← Back
BuildNYC
Stand-alone food establishment
255-06 HILLSIDE AVENUE
QUEENS · BIN 4826263
💬 Discuss this project
1979Year Built
1Stories
K5Building Class
R3-2Zoning
2,740 sfGross Floor Area
1Units
Stand-alone food establishment · Owner of record: M.A. Francioni & Daughters · 5,000 sf lot · 0.55 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofDunkin' / Baskin-robbins OmniUnder Construction5p · 1 filing · 20 docs
Floor 1Dunkin' / Baskin-robbins OmniUnder Construction21p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Zelta Design206/27/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Epac Building Consulting403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Btu Delta Construction *General Contractor507/03/2026
Tri State Plumbing & HeatingPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
G Engineering7778103/05/2022
Building Lifecycle
All (36)Filed (2)Permit Issued (5)Objection (10)Special Inspection (19)
06/04/2026
Permit issued — Mechanical Systems
Q00678818-I1-GC
06/18/2025
Permit issued — Structural
Q00678818-I1-GC
11/18/2024
Permit issued — Plumbing
Q00678818-S1-PL
06/26/2024
Permit issued — General Construction
Q00678818-I1-GC
10/14/2022
Permit issued — Plumbing
Q00678818-S1-PL
06/27/2022
Filed — Alteration CO
PROPOSED RENOVATION AT EXISTING COMMERCIAL SPACE FOR AN EATING & DRINKING ESTABLISHMENT; PARTIAL DEMO PORTION OF THE EXTERIOR WALL TO CREATE AN ACCESSORY DRIVE THRU AT THE FIRST FLOOR LEVEL; PROPOSED SEVEN OPEN PARKING SPACES. OBTAIN A NEW C OF O.
Q00678818-S1
03/12/2022
Objection raised — Scope
03/12/2022
Objection resolved — Addressed
03/12/2022
Objection raised — Energy
03/12/2022
Objection resolved — Addressed
03/12/2022
Objection raised — Admin
03/12/2022
Objection resolved — Addressed
03/12/2022
Objection raised — Zoning
03/12/2022
Objection resolved — Addressed
03/12/2022
Objection raised — Zoning
03/12/2022
Objection resolved — Addressed
03/05/2022
Filed — Alteration CO
PROPOSED RENOVATION AT EXISTING COMMERCIAL SPACE FOR AN EATING & DRINKING ESTABLISHMENT; PARTIAL DEMO PORTION OF THE EXTERIOR WALL TO CREATE AN ACCESSORY DRIVE THRU AT THE FIRST FLOOR LEVEL; PROPOSED SEVEN OPEN PARKING SPACES. OBTAIN A NEW C OF O.
Q00678818-I1
02/23/2022
Special inspection requirement — Fenestration areas
XIONGCAI GU
02/23/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
XIONGCAI GU
02/23/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
XIONGCAI GU
02/23/2022
Special inspection requirement — Shutoff dampers
XIONGCAI GU
02/23/2022
Special inspection requirement — Lighting controls
XIONGCAI GU
02/23/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIONGCAI GU
02/23/2022
Special inspection requirement — Energy Code Compliance Inspections
XIONGCAI GU
02/23/2022
Special inspection requirement — HVAC-R and service water heating equipment
XIONGCAI GU
02/23/2022
Special inspection requirement — Air barrier - visual inspection
XIONGCAI GU
02/23/2022
Special inspection requirement — Interior lighting power
XIONGCAI GU
02/23/2022
Special inspection requirement — Fenestration air leakage
XIONGCAI GU
02/23/2022
Special inspection requirement — HVAC-R and service water heating system controls
XIONGCAI GU
02/23/2022
Special inspection requirement — Duct leakage testing, insulation and design
XIONGCAI GU
02/23/2022
Special inspection requirement — Exterior lighting power
XIONGCAI GU
02/23/2022
Special inspection requirement — Maintenance information
XIONGCAI GU
02/11/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
