Public elementary, junior or senior high
P.S. 277 Gerritsen Beach
2529 GERRITSEN AVENUE · BIN 3242369
💬 Discuss this project
1967Year Built
2Stories
W1Building Class
PARKZoning
60,000 sfGross Floor Area
0Units
LL97 Covered9 Open Violations 4 unresolved · 5 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF PARKS AND RECREATION · 83,844 sf lot · 0.72 FAR built · Flood zone X500
Locations of Work
ArchitectureElectricalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction67p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC SCHOOL CONSTRUCTION AUTHORITY1407/08/2026
NYC DEPARTMENT OF PARKS AND RECREATION103/22/2026
DOE PS 277 040603/22/2026
DOE PS 277203/22/2026
DEPARTMENT OF EDUCATION503/22/2026
DOE 040303/22/2026
PS 277 DOE 0603/22/2026
PS 277 DEPT OF EDUCATION0103/22/2026
BOARD OF EDUCATION PS 277203/22/2026
DEPT OF EDUCATION/ PS 277203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GOSHOW ARCHITECTS LLP411/21/2022
DSENY ENGINEERING SERVICES, PC411/08/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KARL SMITH403/21/2026
DSENY ENGINEERING SERVICES803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
OUDAZ GENERAL CONTRACTINGGeneral Contractor2607/08/2026
VARSITY PLBG AND HTG INCPlumbing407/08/2026
GIOVANNI DITURIElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FUTURE TECH CONSULTANTS O589411/21/2022
MUNICIPAL TESTING LABORAT230109/29/2022
Building Lifecycle
All (101)Filed (8)Permit Issued (16)Signed Off (1)Violation (60)Objection (4)Special Inspection (12)
09/14/2026
Signed off — Alteration
FN/PS277K- FOR TEMPORARY CONSTRUCTION EQUIPMENT(FENCE) SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH DOB # B00714939 NO CHANGE IN USE, OCCUPANCY OR EGRESS
B08009247-I1
03/11/2026
Violation issued (ECB, open)
Construction
03/11/2026
Violation issued (ECB, open)
Construction
03/11/2026
Violation issued (ECB, open)
Construction
03/11/2026
Violation issued (ECB, open)
Construction
03/11/2026
Violation issued (ECB, open)
Construction
02/17/2026
Permit issued — Plumbing
B00714939-S2-PL
05/01/2025
Violation issued (ECB, closed)
Construction
02/18/2025
Permit issued — Plumbing
B00714939-S2-PL
10/30/2024
Permit issued — Sidewalk Shed
B08009284-I1-SH
10/30/2024
Permit issued — Construction Fence
B08009247-I1-FN
10/30/2024
Permit issued — Supported Scaffold
B08009287-I1-SF
09/16/2024
Permit issued — General Construction
B00714939-I1-GC
02/20/2024
Permit issued — Plumbing
B00714939-S2-PL
08/25/2023
Permit issued — Sidewalk Shed
B08009284-I1-SH
08/24/2023
Permit issued — General Construction
B00714939-I1-GC
08/24/2023
Permit issued — Construction Fence
B08009247-I1-FN
08/24/2023
Permit issued — Supported Scaffold
B08009287-I1-SF
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/28/2023
Violation issued (ECB, closed)
Construction
02/27/2023
Permit issued — Plumbing
B00714939-S2-PL
12/09/2022
Permit issued — General Construction
B00714939-I1-GC
11/22/2022
Special inspection requirement — Post-installed Anchors
Noel Tolentino
11/22/2022
Special inspection requirement — Masonry
Noel Tolentino
11/22/2022
Special inspection requirement — Energy Code Compliance Inspections
Michael Marchese
11/22/2022
Special inspection requirement — Insulation placement and R values
Michael Marchese
11/22/2022
Special inspection requirement — Air barrier - visual inspection
Michael Marchese
11/22/2022
Special inspection requirement — Exterior lighting power
Michael Marchese
11/21/2022
Filed — Alteration
Removal and replacement of existing roof membrane, protection board, insulation and base layer with new energy code compliant roof. Masonry replacement, repointing, replacement of exterior lighting, and repair on parapets and facade.
B00714939-P2
11/21/2022
Filed — Alteration
Removal and replacement of existing roof membrane, protection board, insulation and base layer with new energy code compliant roof. Masonry replacement, repointing, replacement of exterior lighting, and repair on parapets and facade.
