Roof2p · 3 filings · 18 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Supported Scaffold
ERECT A NON-ILLUMINATED ACCESSORY POLE BANNER SIGN ON EXISTING BRACKETS @WEST 35 STREET ELEVATION VIEW. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Local Law 11 Facade Repairs work that includes brick masonry repairs, replacement of brick masonry parapet wall, cut and point mortar joints, etc. as shown on plans filed herewith. No change in use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
7 documents
Floor 151p · 1 filing · 8 docs
EquipmentMechanicalStructural
Issued Permit Scope
Mechanical Systems · Supported Scaffold
INSTALLATION OF 16 UNITS ON THE WEST STORE & MIDDLE STORE 1ST FLOOR, 9TH FLOOR, AND 15TH FLOOR WITH A TOTAL CAPACITY OF 70 TONS. NO CHANGE TO EGRESS, USE, OR OCCUPATION.
On file for this project
8 documents · 1 drawing sheet
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 91p · 1 filing · 8 docs
EquipmentMechanicalStructural
Issued Permit Scope
Mechanical Systems · Supported Scaffold
INSTALLATION OF 16 UNITS ON THE WEST STORE & MIDDLE STORE 1ST FLOOR, 9TH FLOOR, AND 15TH FLOOR WITH A TOTAL CAPACITY OF 70 TONS. NO CHANGE TO EGRESS, USE, OR OCCUPATION.
On file for this project
8 documents · 1 drawing sheet
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 31p · 1 filing · 10 docs
EquipmentMechanicalStructural
Issued Permit Scope
Mechanical Systems · Supported Scaffold
INSTALLATION OF AIR HANDLERS AND CONDENSER UNITS ON THE 3RD FLOOR WITH A TOTAL CAPACITY OF 28 TONS. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
On file for this project
10 documents · 1 drawing sheet
Floor 21p · 1 filing · 7 docs
EquipmentMechanicalStructural
Issued Permit Scope
Mechanical Systems · Supported Scaffold
INSTALLATION OF 2 UNITS ON THE 10TH FLOOR WITH A TOTAL CAPACITY OF 10 TONS. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
Floor 15p · 11 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural · Supported Scaffold
Sprinkler changes on the 1st floor and mezzanine as indicated on drawings.
On file for this project
5 documents
Standpipe changes on the 1st floor as indicated on drawings.
On file for this project
5 documents · 1 drawing sheet
Architectural changes on the 1st floor and mezzanine as indicated on drawings.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 11 filings on this floor.
Mezzanine2p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Sprinkler changes on the 1st floor and mezzanine as indicated on drawings.
On file for this project
5 documents
Architectural changes on the 1st floor and mezzanine as indicated on drawings.
On file for this project
5 documents
Mechanical changes on the 1st floor and mezzanine as indicated on drawings.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Cellar6p · 4 filings · 20 docs
ArchitectureCivilFire ProtectionMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Plumbing · Sprinklers
REPLACEMENT (1) NEW COMBINATION GAS/OIL BURNER ON (1) EXISTING LOW PRESSURE BOILER. CHANGE GRADE OF FUEL OIL FROM #4 TO #2 OIL. NO CHANGE IN MEANS OF EGRESS USE GROUP OR OCCUPANCY.
On file for this project
32 documents · 3 drawing sheets
Propose sprinkler modifications at cellar, 001 and mezzanine floors all as per plans herewith filed. No change in use, egress, or occupancy filed under this application.
On file for this project
4 documents
Plumbing work in conjunction with interior renovation of an existing commercial space on the cellar, first, and mezzanine floors of an existing commercial building. No change in use, occupancy, or egress.
On file for this project
10 documents
Latest 3 of 4 filings on this floor.
Site & exterior7 filings · 18 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · General Construction · Protection and Mechanical Methods · Sidewalk Shed · Sign · Supported Scaffold
ERECT AN ILLUMINATED ACCESSORY CABINET SIGN @WEST 35 STREET ELEVATION VIEW. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. (NEW YORK BLOOD CENTER)
On file for this project
5 documents · 3 drawing sheets
ERECT A NON-ILLUMINATED ACCESSORY POLE BANNER SIGN ON EXISTING BRACKETS @WEST 35 STREET ELEVATION VIEW. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 3 drawing sheets
Local Law 11 Facade Repairs work that includes brick masonry repairs, replacement of brick masonry parapet wall, cut and point mortar joints, etc. as shown on plans filed herewith. No change in use, egress or occupancy.
On file for this project
8 documents · 4 drawing sheets
Latest 3 of 7 filings on this floor.
Filed — no permit issued5 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbing
Standpipe changes on the 1st floor as indicated on drawings.
On file for this project
6 documents · 3 drawing sheets
No filed description on record for this project.
On file for this project
8 documents · 5 drawing sheets
No filed description on record for this project.
On file for this project
6 documents · 5 drawing sheets
Latest 3 of 5 filings on this floor.