Elevator apt, miscellaneous
253 EAST 202 STREET
BRONX · Bedford Park · BIN 2097987
💬 Discuss this project
1965Year Built
6Stories
D9Building Class
R8Zoning
101,050 sfGross Floor Area
102Units
LL97 CoveredRent Stabilized89 Open Violations 87 unresolved · 2 paperwork only ▸FISP: No Report FiledFDNY Report ↗
Elevator apt, miscellaneous · Owner of record: NINCILA PROPERTIES LLC · 22,300 sf lot · 4.53 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalEquipmentGeneral
Site & exterior5p · 3 filings · 8 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DELTA CONTRACTING GROUP I507/08/2026
DELTA CONSTRUCTION303/21/2026
NINCILA PROPERTIES LLC103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/21/2016$18.4M—CHATHAM REALTY LLC → NINCILA PROPERTIES LLC$182/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASHRAF CORP104/24/2025
GREEN DESIGN204/10/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ATLANTIC BUILDING SUPPLY INC.403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ALPHA SCAFFOLDING INCGeneral Contractor406/27/2026
DELTA CONTRACTING GROUP IGeneral Contractor407/08/2026
Building Lifecycle
All (77)Filed (3)Permit Issued (4)Signed Off (2)Facade (FISP) (6)Violation (60)Special Inspection (2)
06/24/2026
Permit issued — Sidewalk Shed
X01214588-I1-SH
04/30/2026
Violation issued (HPD, closed)
A
04/17/2026
Cycle 9 facade report signed — UNSAFE
03/30/2026
Cycle 9 facade inspection completed
03/30/2026
Violation issued (HPD, closed)
A
03/30/2026
Violation issued (HPD, closed)
C
03/03/2026
Violation issued (HPD, open)
A
03/03/2026
Violation issued (HPD, closed)
B
03/03/2026
Violation issued (HPD, closed)
C
02/11/2026
Violation issued (HPD, closed)
A
02/11/2026
Violation issued (HPD, open)
C
02/11/2026
Violation issued (HPD, closed)
A
02/11/2026
Violation issued (HPD, closed)
B
02/11/2026
Violation issued (HPD, closed)
A
02/09/2026
Violation issued (HPD, closed)
A
02/01/2026
Violation issued (HPD, closed)
A
02/01/2026
Violation issued (HPD, closed)
B
02/01/2026
Violation issued (HPD, closed)
C
02/01/2026
Violation issued (HPD, closed)
C
12/17/2025
Violation issued (HPD, closed)
B
12/17/2025
Violation issued (HPD, closed)
A
12/17/2025
Violation issued (HPD, closed)
B
12/17/2025
Violation issued (HPD, closed)
C
08/16/2025
Violation issued (HPD, closed)
C
08/16/2025
Violation issued (HPD, closed)
B
08/16/2025
Violation issued (HPD, closed)
C
07/27/2025
Violation issued (HPD, closed)
C
07/27/2025
Violation issued (HPD, closed)
A
07/27/2025
Violation issued (HPD, closed)
C
07/27/2025
Violation issued (HPD, closed)
B
07/27/2025
Violation issued (HPD, closed)
B
07/27/2025
Violation issued (HPD, closed)
C
06/28/2025
Violation issued (HPD, closed)
C
06/28/2025
Violation issued (HPD, closed)
C
06/28/2025
Violation issued (HPD, closed)
C
06/28/2025
Violation issued (HPD, closed)
A
06/28/2025
Violation issued (HPD, closed)
C
04/25/2025
Permit issued — Sidewalk Shed
X01214588-I1-SH
04/24/2025
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
X01214588-I1
02/18/2025
Violation issued (HPD, closed)
C
01/23/2025
Violation issued (ECB, open)
Construction
01/08/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/20/2024
Cycle 9 facade report submitted
12/20/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/24/2024
Violation issued (ECB, open)
Construction
09/05/2024
Violation issued (HPD, closed)
A
09/05/2024
Violation issued (HPD, closed)
A
09/05/2024
Violation issued (HPD, closed)
B
09/05/2024
Violation issued (HPD, closed)
B
09/05/2024
Violation issued (HPD, closed)
C
09/05/2024
Violation issued (HPD, open)
C
09/05/2024
Violation issued (HPD, closed)
C
09/05/2024
Violation issued (HPD, closed)
A
09/05/2024
Violation issued (HPD, open)
B
09/05/2024
Violation issued (HPD, open)
C
09/05/2024
Violation issued (HPD, closed)
B
09/05/2024
Violation issued (HPD, closed)
B
09/05/2024
Violation issued (HPD, closed)
A
08/16/2024
Violation issued (HPD, closed)
C
08/16/2024
Violation issued (HPD, closed)
A
Latest 60 of 77 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedALPHA SCAFFOLDING INC06/24/2026
DOB NOWSidewalk ShedPermit IssuedALPHA SCAFFOLDING INC04/25/2025
DOB NOWSidewalk ShedSigned-offDELTA CONTRACTING GROUP I04/11/2019
DOB NOWSupported ScaffoldSigned-offDELTA CONTRACTING GROUP I04/11/2019
BISOTISSUEDDELTA CONTRACTING GROUP I04/16/2019
BISBLISSUEDIRVING BAUER09/30/1997
3 projects · most recent 04/26/2025
General Wiring
FiledStatusContractorScope
04/26/2025Permit IssuedRICHARD NEU—
12/02/2022CompleteNET POWER ELECTRIC CORPGeneral Wiring
04/08/2019CompleteRICHARD NEU—
1 project · most recent 04/24/2025
Sidewalk Shed
FiledStatusContractorScope
04/24/2025Permit IssuedALPHA SCAFFOLDING INCSidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
04/05/2019FinalBRIAN T. O'CONNORprogress
04/05/2019FinalBRIAN T. O'CONNORprogress
▾Documents — 26 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/26/2026X00151469-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
08/26/2026X00151478-I1Request digital key ↗
▸DOB NOWPlans/Sketch1
08/19/2026X01214588-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
04/15/2019240252052Open ↗
▸BISWORK PERMIT APPLICATION1
04/15/2019240252052Open ↗
▸Seals & Professional Certifications9
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026X00151478-I1Open ↗
08/13/2026X01214588-I1Open ↗
08/13/2026X00151469-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/28/2026X00151469-I1Open ↗
08/28/2026X00151478-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
04/15/2019240252052Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
04/15/2019240252052Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/15/2019240252052Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
10/03/2019240252052Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
04/15/2019240252052Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
04/15/2019240252052Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
04/15/2019240252052Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/03/2019240252052Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
04/15/2019240252052Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
10/03/2019240252052Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
04/15/2019240252052Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/03/2019240252052Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
10/03/2019240252052Open ↗
04/15/2019240252052Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
04/15/2019240252052Open ↗
▸BISBOROUGH INTAKE FORM1
10/03/2019240252052Open ↗