B00714939-P1
11/10/2022
Special inspection requirement — Post-installed Anchors
Noel Tolentino
11/10/2022
Special inspection requirement — Energy Code Compliance Inspections
Michael Marchese
11/10/2022
Special inspection requirement — Exterior lighting power
Michael Marchese
11/10/2022
Special inspection requirement — Insulation placement and R values
Michael Marchese
11/10/2022
Special inspection requirement — Air barrier - visual inspection
Michael Marchese
11/10/2022
Special inspection requirement — Masonry
Noel Tolentino
11/08/2022
Filed — Alteration
FN/PS277K- FOR TEMPORARY CONSTRUCTION EQUIPMENT(FENCE) SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH DOB # B00714939 NO CHANGE IN USE, OCCUPANCY OR EGRESS
B08009247-P1
11/08/2022
Permit issued — Supported Scaffold
B08009287-I1-SF
10/25/2022
Permit issued — Sidewalk Shed
B08009284-I1-SH
10/20/2022
Permit issued — Construction Fence
B08009247-I1-FN
09/29/2022
Filed — Alteration
FN/PS277K- FOR TEMPORARY CONSTRUCTION EQUIPMENT(FENCE) SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH DOB # B00714939 NO CHANGE IN USE, OCCUPANCY OR EGRESS
B08009247-I1
09/29/2022
Filed — Alteration
B08009284-I1
09/29/2022
Filed — Alteration
SF/PS277K- FOR TEMPORARY CONSTRUCTION EQUIPMENT(SCAFFOLD) SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH DOB # B00714939 NO CHANGE IN USE, OCCUPANCY OR EGRESS
B08009287-I1
05/06/2022
Objection raised — Other
05/06/2022
Objection resolved — Addressed
04/26/2022
Filed — Alteration
Removal and replacement of existing roof membrane, protection board, insulation and base layer with new energy code compliant roof. Masonry replacement, repointing, replacement of exterior lighting, and repair on parapets and facade.
B00714939-S2
04/26/2022
Objection raised — Other
04/26/2022
Objection resolved — Addressed
04/13/2022
Filed — Alteration
Removal and replacement of existing roof membrane, protection board, insulation and base layer with new energy code compliant roof. Masonry replacement, repointing, replacement of exterior lighting, and repair on parapets and facade.
B00714939-I1
06/20/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/26/2021
Violation issued (ECB, closed)
Construction
03/11/2019
Violation issued (ECB, closed)
Construction
04/13/2017
Violation issued (ECB, closed)
Construction
04/13/2017
Violation issued (ECB, closed)
Construction
04/13/2017
Violation issued (ECB, closed)
Construction
06/28/2016
Violation issued (ECB, closed)
Construction
06/28/2016
Violation issued (ECB, closed)
Construction
Latest 60 of 101 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedVARSITY PLBG AND HTG INC02/17/2026
DOB NOWPlumbingPermit IssuedVARSITY PLBG AND HTG INC02/18/2025
DOB NOWSidewalk ShedSigned-offOUDAZ GENERAL CONTRACTING10/30/2024
DOB NOWConstruction FenceSigned-offOUDAZ GENERAL CONTRACTING10/30/2024
DOB NOWSupported ScaffoldPermit IssuedOUDAZ GENERAL CONTRACTING10/30/2024
DOB NOWGeneral ConstructionPermit IssuedOUDAZ GENERAL CONTRACTING09/16/2024
DOB NOWPlumbingPermit IssuedVARSITY PLBG AND HTG INC02/20/2024
DOB NOWSidewalk ShedSigned-offOUDAZ GENERAL CONTRACTING08/25/2023
DOB NOWGeneral ConstructionPermit IssuedOUDAZ GENERAL CONTRACTING08/24/2023
DOB NOWConstruction FenceSigned-offOUDAZ GENERAL CONTRACTING08/24/2023
DOB NOWSupported ScaffoldPermit IssuedOUDAZ GENERAL CONTRACTING08/24/2023
DOB NOWPlumbingPermit IssuedVARSITY PLBG AND HTG INC02/27/2023
DOB NOWGeneral ConstructionPermit IssuedOUDAZ GENERAL CONTRACTING12/09/2022
DOB NOWSupported ScaffoldPermit IssuedOUDAZ GENERAL CONTRACTING11/08/2022
DOB NOWSidewalk ShedSigned-offOUDAZ GENERAL CONTRACTING10/25/2022
DOB NOWConstruction FenceSigned-offOUDAZ GENERAL CONTRACTING10/20/2022
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/12/2026
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/12/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/12/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/12/2026
BISOTISSUEDLAWRENCE'S CONTRACTOR,INC12/04/2025
BISMHISSUEDYOLAND CONSTRUCTION & MET07/28/2025
BISPLISSUEDLATTY'S GEN PLBG CONT COR06/23/2025
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISPLISSUEDFORSYTHE P&H CORP02/06/2025
