← Back
BuildNYC
Two family brick
2521 PAULDING AVENUE
BRONX · BIN 2051706
💬 Discuss this project
1950Year Built
2Stories
B1Building Class
R5Zoning
1,962 sfGross Floor Area
2Units
3 Active Violations 0 unresolved · 3 paperwork only ▸
Two family brick · 1,800 sf lot · 1.09 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 2Change in Certificate of Occupancy, legalize exterior wall3p · 1 filing · 20 docs
Floor 1Change in Certificate of Occupancy, legalize exterior wall3p · 1 filing · 20 docs
BasementChange in Certificate of Occupancy, legalize exterior wallUnder Construction4p · 2 filings · 20 docs
Sub-BasementUnder Construction4p · 1 filing · 10 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Urban Architectural Design511/05/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
New Prime General ConstructionGeneral Contractor104/09/2026
Plumbing P & HPlumbing107/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Meldan Group8100411/05/2026
Building Lifecycle
11/05/2026
Filed — Alteration
APPLICATION FILED FOR LEGALIZATION OF 3-PIECE BATHROOM((1)SHOWER, (1)LAV & (1) W.C.) & KITCHEN((1)SINK & (1) GAS RANGE) IN BASEMENT. IN ORDER TO RECTIFY ECB VIOLATION# 39130791Y. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01164375-P3
11/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jeffrey Reid
09/14/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/30/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/17/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
56 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedPlumbing P & H06/16/2026
DOB NOWGeneral ConstructionPermit IssuedNew Prime General Construction04/06/2026
1 project · most recent 11/05/2026
Gas Water/Sanitary
FiledStatusContractorScope
11/05/2026Permit IssuedPlumbing P & HGas, Water/Sanitary
1 project · most recent 06/07/2026
General Wiring
FiledStatusContractorScope
06/07/2026Permit IssuedR.A. Phillips ElectricalGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
09/14/2026Pass-Final CND-Occupancy InspectionPassView ↗
08/30/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/17/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/26/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/26/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
11/04/2026Fire-Resistant Penetrations and JointsJeffrey Reidspecial
07/29/2026Structural Stability – Alterations of existing buildings—special
07/29/2026Fire-Resistance Rated Construction—progress
07/29/2026Energy Code Compliance Inspections—progress
07/29/2026Interior lighting power—energy_progress
07/29/2026Insulation placement and R values—energy_progress
07/29/2026Fenestration areas—energy_progress
07/29/2026Fenestration air leakage—energy_progress
07/29/2026Air barrier - visual inspection—energy_progress
07/29/2026Fenestration and door U-factor and product ratings—energy_progress
07/29/2026Electric vehicle service equipment requirements—energy_progress
07/29/2026Metering—energy_progress
07/29/2026Fire-Resistant Penetrations and Joints—special
07/07/2026Fire-Resistant Penetrations and JointsJeffrey Reidspecial
02/19/2026Energy Code Compliance Inspections—progress
02/19/2026Fire-Resistance Rated Construction—progress
02/19/2026Electric vehicle service equipment requirements—energy_progress
02/19/2026Air barrier - visual inspection—energy_progress
02/19/2026Fenestration and door U-factor and product ratings—energy_progress
02/19/2026Insulation placement and R values—energy_progress
02/19/2026Interior lighting power—energy_progress
02/19/2026Fenestration areas—energy_progress
02/19/2026Metering—energy_progress
02/19/2026Fenestration air leakage—energy_progress
02/19/2026Structural Stability – Alterations of existing buildings—special
Latest 25 of 26.
46 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account