XIONGCAI GU
02/11/2022
Special inspection requirement — Mechanical Systems
XIONGCAI GU
02/11/2022
Special inspection requirement — Structural Steel - Details
XIONGCAI GU
02/11/2022
Special inspection requirement — Final
XIONGCAI GU
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedBtu Delta Construction *06/04/2026
DOB NOWStructuralPermit IssuedBtu Delta Construction *06/18/2025
DOB NOWPlumbingPermit IssuedDW Plumbing11/18/2024
DOB NOWGeneral ConstructionPermit IssuedBtu Delta Construction *06/26/2024
DOB NOWPlumbingPermit IssuedDW Plumbing10/14/2022
1 project · most recent 06/27/2022
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/27/2022Permit IssuedBtu Delta Construction *Air Conditioning Systems
Cooling
Trane YHC072F3RMA-HOBA1A 6 tons · Condensing Unit ×1
1 project · most recent 06/27/2022
Gas Water/Sanitary
FiledStatusContractorScope
06/27/2022Permit IssuedTri State Plumbing & HeatingGas, Water/Sanitary
1 project · most recent 06/27/2022
Steel
FiledStatusContractorScope
06/27/2022Permit IssuedBtu Delta Construction *Steel
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
02/23/2022Fenestration areasXIONGCAI GUenergy_progress
02/23/2022Fenestration and door U-factor and product ratingsXIONGCAI GUenergy_progress
02/23/2022HVAC-R and service water piping design and insulationXIONGCAI GUenergy_progress
02/23/2022Shutoff dampersXIONGCAI GUenergy_progress
02/23/2022Lighting controlsXIONGCAI GUenergy_progress
02/23/2022Fire-Resistant Penetrations and JointsXIONGCAI GUspecial
02/23/2022Energy Code Compliance InspectionsXIONGCAI GUprogress
02/23/2022HVAC-R and service water heating equipmentXIONGCAI GUenergy_progress
02/23/2022Air barrier - visual inspectionXIONGCAI GUenergy_progress
02/23/2022Interior lighting powerXIONGCAI GUenergy_progress
02/23/2022Fenestration air leakageXIONGCAI GUenergy_progress
02/23/2022HVAC-R and service water heating system controlsXIONGCAI GUenergy_progress
02/23/2022Duct leakage testing, insulation and designXIONGCAI GUenergy_progress
02/23/2022Exterior lighting powerXIONGCAI GUenergy_progress
02/23/2022Maintenance informationXIONGCAI GUenergy_progress
02/11/2022Structural Stability – Alterations of existing buildingsXIONGCAI GUspecial
02/11/2022Mechanical SystemsXIONGCAI GUspecial
02/11/2022Structural Steel - DetailsXIONGCAI GUspecial
02/11/2022FinalXIONGCAI GUprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Dunkin' / Baskin-robbins OmniRestaurant / Food ServiceFloor 1, Roof
Project Q00678818 Alteration CO · Permit Issued · 03/05/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 29 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/26/2026Q00678818-I1Request digital key ↗
08/26/2026Q00678818-S1Request digital key ↗
▸Seals & Professional Certifications21
▸DOB NOWProgress Inspector Seal & Signature15
08/26/2026Q00678818-I1Open ↗
08/26/2026Q00678818-I1Open ↗
08/26/2026Q00678818-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/26/2026Q00678818-I1Open ↗
08/26/2026Q00678818-I1Open ↗
08/26/2026Q00678818-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q00678818-S1Open ↗
08/13/2026Q00678818-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026Q00678818-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q00678818-I1Open ↗
08/13/2026Q00678818-S1Open ↗
▸DOB NOWOER: Notice to Proceed2
08/13/2026Q00678818-I1Open ↗
08/13/2026Q00678818-S1Open ↗
▸Other Documents1
▸DOB NOWProperty Ownership Certification1
08/13/2026Q00678818-I1Open ↗