← Back
Elevator cooperative
Concerts in the Heights
251 SEAMAN AVENUE · Inwood · BIN 1065036
💬 Discuss this project
1939Year Built
6Stories
D4Building Class
R7AZoning
63,804 sfGross Floor Area
67Units
LL97 CoveredRent Stabilized3 Open Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: 251 SEAMAN OWNERS CORP · 15,000 sf lot · 4.25 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Floor 346p · 3 filings · 20 docs
Floor 239p · 3 filings · 20 docs
Floor 1
Cellar11p · 2 filings · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
251 SEAMAN OWNERS1603/22/2026
251 SEAMAN AVENUE OWNERS CORP.803/21/2026
STEEL SYSTEMS203/21/2026
EQUITIES TIME103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LMS-ACE SERVICES303/21/2026
CORE CONSULTANTS NYC503/21/2026
SKY MANAGEMENT GROUP603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RK PRECISION LLCGeneral Contractor707/08/2026
ANTHONY LUCIANOElectrical403/21/2026
A.M.N. CORPORATIONPlumbing207/08/2026
ALAN RIBACKElectrical103/21/2026
LXS AIR INCGeneral Contractor107/08/2026
ABSOLUTE PLBG HTG & MECHPlumbing107/08/2026
VOLTAGE ELECTRIC CORPElectrical103/22/2026
CANALE, WILLIAMElectrical103/21/2026
DACON, CHADElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CROSSCHECK INSPECTION SER544709/30/2024
STRUCT. ENGINEERING INTEG4174101/27/2023
GREENLINE DEVELOPERS, LLC3447110/14/2020
Building Lifecycle
All (123)Filed (12)Permit Issued (10)Signed Off (6)Facade (FISP) (12)Violation (30)Inspection (5)Objection (18)Special Inspection (30)
12/22/2025
Signed off — Alteration
M01103164-I1
12/22/2025
Permit issued — Suspended Scaffold
M01103164-I1-SC
11/12/2024
Signed off — Alteration
Modification of existing plumbing system to include installation, relocation, and removal of fixtures. No change in use, egress, or occupancy. Apartments combined in compliance with TPPN 3/97.
M08022968-I1
10/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
10/25/2024
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
09/30/2024
Filed — Alteration
Modification of existing plumbing system to include installation, relocation, and removal of fixtures. No change in use, egress, or occupancy. Apartments combined in compliance with TPPN 3/97.
M08022968-P3
09/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
09/20/2024
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
09/12/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/12/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/06/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/05/2024
Permit issued — Suspended Scaffold
M01103164-I1-SC
08/28/2024
Filed — Alteration
M01103164-I1
08/28/2024
Signed off — Alteration
COMBINING TWO EXISTING APARTMENTS 2D & 3D ON THE 2ND & 3RD FLOOR WITH A NEW COMMUNICATING STAIR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. APARTMENTS COMBINED IN COMPLIANCE WITH TPPN 3/97.
M08022954-I1
08/26/2024
Filed — Alteration
Modification of existing plumbing system to include installation, relocation, and removal of fixtures. No change in use, egress, or occupancy. Apartments combined in compliance with TPPN 3/97.
M08022968-P2
08/05/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
08/05/2024
Special inspection requirement — Final
EUGENE BIFULCO
08/05/2024
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
08/05/2024
Special inspection requirement — Fire-Resistance Rated Construction
EUGENE BIFULCO
08/05/2024
Special inspection requirement — Metering
EUGENE BIFULCO
08/05/2024
Special inspection requirement — Lighting controls
EUGENE BIFULCO
08/05/2024
Special inspection requirement — Lighting in dwelling units
EUGENE BIFULCO
08/04/2024
Signed off — Alteration
M08052360-I1
07/30/2024
Objection resolved — Addressed
07/29/2024
Objection resolved — Addressed
07/25/2024
Objection resolved — Addressed
07/08/2024
Objection raised — Scope
07/08/2024
Objection raised — Scope
07/08/2024
Objection raised — Energy
06/27/2024
Filed — Alteration
Modification of existing plumbing system to include installation, relocation, and removal of fixtures. No change in use, egress, or occupancy. Apartments combined in compliance with TPPN 3/97.