BISOTISSUEDLAWRENCE'S CONTRACTOR,INC11/22/2024
BISMHISSUEDYOLAND CONSTRUCTION & MET07/25/2024
BISBLISSUEDFORSYTHE P&H CORP06/05/2024
BISPLISSUEDLATTY'S GEN PLBG CONT COR05/13/2024
BISPLISSUEDLATTY'S GEN PLBG CONT COR05/10/2024
BISOTISSUEDLAWRENCE'S CONTRACTOR,INC04/30/2024
+ 26 more permits on file
1 project · most recent 11/21/2022
Storm
FiledStatusContractorScope
11/21/2022Permit IssuedVARSITY PLBG AND HTG INCStorm
16 projects · most recent 07/27/2026
General Wiring
FiledStatusContractorScope
07/27/2026Permit IssuedINLIGHT ELECTRICAL CORPGeneral Wiring
07/30/2025CompleteEVEREST ELECTRIC CORP—
03/27/2025CancelledAROUND ELECTRIC CORP.General Wiring
01/07/2025Permit IssuedLUNA NYC ELECTRIC CORPGeneral Wiring
12/13/2024Permit IssuedWILLDAN ELECTRICAL OF NYGeneral Wiring
11/06/2024CompleteURBAN ELECTRICAL CORPGeneral Wiring
08/27/2024CompleteCHARAN ELEC'L ENTERP'S IN—
05/30/2023Permit IssuedHIGH VOLT ELEC CORP. OFGeneral Wiring
05/10/2023CompleteGEMINI ELECTRIC CO., INC.—
10/24/2022Permit IssuedI.S.M. ELECTRIC, INC.—
01/11/2022CompleteABM ELECTRIC, INC—
09/06/2019Permit IssuedFALCON ELEC'L CONTR'G COR—
06/12/2019CompleteFALCON ELEC'L CONTR'G CORGeneral Wiring
05/02/2019CompleteFALCON ELEC'L CONTR'G COR—
04/09/2019Permit IssuedCHARAN ELEC'L ENTERP'S INGeneral Wiring
2 projects · most recent 11/08/2022
Fence Scaffold
FiledStatusContractorScope
11/08/2022Signed-offOUDAZ GENERAL CONTRACTINGFence
09/29/2022Permit IssuedOUDAZ GENERAL CONTRACTINGScaffold
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
11/22/2022Post-installed AnchorsNoel Tolentinospecial
11/22/2022MasonryNoel Tolentinospecial
11/22/2022Energy Code Compliance InspectionsMichael Marcheseprogress
11/22/2022Insulation placement and R valuesMichael Marcheseenergy_progress
11/22/2022Air barrier - visual inspectionMichael Marcheseenergy_progress
11/22/2022Exterior lighting powerMichael Marcheseenergy_progress
11/10/2022Post-installed AnchorsNoel Tolentinospecial
11/10/2022Energy Code Compliance InspectionsMichael Marcheseprogress
11/10/2022Exterior lighting powerMichael Marcheseenergy_progress
11/10/2022Insulation placement and R valuesMichael Marcheseenergy_progress
11/10/2022Air barrier - visual inspectionMichael Marcheseenergy_progress
11/10/2022MasonryNoel Tolentinospecial
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Ps277kEducation—
Project B08009284 Alteration · Permit Entire · 09/29/2022
P.S. 277Education—
Project B00714939 Alteration · Permit Entire · 04/13/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 56 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/29/2026B00714939-P2Request digital key ↗
08/29/2026B00714939-S2Request digital key ↗
08/29/2026B00714939-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/29/2026B00714939-P2Open ↗
08/29/2026B00714939-I1Open ↗
08/29/2026B00714939-S2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/29/2026B00714939-I1Open ↗
08/29/2026B00714939-I1Open ↗
08/25/2026B00714939-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/29/2026B00714939-I1Open ↗
08/26/2026B00714939-S2Open ↗
08/25/2026B00714939-P2Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment1
▸BISFA - FDNY APPROVAL : FD-FAA1
01/12/2022302583666Open ↗
▸Safety & Tenant Protection4
▸DOB NOWNYCSCA - Approved Site Safety Plans4
08/13/2026B08009247-P1Open ↗
08/13/2026B08009247-I1Open ↗
08/13/2026B08009287-I1Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs19
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/28/2026B08009284-I1Open ↗
08/13/2026B08009247-I1Open ↗
08/13/2026B08009247-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)8
08/13/2026B08009247-P1Open ↗
08/13/2026B08009247-I1Open ↗
08/13/2026B00714939-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDEP Variance (V5) letter2
08/13/2026B00714939-I1Open ↗
08/13/2026B00714939-S2Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)1
08/13/2026B00714939-I1Open ↗
▸Other Documents8
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal8
08/13/2026B08009247-I1Open ↗
08/13/2026B00714939-P2Open ↗
08/13/2026B00714939-P1Open ↗
Showing 3 of 8 on file for this type