| Owner | Filings | Most Recent |
|---|---|---|
| YESHIVA UNIVERSITY | 97 | 09/03/2026 |
| ACE GROUP NY | 18 | 09/07/2026 |
| KAJ NY CONSTRUCTION | 12 | 08/29/2026 |
| RELIABLE RESTORATION NY LLC | 11 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| EOC-NY | 5 | 06/30/2026 |
| FL&M ENGINEERING DESIGN &INSPECTION | 4 | 06/24/2026 |
| VOLUME SPACE CONSULTING INC. | 5 | 06/23/2026 |
| MARPILLERO POLLAK ARCHITECTS | 3 | 10/31/2025 |
| ROBERT DERECTOR ASSOCIATES | 10 | 10/21/2025 |
| BURO EHRING ENGINEERING P.C. | 4 | 05/05/2025 |
| APPLIED DESIGN INITIATIVE, LLC | 7 | 04/08/2025 |
| TOHFAZ UDDIN PE PC | 9 | 02/08/2024 |
| ASR ENGINEERING PC | 2 | 08/01/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN STUDIO | 6 | 03/21/2026 |
| MMSR CONSULTING GROUP LLC | 8 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 16 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | 18 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 2 | 03/21/2026 |
| P WOLFE CONSULTANTS | 16 | 03/21/2026 |
| THE GREEN STUDIO | 1 | 03/21/2026 |
| MILLENNIUM DESIGNS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JRM CONSTRUCTION MGMT LLC | General Contractor | 15 | 07/08/2026 |
| ACE GROUP NY CORP | General Contractor | 13 | 09/07/2026 |
| RELIABLE RESTORATION.NY | General Contractor | 9 | 03/21/2026 |
| ICON CONTRACTING GROUP | General Contractor | 8 | 09/03/2026 |
| OMARA ORGANIZATION INC | General Contractor | 7 | 07/08/2026 |
| KAJ NY CONSTRUCTION INC | General Contractor | 4 | 06/28/2026 |
| R.N.K. ROMEO CONST INC | General Contractor | 4 | 04/09/2026 |
| AMERICAN CONSTRUCTION MAN | General Contractor | 4 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 4 | 07/08/2026 |
| MEGA PLBG CORP | Plumbing | 3 | 07/08/2026 |
| SOCOL, JEFFREY | Electrical | 2 | 03/21/2026 |
| PROLINE CONTRACTING GROUP | General Contractor | 1 | 07/02/2026 |
| NYC IRONWORKERS LOCAL 40 | Electrical | 1 | 03/21/2026 |
| MOLLER, GEORGE | Electrical | 1 | 03/21/2026 |
| GARY BLANKOPH | Electrical | 1 | 03/21/2026 |
| A.GOLDNER INC | Plumbing | 1 | 07/08/2026 |
| MAC FELDER INC | Plumbing | 1 | 07/08/2026 |
| V ELECTRIC NY INC | Electrical | 1 | 03/22/2026 |
| COGEN ELEC'L SERVICES,INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| EOC-NY | 6548 | 5 | 06/30/2026 |
| MEP INSPECTIONS, INC | 1102 | 14 | 10/31/2025 |
| METRIC CONSULTING AND INS | 1803 | 6 | 10/21/2025 |
| AK CONSULTING SERVICES, I | 6198 | 1 | 08/08/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | ACE GROUP NY CORP | 09/03/2026 |
| DOB NOW | General Construction | Permit Issued | ICON CONTRACTING GROUP | 09/02/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | ACE GROUP NY CORP | 08/25/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | ACE GROUP NY CORP | 04/22/2026 |
| DOB NOW | Construction Fence | Permit Issued | ACE GROUP NY CORP | 04/13/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | ACE GROUP NY CORP | 04/01/2026 |
| DOB NOW | Structural | Permit Issued | ICON CONTRACTING GROUP | 03/12/2026 |
| DOB NOW | Structural | Permit Issued | ICON CONTRACTING GROUP | 10/27/2025 |
| DOB NOW | Structural | Permit Issued | ICON CONTRACTING GROUP | 08/21/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | ACE GROUP NY CORP | 07/29/2025 |
| DOB NOW | General Construction | Signed-off | R.N.K. ROMEO CONST INC | 07/23/2025 |
| DOB NOW | Structural | Signed-off | R.N.K. ROMEO CONST INC | 07/23/2025 |
| DOB NOW | General Construction | Signed-off | R.N.K. ROMEO CONST INC | 05/28/2025 |