M08022968-P1
06/27/2024
Filed — Alteration
COMBINING TWO EXISTING APARTMENTS 2D & 3D ON THE 2ND & 3RD FLOOR WITH A NEW COMMUNICATING STAIR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. APARTMENTS COMBINED IN COMPLIANCE WITH TPPN 3/97.
M08022954-P2
06/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Final
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Fire-Resistance Rated Construction
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Lighting controls
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Metering
EUGENE BIFULCO
06/06/2024
Special inspection requirement — Lighting in dwelling units
EUGENE BIFULCO
12/11/2023
Permit issued — Structural
M08052360-I1-ST
12/11/2023
Permit issued — General Construction
M08022954-I1-GC
07/21/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/15/2023
Cycle 9 facade report signed — SAFE
07/14/2023
Permit issued — Plumbing
M08022968-I1-PL
06/16/2023
Cycle 9 facade report submitted
05/18/2023
Permit issued — Structural
M08052360-I1-ST
05/17/2023
Permit issued — General Construction
M08022954-I1-GC
05/12/2023
Filed — Alteration
COMBINING TWO EXISTING APARTMENTS 2D & 3D ON THE 2ND & 3RD FLOOR WITH A NEW COMMUNICATING STAIR. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. APARTMENTS COMBINED IN COMPLIANCE WITH TPPN 3/97.
M08022954-P1
05/11/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
05/11/2023
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
05/11/2023
Special inspection requirement — Final
EUGENE BIFULCO
05/11/2023
Special inspection requirement — Fire-Resistance Rated Construction
EUGENE BIFULCO
05/11/2023
Special inspection requirement — Lighting controls
EUGENE BIFULCO
05/11/2023
Special inspection requirement — Metering
EUGENE BIFULCO
05/11/2023
Special inspection requirement — Lighting in dwelling units
EUGENE BIFULCO
04/20/2023
Cycle 9 facade inspection completed
02/07/2023
Permit issued — General Construction
M08022954-I1-GC
01/27/2023
Filed — Alteration
M08052360-I1
Latest 60 of 123 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offAVARGA CONSTRUCTION CORP12/22/2025
DOB NOWSuspended ScaffoldSigned-offAVARGA CONSTRUCTION CORP09/05/2024
DOB NOWStructuralSigned-offRK PRECISION LLC12/11/2023
DOB NOWGeneral ConstructionSigned-offRK PRECISION LLC12/11/2023
DOB NOWPlumbingSigned-offA.M.N. CORPORATION07/14/2023
DOB NOWStructuralSigned-offRK PRECISION LLC05/18/2023
DOB NOWGeneral ConstructionSigned-offRK PRECISION LLC05/17/2023
DOB NOWGeneral ConstructionSigned-offRK PRECISION LLC02/07/2023
DOB NOWMechanical SystemsSigned-offLXS AIR INC06/03/2021
DOB NOWPlumbingSigned-offABSOLUTE PLBG HTG & MECH03/23/2021
BISOTISSUEDDUAL FUEL COMPANY LLC06/04/2019
BISPLISSUEDDUAL FUEL PLUBING & HTING06/04/2019
BISOTISSUEDVICHIHEL RESTORATION, INC04/19/2018
BISEQISSUEDSTEEL SYSTEMS LLC09/13/2017
BISOTISSUEDVICHIHEL RESTORATION, INC08/07/2017
BISEQISSUEDINTERSYSTEM S&S CORP04/02/2015
BISPLISSUEDWTC PLBG & HEATING CORP02/04/2013
BISPLISSUEDWTC PLBG & HEATING CORP12/12/2012
BISOTISSUEDANTARCTIC CONST. INC01/24/2012
BISPLISSUEDENTERPRISE PLBG & HTG INC01/23/2012
BISOTISSUEDPATRICA DOUGLAS01/23/2012
BISOTISSUEDALLIED CONTRACTING II COR07/19/2011
