | General Contractor | 16 | 08/25/2026 |
| FORTE EXPRESS P & H INC | Plumbing | 7 | 07/08/2026 |
| PRAT ENTERPRISES CORP | General Contractor | 6 | 03/21/2026 |
| PRATT CONSTRUCTION & REST | General Contractor | 4 | 07/08/2026 |
| HARPER DESIGN BUILD INC | General Contractor | 4 | 07/08/2026 |
| SYNC CONSTRUCTION LLC | General Contractor | 3 | 03/21/2026 |
| PERFECTAIRE CO INC | General Contractor | 3 | 04/09/2026 |
| V. DISALVO CONTRACTING CO | General Contractor | 3 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| CS BRIDGE CORP | General Contractor | 2 | 07/08/2026 |
| GALLERY RESTORATION LTD | General Contractor | 2 | 03/21/2026 |
| HENRY MYERS P & H, INC | Plumbing | 2 | 07/08/2026 |
| KLDNY INC | General Contractor | 2 | 03/21/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 2 | 03/21/2026 |
| TIMOTHY MCDONALD | Electrical | 1 | 03/21/2026 |
| VAN VASSELL | Electrical | 1 | 03/21/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 1 | 07/08/2026 |
| BILT/DFI INC | General Contractor | 1 | 07/08/2026 |
| ANTONIO CERIELLO ELEC INC | Electrical | 1 | 03/22/2026 |
| FORM FACTORY CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| LTB MECHANICAL CORP | General Contractor | 1 | 07/08/2026 |
| TOKA HOME, LLC | General Contractor | 1 | 07/08/2026 |
| ARCON PLBG SOLUTIONS | Plumbing | 1 | 07/08/2026 |
| ASTORIA P & H CORP | Plumbing | 1 | 07/08/2026 |
| NEW MILLENNIUM P & H CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| QUALITY TESTING, LLC | 7344 | 17 | 09/29/2025 |
| P.A.COLLINS INSPECTIONS P | 2168 | 2 | 05/22/2024 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 04/26/2024 |
| ABS ENGINEERING, PLLC | 4835 | 3 | 11/21/2023 |
| HT ENGINEERING, PLLC | 6274 | 1 | 06/22/2023 |
| D'ANTONIO CONSULTING ENGI | 931 | 4 | 01/06/2023 |
| SKYLINE ENGINEERING, PLLC | 267 | 1 | 01/05/2023 |
| JACK GREEN ASSOCIATES | 422 | 1 | 01/04/2023 |
| OUTSOURCE SPECIAL INSPECT | 2827 | 1 | 09/02/2022 |
| INTEGRITY CONSULTING SERV | 666 | 1 | 10/04/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | REGELE BUILDERS, INC | 08/24/2026 |
| DOB NOW | General Construction | Permit Issued | REGELE BUILDERS, INC | 08/24/2026 |
| DOB NOW | Plumbing | Permit Issued | FORTE EXPRESS P & H INC | 05/26/2026 |
| DOB NOW | Plumbing | Permit Issued | FORTE EXPRESS P & H INC | 02/26/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | PERFECTAIRE CO INC | 02/25/2026 |
| DOB NOW | General Construction | Permit Issued | REGELE BUILDERS, INC | 02/13/2026 |
| DOB NOW | Structural | Signed-off | REGELE BUILDERS, INC | 02/12/2026 |
| DOB NOW | Plumbing | Permit Issued | FORTE EXPRESS P & H INC | 05/28/2025 |
| DOB NOW | Plumbing | Permit Issued | FORTE EXPRESS P & H INC | 03/05/2025 |
| DOB NOW | General Construction | Permit Issued | REGELE BUILDERS, INC | 02/25/2025 |
| DOB NOW | Structural | Signed-off | REGELE BUILDERS, INC | 02/25/2025 |
| DOB NOW | General Construction | Signed-off | SYNC CONSTRUCTION LLC | 06/12/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | PERFECTAIRE CO INC | 06/06/2024 |
| DOB NOW | Plumbing | Signed-off | ASTORIA P & H CORP | 06/05/2024 |
| DOB NOW | Plumbing | Permit Issued | FORTE EXPRESS P & H INC | 05/31/2024 |
| DOB NOW | Mechanical Systems | Signed-off | DEMAR PLUMBING CORP | 04/15/2024 |
| DOB NOW | Mechanical Systems | Signed-off | LTB MECHANICAL | 03/28/2024 |
| DOB NOW | General Construction | Permit Issued | REGELE BUILDERS, INC | 03/11/2024 |
