| Owner | Filings | Most Recent |
|---|---|---|
| HNL MANAGEMENT | 10 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/11/2023 | $1.4M | — | GXL REALTY LLC → Private party | $644/sf building |
| 01/23/2019 | $1.2M | — | Private party → GXL REALTY LLC | $554/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BASSIRI | 1 | 09/06/2023 |
| CLIP ARCHITECTS | 7 | 05/19/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| MODERN BUILDING CONSULTANT | 7 | 03/21/2026 |
| ECDESIGN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JZ CONSTRUCTION GROUP INC | General Contractor | 3 | 03/21/2026 |
| KLE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| INNOVATION PLUMBING LLC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GREAT WALL CONSULTANT P.E | 5633 | 7 | 05/19/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | KLE CONSTRUCTION INC | 09/07/2023 |
| DOB NOW | Plumbing | Signed-off | INNOVATION PLUMBING LLC | 11/09/2022 |
| DOB NOW | General Construction | Signed-off | JZ CONSTRUCTION GROUP INC | 11/02/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/28/2023 | Complete | A.C. MORGAN ELECTRIC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/21/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/24/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/13/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/30/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/13/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/06/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/06/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/19/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 05/19/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 04/11/2023 | Fire-Resistance Rated Construction | Xiong Wei Wu | progress |
| 04/11/2023 | Fenestration air leakage | Xiong Wei Wu | energy_progress |
| 04/11/2023 | Interior lighting power | Xiong Wei Wu | energy_progress |
| 04/11/2023 | Insulation placement and R values | Xiong Wei Wu | energy_progress |
| 04/11/2023 | Fenestration areas | Xiong Wei Wu | energy_progress |
| 04/11/2023 | Fenestration and door U-factor and product ratings | Xiong Wei Wu | energy_progress |
| 04/11/2023 | Air barrier - visual inspection | Xiong Wei Wu | energy_progress |
| 04/11/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 04/11/2023 | Air barrier — testing | Xiong Wei Wu | energy_progress |
| 04/11/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 03/31/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 03/31/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 03/08/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 03/08/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 01/03/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 01/03/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |