| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/14/2022 | $1.3M | — | 255 BB LLC → B & A DEVELOPMENT OF NY, LLC | $510/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Kindo | 2 | 06/12/2026 |
| Chon Engineering | 4 | 05/29/2026 |
| Madriaga Engineering | 1 | 12/03/2024 |
| Winton Group Architecture | 1 | 07/09/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| AR Kissil | 8 | 03/21/2026 |
| Skyline Building Consulting | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| V.A.N. Construction | General Contractor | 2 | 07/08/2026 |
| Nilcomat | General Contractor | 1 | 04/09/2026 |
| Plumbing NYC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Winton Group Architecture | 4343 | 2 | 06/12/2026 |
| Chon Engineering | 2454 | 4 | 05/29/2026 |
| J&R Design and Inspection | 6637 | 1 | 12/03/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | V.A.N. Construction | 07/06/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Nilcomat | 03/09/2026 |
| DOB NOW | Plumbing | Permit Issued | Plumbing Works NYC | 02/10/2026 |
| DOB NOW | General Construction | Permit Issued | V.A.N. Construction | 09/02/2025 |
| BIS | PL | ISSUED | Plumbing NYC | 03/29/2010 |
| BIS | EQ | ISSUED | B & K Advance Laundromat | 03/22/2010 |
| BIS | OT | ISSUED | B & K Advance Laundromat | 03/22/2010 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/03/2024 | Permit Issued | Nilcomat | Heating and Air Conditioning Systems | Heat / Cool Cooper & Hunter CH-N60LCU-230VO, CH-60LCDTU/I 54,000 BTU · Heat Pump Outdoor ×5 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/12/2026 | — | — | 26 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/12/2026 | Permit Issued | Plumbing Works NYC | Gas, Plumbing-Sprinkler, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/30/2025 | Permit Issued | Enterprise Electrical Systems | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/19/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/03/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/03/2026 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 03/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/23/2026 | Fire-Resistant Penetrations and Joints | Steve Chon | special |
| 07/23/2026 | Energy Code Compliance Inspections | Steve Chon | progress |
| 07/23/2026 | HVAC-R and service water piping design and insulation | Steve Chon | energy_progress |
| 07/23/2026 | HVAC-R and service water heating equipment | Steve Chon | energy_progress |
| 07/23/2026 | HVAC-R and service water heating system controls | Steve Chon | energy_progress |
| 06/11/2026 | Fire-Resistance Rated Construction | Vladimir Kaushansky | progress |
| 06/11/2026 | Fenestration areas | Vladimir Kaushansky | energy_progress |
| 06/11/2026 | Fenestration and door U-factor and product ratings | Vladimir Kaushansky | energy_progress |
| 06/11/2026 | Air barrier - visual inspection | Vladimir Kaushansky | energy_progress |
| 06/11/2026 | Interior lighting power | Vladimir Kaushansky | energy_progress |
| 06/11/2026 | Insulation placement and R values | Vladimir Kaushansky | energy_progress |
| 06/11/2026 | Maintenance information | Vladimir Kaushansky | energy_progress |
| 06/11/2026 | Concrete - Cast-In-Place | Vladimir Kaushansky | special |
| 06/11/2026 | Fire-Resistant Penetrations and Joints | Vladimir Kaushansky | special |
| 06/11/2026 | Masonry | Vladimir Kaushansky | special |
| 06/11/2026 | Structural Stability – Alterations of existing buildings | Vladimir Kaushansky | special |
| 06/11/2026 | Energy Code Compliance Inspections | Vladimir Kaushansky | progress |
| 05/20/2026 | HVAC-R and service water heating equipment | Steve Chon | energy_progress |
| 05/20/2026 | HVAC-R and service water piping design and insulation | Steve Chon | energy_progress |
| 05/20/2026 | HVAC-R and service water heating system controls | Steve Chon | energy_progress |
| 05/20/2026 | Energy Code Compliance Inspections | Steve Chon | progress |
| 05/20/2026 | Fire-Resistant Penetrations and Joints | Steve Chon | special |
| 09/19/2024 | Air barrier - visual inspection | Vladimir Kaushansky | energy_progress |
| 09/19/2024 | Concrete - Cast-In-Place | Vladimir Kaushansky | special |
| 09/19/2024 | Masonry | Vladimir Kaushansky | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Brightway Laundry | Personal services | Floors 1, 2 | Project B00909655 |