| DOB NOW | Structural | Signed-off | REGELE BUILDERS, INC | 03/11/2024 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 03/06/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CS BRIDGE CORP | 03/06/2024 |
| DOB NOW | Plumbing | Permit Issued | FORTE EXPRESS P & H INC | 02/27/2024 |
| DOB NOW | Plumbing | Signed-off | HENRY MYERS P & H, INC | 11/02/2023 |
| DOB NOW | Plumbing | Signed-off | HENRY MYERS P & H, INC | 07/19/2023 |
| DOB NOW | General Construction | Signed-off | TOKA HOME, LLC | 07/13/2023 |
| DOB NOW | Structural | Signed-off | REGELE BUILDERS, INC | 03/17/2023 |
| DOB NOW | General Construction | Permit Issued | REGELE BUILDERS, INC | 03/17/2023 |
| DOB NOW | Plumbing | Permit Issued | FORTE EXPRESS P & H INC | 02/28/2023 |
| DOB NOW | General Construction | Signed-off | V. DISALVO CONTRACTING CO | 02/10/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | V. DISALVO CONTRACTING CO | 02/10/2023 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 09/27/2022 |
| DOB NOW | General Construction | Signed-off | FORM FACTORY CONSTRUCTION | 09/21/2022 |
| DOB NOW | Structural | Signed-off | REGELE BUILDERS, INC | 09/06/2022 |
| DOB NOW | General Construction | Permit Issued | REGELE BUILDERS, INC | 09/06/2022 |
| DOB NOW | Plumbing | Signed-off | ORBIT PLBG & HTG INC | 06/15/2022 |
| DOB NOW | General Construction | Signed-off | KLDNY | 05/18/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HARPER DESIGN BUILD INC | 03/31/2022 |
| DOB NOW | Plumbing | Signed-off | NEW MILLENNIUM P & H CORP | 01/01/2022 |
| DOB NOW | General Construction | Signed-off | BILT/DFI INC | 12/20/2021 |
| DOB NOW | General Construction | Signed-off | GALLERY RESTORATION LTD | 09/17/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/22/2024 | Permit Issued | PERFECTAIRE CO INC | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems | Cooling Mitsubishi Electric PEFY-P12NMAU-E3 1 tons · Vrf Indoor ×8 PEFY-P24NMAU-E3 2 tons · Vrf Indoor ×6 PVFY-P18NAMU-E1 18,000 BTU · Vrf Indoor ×6 CMB-P1012NU-JA1-BV Vrf Outdoor ×4 PEFY-P36NMAU-E3 3 tons · Vrf Indoor ×4 PVFY-P24NAMU-E1 2 tons · Vrf Indoor ×4 PEFY-P06NMSU-ER2 6,000 BTU · Vrf Indoor ×2 PEFY-P18NMAU-E3 18,000 BTU · Vrf Indoor ×2 PEFY-P30NMAU-E3 30,000 BTU · Vrf Indoor ×2 PURY-EP144TNU-A 144,000 BTU · Vrf Outdoor ×2 PURY-EP168TNU-A 168,000 BTU · Vrf Outdoor ×2 Atmosair FC-400FM ×2 Heating Ventilation Fantech DEDPV-705 150 CFM · Exhaust Fan ×2 PRIOAIR 10 EC 1,135 CFM · Exhaust Fan ×2 PRIOAIR 8 EC 735 CFM · Exhaust Fan ×2 Nortek NORTEC RH DUCT ×4 Atmosair MATTERHORN 1000 ×2 Pennbarry SX095QCGP 1,200 CFM · Exhaust Fan ×2 Ducts & Piping N/A n/a Ductwork |
| 01/04/2023 | Permit Issued | V. DISALVO CONTRACTING CO | Air Conditioning Systems | Cooling Florida Heat Pump LV015 15,000 BTU · Heat Pump Outdoor ×4 LV018 18,000 BTU · Heat Pump Outdoor ×3 LV07 7,000 BTU · Heat Pump Outdoor ×3 LM024 24,000 BTU · Condensing Unit ×2 LV024 24,000 BTU · Heat Pump Outdoor ×2 LM036 36,000 BTU · Condensing Unit ×1 LM048 48,000 BTU · Condensing Unit ×1 LM07 7,000 BTU · Condensing Unit ×1 LV012 12,000 BTU · Heat Pump Outdoor ×1 LV036 36,000 BTU · Heat Pump Outdoor ×1 LV048 48,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2025 | Permit Issued | FORTE EXPRESS P & H INC | Gas, Water/Sanitary |
| 09/29/2025 | Permit Issued | FORTE EXPRESS P & H INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | G.E.O. ELECTRIC CORP | General Wiring |
| 05/06/2026 | Permit Issued | EIS ELECTRIC CORP DBA | General Wiring |
| 03/11/2025 | Permit Issued | MODERN VOLTAGE NYC INC | 1 meters, 1 new_meters |
| 03/11/2025 | Permit Issued | MODERN VOLTAGE NYC INC | General Wiring |