| DOB NOW | Structural | Signed-off | R.N.K. ROMEO CONST INC | 05/28/2025 |
| DOB NOW | Construction Fence | Permit Issued | ACE GROUP NY CORP | 04/15/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | ACE GROUP NY CORP | 04/04/2025 |
| DOB NOW | General Construction | Signed-off | PROLINE CONTRACTING GROUP | 03/26/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | ACE GROUP NY CORP | 03/24/2025 |
| DOB NOW | General Construction | Permit Issued | ICON CONTRACTING GROUP | 11/27/2024 |
| DOB NOW | General Construction | Signed-off | JRM CONSTRUCTION MGMT LLC | 10/16/2024 |
| DOB NOW | Structural | Signed-off | JRM CONSTRUCTION MGMT LLC | 10/16/2024 |
| DOB NOW | Plumbing | Permit Issued | MEGA PLBG CORP | 10/11/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM CONSTRUCTION MGMT LLC | 10/10/2024 |
| DOB NOW | General Construction | Permit Issued | ICON CONTRACTING GROUP | 10/09/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | SAHARA CONTRACTING CORP | 08/29/2024 |
| DOB NOW | General Construction | Signed-off | JRM CONSTRUCTION MGMT LLC | 07/11/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JRM CONSTRUCTION MGMT LLC | 07/11/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | ACE GROUP NY CORP | 07/10/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | ACE GROUP NY CORP | 03/14/2024 |
| DOB NOW | Sidewalk Shed | Permit Issued | KAJ NY CONSTRUCTION INC | 01/05/2024 |
| DOB NOW | Plumbing | Permit Issued | MEGA PLBG CORP | 10/11/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM CONSTRUCTION MGMT LLC | 10/05/2023 |
| DOB NOW | Structural | Signed-off | JRM CONSTRUCTION MGMT LLC | 10/02/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | OMARA ORGANIZATION INC | 10/02/2023 |
| DOB NOW | General Construction | Signed-off | RELIABLE RESTORATION.NY | 09/22/2023 |
| DOB NOW | Plumbing | Signed-off | MAC FELDER INC | 08/21/2023 |
| DOB NOW | General Construction | Signed-off | JRM CONSTRUCTION MGMT LLC | 08/16/2023 |
| DOB NOW | General Construction | Signed-off | RELIABLE RESTORATION.NY | 08/04/2023 |
| DOB NOW | Construction Fence | Signed-off | RELIABLE RESTORATION.NY | 08/02/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 07/25/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/07/2023 | Permit Issued | JRM CONSTRUCTION MGMT LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric TUHYE2403AN40AN 240,000 BTU · Vrf Outdoor ×6 TUHYE3603AN40AN 360,000 BTU · Vrf Outdoor ×4 • TUHYE3843AN40AN 384,000 BTU · Rooftop Unit ×4 TUHYE3843AN40AN 384,000 BTU · Vrf Outdoor ×2 TUYHE1203AN40AN 120,000 BTU · Rooftop Unit ×2 • TUHYE3603AN40AN 360,000 BTU · Rooftop Unit ×2 Trane TWE2403BAA 246,000 BTU · Fan Coil Indoor ×2 Ventilation Trane OAND600A3-D1C400JT-D3F00AL1JR2F52C004A0 8,000 CFM · Ahu ×2 • OAND600A3-D1C400JT-D3F00AL1JR2F52C004A0 8,000 CFM · Ahu ×2 |
| 07/27/2022 | Permit Issued | AMERICAN CONSTRUCTION MAN | Others | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | — | — | Storm |
| 08/01/2023 | Permit Issued | REAL PLUMBING CORP | Water/Sanitary |
| 08/26/2022 | Signed-off | MAC FELDER INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2026 | Permit Issued | COGEN ELEC'L SERVICES,INC | General Wiring |
| 06/03/2026 | Permit Issued | COGEN ELEC'L SERVICES,INC | General Wiring |
| 06/10/2025 | Complete | COGEN ELEC'L SERVICES,INC | General Wiring |
| 02/26/2024 | Complete | COGEN ELEC'L SERVICES,INC | — |
| 01/04/2024 | Permit Issued | HIGH QUALITY ELECTRIC OF | — |