BISEQISSUEDPOWERS BRIDGING & SCAFFOLDING07/14/2011
BISOTISSUEDALLIED CONTRACTING II05/25/2011
BISOTISSUEDALLIED CONTRACTING II05/02/2011
BISEQISSUEDPOWERS BRIDGING & SCAFFOLDING04/15/2011
BISOTISSUEDREAL DEAL DECORATION LLC04/06/2006
BISPLISSUEDCARRERAS HOME IMPROV INC03/21/2006
BISOTISSUEDREAL DEAL DECORATION LLC03/16/2006
BISOTISSUEDHEIGHTS PLUMBING & HEATING INC.05/26/2005
BISPLISSUEDHEIGHTS PLUMBING & HEATING05/26/2005
BISPLISSUEDCOOPRER MECHANICAL CORP03/01/2005
BISPLISSUEDBAN PLBG & HTG CO10/09/2001
BISOTISSUEDB&H CONTRACTING10/03/2001
BISOTISSUEDCRAFT CONST09/20/1999
BISEQISSUEDSPRING SCAFFOLDING INC12/15/1997
BISFBISSUEDHERCULES WELDING & BOILER11/19/1997
BISFSISSUEDG.BAUER ,INC.09/30/1992
10 projects · most recent 04/06/2026
General Wiring
FiledStatusContractorScope
04/06/2026CompleteKET ELECTRIC LLC—
02/13/2026Permit IssuedELECTRICAL SECURITY CORP.General Wiring
12/23/2025CompleteJAM ELECTRICAL CORP—
07/10/2024CompleteBELMONT ELECTRICAL, INCGeneral Wiring
08/17/2023CompletePK ELECTRIC INCGeneral Wiring
08/04/2022CompleteVOLTAGE ELECTRIC CORP—
05/10/2021CompleteFUSION ELECTL CONTRNG LLCGeneral Wiring
06/01/2020CompleteRELIANT ELEC'L CONT'G INCGeneral Wiring
11/08/2019CompleteVOLTAGE ELECTRIC CORP—
01/23/2019CompleteVOLTAGE ELECTRIC CORP—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
09/12/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/12/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/06/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/05/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/21/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 31
DateRequirementInspectorRole
10/25/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
10/25/2024Energy Code Compliance InspectionsEUGENE BIFULCOprogress
09/20/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
09/20/2024Energy Code Compliance InspectionsEUGENE BIFULCOprogress
08/05/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
08/05/2024FinalEUGENE BIFULCOprogress
08/05/2024Energy Code Compliance InspectionsEUGENE BIFULCOprogress
08/05/2024Fire-Resistance Rated ConstructionEUGENE BIFULCOprogress
08/05/2024MeteringEUGENE BIFULCOenergy_progress
08/05/2024Lighting controlsEUGENE BIFULCOenergy_progress
08/05/2024Lighting in dwelling unitsEUGENE BIFULCOenergy_progress
06/06/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
06/06/2024Energy Code Compliance InspectionsEUGENE BIFULCOprogress
06/06/2024Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
06/06/2024Energy Code Compliance InspectionsEUGENE BIFULCOprogress
06/06/2024FinalEUGENE BIFULCOprogress
06/06/2024Fire-Resistance Rated ConstructionEUGENE BIFULCOprogress
06/06/2024Lighting controlsEUGENE BIFULCOenergy_progress
06/06/2024MeteringEUGENE BIFULCOenergy_progress
06/06/2024Lighting in dwelling unitsEUGENE BIFULCOenergy_progress
05/11/2023Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
05/11/2023Energy Code Compliance InspectionsEUGENE BIFULCOprogress
05/11/2023FinalEUGENE BIFULCOprogress
05/11/2023Fire-Resistance Rated ConstructionEUGENE BIFULCOprogress
05/11/2023Lighting controlsEUGENE BIFULCOenergy_progress
Latest 25 of 31.
