← Back
Miscellaneous one family
251 DOANE AVENUE
STATEN ISLAND · Great Kills-Eltingville · BIN 5070559
💬 Discuss this project
1977Year Built
2Stories
A9Building Class
R3-1Zoning
1,496 sfGross Floor Area
1Units
Miscellaneous one family · 2,300 sf lot · 0.65 FAR built · Flood zone X
Locations of Work
Electrical
Roof3p · 1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR202/23/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281202/23/2026
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
03/16/2026
Signed off — Alteration
Installation of solar panels, rooftop, grid tied, railed, 19 modules, 7.79 KW
S01328887-I1
02/26/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
02/26/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
02/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
02/26/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
02/26/2026
Special inspection requirement — Final
Mina Makar
02/23/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 19 modules, 7.79 KW
S01328887-P1
02/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
02/19/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
02/19/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
02/19/2026
Special inspection requirement — Final
Mina Makar
02/19/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
12/08/2025
Permit issued — Solar
S01328887-I1-SL
12/04/2025
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 19 modules, 7.79 KW
S01328887-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR12/08/2025
1 project · most recent 12/04/2025
FiledStatusContractorScope
12/04/2025CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
02/26/2026Air barrier - visual inspectionMina Makarenergy_progress
02/26/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
02/26/2026Fire-Resistant Penetrations and JointsMina Makarspecial
02/26/2026Energy Code Compliance InspectionsMina Makarprogress
02/26/2026FinalMina Makarprogress
02/19/2026Fire-Resistant Penetrations and JointsMina Makarspecial
02/19/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
02/19/2026Energy Code Compliance InspectionsMina Makarprogress
02/19/2026FinalMina Makarprogress
02/19/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026S01328887-P1Request digital key ↗
08/17/2026S01328887-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026S01328887-P1Open ↗
09/01/2026S01328887-P1Open ↗
08/23/2026S01328887-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026S01328887-I1Open ↗
08/17/2026S01328887-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026S01328887-P1Open ↗
08/23/2026S01328887-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026S01328887-I1Open ↗
08/17/2026S01328887-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026S01328887-I1Open ↗