| 12/07/2023 | Complete | V ELECTRIC NY INC | General Wiring |
| 07/20/2023 | Complete | TOP SHELF ELECTRIC CORP | — |
| 10/10/2022 | Permit Issued | PATRIOT ELECTRIC CORP | — |
| 09/28/2022 | Permit Issued | PATRIOT ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/31/2025 | Permit Issued | ICON CONTRACTING GROUP | 1 scope_items |
| 09/11/2025 | Signed-off | R.N.K. ROMEO CONST INC | Masonry |
| 05/05/2025 | Permit Issued | ICON CONTRACTING GROUP | Masonry |
| 07/20/2023 | Signed-off | JRM CONSTRUCTION MGMT LLC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2026 | Permit Issued | ACE GROUP NY CORP | Sidewalk Shed |
| 06/23/2026 | Permit Issued | ACE GROUP NY CORP | Fence |
| 06/23/2026 | Permit Issued | ACE GROUP NY CORP | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | Signed-off | PROLINE CONTRACTING GROUP | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/18/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/05/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/05/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/22/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/06/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/25/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/25/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/08/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/08/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/09/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/05/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/05/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/03/2025 | Sprayed fire-resistant materials | Nicolas Crosetto | special |
| 12/03/2025 | Fenestration and door U-factor and product ratings | Nicolas Crosetto | energy_progress |
| 12/03/2025 | Fenestration air leakage | Nicolas Crosetto | energy_progress |
| 12/03/2025 | Air barrier - visual inspection | Nicolas Crosetto | energy_progress |
| 12/03/2025 | Insulation placement and R values | Nicolas Crosetto | energy_progress |
| 12/03/2025 | Fenestration areas | Nicolas Crosetto | energy_progress |
| 12/03/2025 | Fire-Resistance Rated Construction | Nicolas Crosetto | progress |
| 12/03/2025 | Final | Nicolas Crosetto | progress |
| 12/03/2025 | Energy Code Compliance Inspections | Nicolas Crosetto | progress |
| 12/03/2025 | Exterior Insulation and Finish Systems (EIFS) | Nicolas Crosetto | special |
| 12/03/2025 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 10/30/2025 | Structural Stability – Alterations of existing buildings | David Merabyan | special |
| 10/30/2025 | Final | David Merabyan | progress |
| 10/30/2025 | Masonry | David Merabyan | special |
| 10/20/2025 | Fenestration and door U-factor and product ratings | Nicolas Crosetto | energy_progress |
| 10/20/2025 | Fenestration areas | Nicolas Crosetto | energy_progress |
| 10/20/2025 | Fenestration air leakage | Nicolas Crosetto | energy_progress |
| 10/20/2025 | Insulation placement and R values | Nicolas Crosetto | energy_progress |
| 10/20/2025 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 10/20/2025 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 10/20/2025 | Sprayed fire-resistant materials | — | special |
| 10/20/2025 | Energy Code Compliance Inspections | — | progress |
| 10/20/2025 | Final | Nicolas Crosetto | progress |
| 10/20/2025 | Fire-Resistance Rated Construction | Nicolas Crosetto | progress |
| 10/20/2025 | Air barrier - visual inspection | Nicolas Crosetto | energy_progress |