▾Documents — 203 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch9
09/01/2026M08052360-I1Request digital key ↗
08/31/2026M08022954-P1Request digital key ↗
08/26/2026M08022968-P3Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
09/04/2026M00411767-I1Request digital key ↗
08/15/2026M00411767-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00411768-I1Request digital key ↗
▸Applications & Permits33
▸BISWORK PERMIT APPLICATION20
06/04/2019123780113Open ↗
06/04/2019123780113Open ↗
06/04/2019123780113Open ↗
Showing 3 of 20 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION13
04/25/2019123045542Open ↗
09/12/2017140692668Open ↗
04/13/2017123045542Open ↗
Showing 3 of 13 on file for this type
▸Seals & Professional Certifications63
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION17
02/24/2020123780113Open ↗
02/24/2020123780113Open ↗
06/17/2019123045542Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
09/04/2026M00411768-I1Open ↗
08/31/2026M08022954-I1Open ↗
08/31/2026M08022954-P1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
09/29/2026M08022954-P1Open ↗
09/29/2026M08022954-P1Open ↗
09/01/2026M08022968-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/29/2026M08022954-P1Open ↗
09/01/2026M08022968-I1Open ↗
08/28/2026M08022968-P3Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
06/04/2019123780113Open ↗
12/23/2011120931215Open ↗
12/02/2011120913280Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
12/23/2011120931215Open ↗
12/02/2011120913280Open ↗
04/27/2011120671870Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
06/04/2019123780113Open ↗
09/12/2017140692668Open ↗
04/01/2015140328483Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
09/12/2017140692668Open ↗
04/01/2015140328483Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
09/12/2017140692668Open ↗
04/01/2015140328483Open ↗
▸Trade Schedules & Equipment8
▸BISSELF-CERT PLUMBING NOTICE4
07/02/2013120913280Open ↗
06/18/2013120913280Open ↗
05/06/2013120913280Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING2
12/23/2011120931215Open ↗
12/02/2011120913280Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
06/04/2019123780113Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
06/04/2019123780113Open ↗
▸Safety & Tenant Protection8
▸BISTenant Protection Plan and Notes3
06/04/2019123780113Open ↗
04/13/2017123045542Open ↗
09/12/2017140692668Open ↗
▸DOB NOWTenant Protection Plan3
09/04/2026M00411768-I1Open ↗
08/13/2026M00411767-P1Open ↗
08/13/2026M00411767-I1Open ↗
▸BISSTREET TREE CHECKLIST2
12/23/2011120931215Open ↗
12/02/2011120913280Open ↗
▸Environmental & Asbestos15
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/31/2026M08022954-P1Open ↗
08/26/2026M08022968-P3Open ↗
08/26/2026M08022968-P2Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
06/04/2019123780113Open ↗
04/13/2017123045542Open ↗
04/27/2011120671870Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
12/02/2011120913280Open ↗
06/21/2011120726456Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
04/27/2011120671870Open ↗
04/19/2011120659420Open ↗
▸Energy Compliance13
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
02/24/2020123780113Open ↗
06/17/2019123045542Open ↗
06/04/2019123780113Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS4
02/24/2020123780113Open ↗
06/17/2019123045542Open ↗
08/13/2013120913280Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY3
02/28/2012120734410Open ↗
12/23/2011120931215Open ↗
12/02/2011120913280Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING2
09/12/2017140692668Open ↗
04/01/2015140328483Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
09/12/2017140692668Open ↗
04/01/2015140328483Open ↗
▸Approvals, Objections & Sign-offs15
▸BISADMINISTRATIVE OBJECTIONS6
12/23/2011120931215Open ↗
12/02/2011120913280Open ↗
06/27/2011120734410Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
02/24/2020123780113Open ↗
06/17/2019123045542Open ↗
02/11/2019140692668Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
02/25/2020123780113Open ↗
02/24/2020123780113Open ↗
08/13/2013120913280Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership13
▸BISCOST AFFIDAVIT13
02/24/2020123780113Open ↗
06/17/2019123045542Open ↗
06/04/2019123780113Open ↗
Showing 3 of 13 on file for this type
▸Filing & Intake Forms17
▸BISEFILING COVER SHEET7
06/04/2019123780113Open ↗
04/13/2017123045542Open ↗
12/23/2011120931215Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM4
02/24/2020123780113Open ↗
06/17/2019123045542Open ↗
04/25/2019123045542Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION3
06/07/2019123045542Open ↗
03/15/2012120671870Open ↗
03/06/2012120671870Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET3
09/12/2017140692668Open ↗
04/01/2015140328483Open ↗
12/02/2011120913280Open ↗
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
12/14/2012120931215Open ↗
01/23/2012120931215Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M01103164-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M01103164-I1Open ↗