1920Year Built
2Stories
B2Building Class
R6BZoning
1,680 sfGross Floor Area
2Units
Two family frame · 880 sf lot · 1.91 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 25p · 2 filings · 20 docs
Floor 16p · 2 filings · 20 docs
Cellar6p · 2 filings · 20 docs
Sub-Basement4p · 2 filings · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LWL Associates508/30/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Prime Zone Building Consulting503/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
L J & A ConstructionGeneral Contractor303/21/2026
Complex DevelopmentGeneral Contractor107/08/2026
Glenns Plumbing ServicesPlumbing107/08/2026
Plumbing-It MechanicalPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Lam and Co Consulting8864308/30/2024
Building Lifecycle
09/18/2024
Signed off — Alteration
EXTERIOR RENOVATION AT EXISTING 2 STORY WITH BASEMENT AND CELLAR BUILDING. REPLACE EXISTING STUCCO AND SIDING FACADE & WINDOWS. INTERIOR RENOVATION WITH PARTITIONS AS PER PLAN. NO CHANGE IN USE, MEANS OF EGRESS OR OCCUPANCY IN THIS APPLICATION.
B00951826-I1
09/18/2024
Signed off — Alteration
plumbing work in conjunction with GC job# B00951826
B00951990-I1
09/09/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
09/03/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JICHEN SUN
09/03/2024
Special inspection requirement — Energy Code Compliance Inspections
JICHEN SUN
34 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offComplex Development05/14/2024
DOB NOWPlumbingSigned-offJVR Plumbing and Heating05/09/2024
DOB NOWPlumbingSigned-offGlenns Plumbing Services01/25/2024
DOB NOWGeneral ConstructionSigned-offL J & A Construction11/13/2023
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
09/09/2024Pass-Final General Construction Non-Directive 14PassView ↗
08/05/2024Fail-Final General Construction Non-Directive 14FailView ↗
07/08/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/07/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
05/21/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/21/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/17/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
09/03/2024Fire-Resistant Penetrations and JointsJICHEN SUNspecial
09/03/2024Energy Code Compliance InspectionsJICHEN SUNprogress
09/03/2024Fenestration and door U-factor and product ratingsJICHEN SUNenergy_progress
09/03/2024Air barrier - visual inspectionJICHEN SUNenergy_progress
09/03/2024Insulation placement and R valuesJICHEN SUNenergy_progress
09/03/2024Fenestration areasJICHEN SUNenergy_progress
09/03/2024Interior lighting powerJICHEN SUNenergy_progress
09/03/2024Fenestration air leakageJICHEN SUNenergy_progress
08/30/2024Fire-Resistant Penetrations and JointsJICHEN SUNspecial
08/30/2024Energy Code Compliance InspectionsJICHEN SUNprogress
08/30/2024Fenestration air leakageJICHEN SUNenergy_progress
08/30/2024Fenestration and door U-factor and product ratingsJICHEN SUNenergy_progress
08/30/2024Interior lighting powerJICHEN SUNenergy_progress
08/30/2024Air barrier - visual inspectionJICHEN SUNenergy_progress
08/30/2024Fenestration areasJICHEN SUNenergy_progress
08/30/2024Insulation placement and R valuesJICHEN SUNenergy_progress