| 02/12/2025 | Permit Issued | ECNY ELEC'L CONTR'S, INC | General Wiring |
| 08/07/2024 | Complete | ASTER ELECTRIC, INC | — |
| 06/13/2024 | Complete | TWINTECH ELECTRIC INC | General Wiring |
| 11/02/2023 | Complete | ECNY ELEC'L CONTR'S, INC | General Wiring |
| 10/10/2023 | Complete | ECNY ELEC'L CONTR'S, INC | General Wiring |
| 07/21/2023 | Complete | BP ELECTRIC & COOLING INC | General Wiring |
| 10/17/2022 | Complete | TM SELECT ELECTRIC CORP | General Wiring |
| 07/28/2022 | Complete | ANTONIO CERIELLO ELEC INC | General Wiring |
| 05/03/2022 | Complete | DELTA PHASE ELEC'L CORP. | General Wiring |
| 10/27/2021 | Complete | DEMAND ELECTRIC INC | General Wiring |
| 06/24/2021 | Complete | SUPER CHARGED ELEC. INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2025 | Permit Issued | REGELE BUILDERS, INC | Steel, Concrete |
| 03/29/2022 | Signed-off | REGELE BUILDERS, INC | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/29/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/02/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/28/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/11/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/20/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 09/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/05/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/07/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/15/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/10/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/25/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/28/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/03/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/21/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/26/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/30/2026 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 01/30/2026 | Post-installed Anchors | KEVIN SNEDEKER | special |
| 10/02/2025 | Post-installed Anchors | KEVIN SNEDEKER | special |
| 10/02/2025 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 09/11/2025 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 09/11/2025 | Post-installed Anchors | KEVIN SNEDEKER | special |
| 05/06/2025 | Post-installed Anchors | KEVIN SNEDEKER | special |
| 05/06/2025 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 02/24/2025 | Post-installed Anchors | KEVIN SNEDEKER | special |
| 02/24/2025 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 02/24/2025 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 02/24/2025 | Post-installed Anchors | KEVIN SNEDEKER | special |
| 08/21/2024 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 08/21/2024 | Tenant Protection Plan Compliance | KEVIN SNEDEKER | special |
| 08/21/2024 | Final | KEVIN SNEDEKER | progress |
| 08/21/2024 | Sprayed fire-resistant materials | KEVIN SNEDEKER | special |
| 06/11/2024 | Sprayed fire-resistant materials | KEVIN SNEDEKER | special |
| 06/11/2024 | Tenant Protection Plan Compliance | — | special |
| 06/11/2024 | Final | KEVIN SNEDEKER | progress |
| 06/11/2024 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 05/17/2024 | Final | Michael Gilmore | progress |
| 05/17/2024 | Sprayed fire-resistant materials | KEVIN SNEDEKER | special |
| 05/17/2024 | Fire-Resistant Penetrations and Joints | KEVIN SNEDEKER | special |
| 04/18/2024 | Energy Code Compliance Inspections | Louisa Anderson | progress |
| 04/18/2024 | Fire-Resistant Penetrations and Joints | William Ryan | special |