← Back
BuildNYC
Walk-up cooperative
252 EAST 89TH STREET
MANHATTAN · BIN 1048873
💬 Discuss this project
1920Year Built
5Stories
C6Building Class
C2-8Zoning
9,250 sfGross Floor Area
18Units
Rent Stabilized0 Active Violations
Walk-up cooperative · Owner of record: 252 E 89th St Apartment · 2,517 sf lot · 3.68 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 1Heavy duty sidewalk shed installation8p · 2 filings · 5 docs
Site & exteriorRepointing front brick facade and caulking windows9p · 2 filings · 12 docs
Filed — no permit issued7p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Dominion Assets109/01/2026
252 E 89th St Apartment103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Boris Balkhiyev, PE105/05/2026
Cna Builders & Consultant201/27/2025
Mje Professional Services208/19/2024
Syed Engineering110/06/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Expediting103/21/2026
SNR Expediting Design403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DNS Contracting NYCGeneral Contractor303/21/2026
Reliable EnterprisesScaffold203/21/2026
JascoScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Cna Builders and Consulta2898201/27/2025
Building Lifecycle
All (47)Filed (6)Permit Issued (4)Signed Off (4)Violation (6)Objection (20)Special Inspection (7)
08/31/2026
Objection resolved — Resolved
08/13/2026
Objection raised — Other
07/14/2026
Objection resolved — Resolved
07/14/2026
Objection resolved — Resolved
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Resolved
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Resolved
07/07/2026
Objection resolved — Addressed
05/29/2026
Objection raised — Fire_Protection
05/29/2026
Objection raised — Other
05/29/2026
Objection raised — Cost
05/29/2026
Objection raised — Zoning
05/29/2026
Objection raised — Other
05/29/2026
Objection raised — Fire_Protection
05/29/2026
Objection raised — Admin
05/29/2026
Objection raised — Other
05/29/2026
Objection raised — Fire_Protection
05/05/2026
Filed — Alteration CO
Application herewith filed to convert 2 commercial offices at 1st floor to apartment units and obtain new CofO.
M01385662-I1
05/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/05/2026
Special inspection requirement — Energy Code Compliance Inspections
05/05/2026
Special inspection requirement — Insulation placement and R values
05/14/2025
Violation issued (HPD, closed)
C
05/14/2025
Violation issued (HPD, closed)
C
01/31/2025
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01097211-I1
01/31/2025
Signed off — Alteration
M01097212-I1
01/27/2025
Signed off — Alteration
REPOINTING THE FRONT BRICK FACADE AND CAULKING OF WINDOWS ON FRONT BUILDING FACADE.
M01104870-I1
01/27/2025
Filed — Alteration
REPOINTING THE FRONT BRICK FACADE AND CAULKING OF WINDOWS ON FRONT BUILDING FACADE.
M01104870-P1
01/27/2025
Special inspection requirement — Tenant Protection Plan Compliance
Choudhry Yusaf
01/27/2025
Special inspection requirement — Final
Choudhry Yusaf
01/22/2025
Special inspection requirement — Tenant Protection Plan Compliance
Choudhry Yusaf
01/22/2025
Special inspection requirement — Final
Choudhry Yusaf
09/19/2024
Permit issued — General Construction
M01104870-I1-GC
09/06/2024
Filed — Alteration
REPOINTING THE FRONT BRICK FACADE AND CAULKING OF WINDOWS ON FRONT BUILDING FACADE.
M01104870-I1
08/20/2024
Permit issued — Supported Scaffold
M01097211-I1-SF
08/19/2024
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01097211-I1
08/16/2024
Filed — Alteration
M01097212-I1
08/16/2024
Permit issued — Sidewalk Shed
M01097212-I1-SH
09/13/2023
Signed off — Alteration
M00408653-I1
10/07/2020
Permit issued — Sidewalk Shed
M00408653-I1-SH
10/06/2020
Filed — Alteration
M00408653-I1
11/28/2005
Violation issued (ECB, closed)
Construction
02/13/2004
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/19/2003
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offDNS Contracting NYC09/19/2024
DOB NOWSupported ScaffoldSigned-offReliable Enterprises08/20/2024
DOB NOWSidewalk ShedSigned-offArsenal Scaffold08/16/2024
DOB NOWSidewalk ShedSigned-offJasco10/07/2020
BISOTISSUEDRegal Construction Group11/12/2020
BISBLISSUEDStatewide Oil & Heating . Co12/06/2005
BISBLISSUEDMetro Fuel Oil10/20/1999
2 projects · most recent 08/19/2024
FiledStatusContractorScope
08/19/2024CompleteRichard Neu—
10/06/2020Permit IssuedRichard Neu—
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
05/05/2026Fire-Resistant Penetrations and Joints—special
05/05/2026Energy Code Compliance Inspections—progress
05/05/2026Insulation placement and R values—energy_progress
01/27/2025Tenant Protection Plan ComplianceChoudhry Yusafspecial
01/27/2025FinalChoudhry Yusafprogress
01/22/2025Tenant Protection Plan ComplianceChoudhry Yusafspecial
01/22/2025FinalChoudhry Yusafprogress
▾Documents — 37 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch5
08/26/2026M01097212-I1Request digital key ↗
08/26/2026M01097211-I1Request digital key ↗
08/25/2026M01104870-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00408653-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
08/25/2020140943237Open ↗
▸BISWORK PERMIT APPLICATION1
11/12/2020140943237Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature6
09/04/2026M00408653-I1Open ↗
08/26/2026M01097212-I1Open ↗
08/25/2026M01104870-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/27/2026M01104870-I1Open ↗
08/28/2026M01104870-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/27/2026M01104870-I1Open ↗
08/28/2026M01104870-P1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
08/25/2020140943237Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
08/25/2020140943237Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/25/2020140943237Open ↗
▸Safety & Tenant Protection3
▸BISTENANT PROTECTION PLAN AND NOTES1
08/25/2020140943237Open ↗
▸DOB NOWStreet Tree Checklist1
08/15/2026M01385662-I1Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00408653-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026M01104870-I1Open ↗
08/25/2026M01104870-P1Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
11/12/2020140943237Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
08/25/2020140943237Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
03/17/2021140943237Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
08/25/2020140943237Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
03/17/2021140943237Open ↗
08/25/2020140943237Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
03/17/2021140943237Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
03/17/2021140943237Open ↗
08/25/2020140943237Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
08/25/2020140943237Open ↗
▸Other Documents1
▸DOB NOWProperty Ownership Certification1
08/15/2026M01385662-I1Open ↗