← Back
Factory, industrial, semi-fireproof
250 AVENUE W
BROOKLYN · Gravesend (East)-Homecrest · BIN 3194341
💬 Discuss this project
1931Year Built
2Stories
F4Building Class
M1-1Zoning
15,195 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Factory, industrial, semi-fireproof · Owner of record: 238-250 AVENUE W LLC · 12,964 sf lot · 1.17 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Floor 22p · 1 filing · 3 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
238-250 AVENUE W LLC C/O403/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/22/2021$6.5M—FW FORMING CORP. → 238-250 AVENUE W LLC$428/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
EDIFICE DRAFTING AND SERVICES306/10/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
4444 PPPP CORP603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ACE MAINTENANCE USA LLCGeneral Contractor104/09/2026
ARCO PLBG AND HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MARCH CHADWICK, ARCHITECT2253105/08/2025
Building Lifecycle
All (28)Filed (3)Permit Issued (2)Signed Off (2)Violation (6)Inspection (2)Objection (8)Special Inspection (5)
01/26/2026
Signed off — Alteration
Replace existing plumbing fixtures on existing roughing in same location as existing fixtures at second floor.
B01220641-S1
01/07/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/29/2025
Signed off — Alteration
Replace existing plumbing fixtures on existing roughing in same location as existing fixtures at second floor.
B01220641-I1
12/23/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
08/13/2025
Violation issued (ECB, closed)
Construction
08/13/2025
Violation issued (ECB, closed)
Construction
06/23/2025
Permit issued — Plumbing
B01220641-S1-PL
06/10/2025
Filed — Alteration
Replace existing plumbing fixtures on existing roughing in same location as existing fixtures at second floor.
B01220641-S1
06/06/2025
Permit issued — General Construction
B01220641-I1-GC
05/08/2025
Filed — Alteration
Replace existing plumbing fixtures on existing roughing in same location as existing fixtures at second floor.
B01220641-I1
05/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MARCH CHADWICK
05/08/2025
Special inspection requirement — Energy Code Compliance Inspections
MARCH CHADWICK
05/08/2025
Special inspection requirement — Fire-Resistance Rated Construction
MARCH CHADWICK
05/08/2025
Special inspection requirement — Insulation placement and R values
MARCH CHADWICK
05/05/2025
Special inspection requirement — Final
MARCH CHADWICK
04/18/2025
Violation issued (ECB, closed)
Construction
04/18/2025
Violation issued (ECB, closed)
Construction
03/28/2022
Objection raised — Accessibility
03/28/2022
Objection raised — Admin
03/28/2022
Objection raised — Fire_Protection
03/28/2022
Objection raised — Structural
03/28/2022
Objection raised — Zoning
03/28/2022
Objection raised — Accessibility
03/28/2022
Objection raised — Structural
03/28/2022
Objection raised — Accessibility
03/22/2022
Filed — Alteration
Removing non-bearing partitions and build new partitions for new floor layout at second floor. No change in Use, Egress or Occupancy.
B00699692-I1
10/20/2000
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/20/2000
Violation issued (DOB, closed)
VW*-VIOLATION - WORK W/O PERMIT DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offARCO PLBG AND HTG INC06/23/2025
DOB NOWGeneral ConstructionSigned-offACE MAINTENANCE USA LLC06/06/2025
3 projects · most recent 07/09/2025
General Wiring
FiledStatusContractorScope
07/09/2025CompleteRACK ELECTRIC INCGeneral Wiring
05/02/2023Permit IssuedKINGS ELECTRIC CO., INC.General Wiring
12/07/2021CompleteNEW PHASE ELEC'L CONTR'SGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
01/07/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/23/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
05/08/2025Fire-Resistant Penetrations and JointsMARCH CHADWICKspecial
05/08/2025Energy Code Compliance InspectionsMARCH CHADWICKprogress
05/08/2025Fire-Resistance Rated ConstructionMARCH CHADWICKprogress
05/08/2025Insulation placement and R valuesMARCH CHADWICKenergy_progress
05/05/2025FinalMARCH CHADWICKprogress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/21/2026B01220641-S1Request digital key ↗
08/21/2026B01220641-I1Request digital key ↗
08/15/2026B00699692-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/21/2026B01220641-I1Open ↗
08/21/2026B01220641-S1Open ↗
08/13/2026B00699692-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026B01220641-I1Open ↗
08/23/2026B01220641-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026B01220641-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/21/2026B01220641-I1Open ↗
08/21/2026B01220641-S1Open ↗
08/13/2026B00699692-I1Open ↗