| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Permit Issued | METROPOLITAN ELEC OF NY I | General Wiring |
| 09/08/2022 | Complete | ABM ELECTRIC, INC | General Wiring |
| 03/04/2022 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 07/08/2021 | Complete | NAIR ELECTRIC CORP | General Wiring |
| 08/10/2020 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 11/27/2019 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 01/25/2019 | Complete | SAMCO ELECTRIC CORP. | — |
| 11/13/2018 | Complete | SAMCO ELECTRIC CORP. | General Wiring |
| 05/23/2018 | Permit Issued | STANCO SYSTEM ELEC'L CONT | — |
| 04/16/2018 | Permit Issued | STANCO SYSTEM ELEC'L CONT | — |
| Owner | Filings | Most Recent |
|---|---|---|
| NYC DEPARTMENT OF EDUCATION | 1 | 03/22/2026 |
| DEPARTMENT OF EDUCATION | 5 | 03/22/2026 |
| DEPT OF EDUCATION P.S. 12 | 12 | 03/22/2026 |
| DOE PS 12 040 | 2 | 03/22/2026 |
| DEPT. OF EDUCATION P.S. 1 | 2 | 03/22/2026 |
| P.S.12 LEWIS & CLARK SCHO | 3 | 03/22/2026 |
| LEWIS & CLARK SCHOOL D.O. | 10 | 03/22/2026 |
| PS 12 D.O.E | 2 | 03/22/2026 |
| PS 12 DEPT OF EDUCATION | 2 | 03/22/2026 |
| PS 12 DEPT OF ED | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SHENOY ENGINEERING, P.C. | 3 | 04/10/2025 |
| SBLM ARCHITECTS, PC | 2 | 03/11/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| SBLM | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LUCIANT CONSULTING CORP | General Contractor | 5 | 08/26/2026 |
| ARAMIS ROSA | Electrical | 1 | 03/21/2026 |
| GASTON STEPHENSON | Electrical | 1 | 03/21/2026 |
| STANCO SYSTEM ELEC'L CONT | Electrical | 1 | 03/22/2026 |
| VARSITY PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 4 | 04/10/2025 |
| MP ENGINEERS & ARCHITECTS | 1438 | 1 | 08/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | LUCIANT CONSULTING CORP | 08/25/2026 |
| DOB NOW | General Construction | Permit Issued | LUCIANT CONSULTING CORP | 08/25/2026 |
| DOB NOW | General Construction | Permit Issued | LUCIANT CONSULTING CORP | 06/15/2026 |
| DOB NOW | General Construction | Permit Issued | LUCIANT CONSULTING CORP | 05/26/2026 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 05/21/2026 |
| DOB NOW | General Construction | Permit Issued | LUCIANT CONSULTING CORP | 04/27/2026 |
| BIS | PL | ISSUED | TRISTAR PLUMBING & HTG IN | 12/04/2023 |
| BIS | PL | ISSUED | TRISTAR PLUMBING & HTG IN | 12/04/2023 |
| BIS | OT | ISSUED | RICI CORP | 07/03/2023 |
| BIS | EQ | ISSUED | RICI CORP | 09/07/2022 |
| BIS | EQ | ISSUED | RICI CORP | 08/31/2022 |
| BIS | EQ | ISSUED | RICI CORP | 08/31/2022 |
| BIS | OT | ISSUED | RICI CORP | 05/20/2022 |
| BIS | OT | ISSUED | RICI CORP | 01/29/2021 |
| BIS | EQ | ISSUED | RICI CORP | 05/26/2020 |
| BIS | EQ | ISSUED | RICI CORP | 05/08/2020 |
| BIS | EQ | ISSUED | RICI CORP | 05/04/2020 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 02/05/2020 |
| BIS | OT | ISSUED | RICI CORP | 01/24/2020 |
| BIS | OT | ISSUED | RICI CORP | 01/07/2020 |
| BIS | EQ | ISSUED | RICI CORP | 04/17/2019 |
| BIS | EQ | ISSUED | RICI CORP | 04/17/2019 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 02/06/2019 |
| BIS | OT | ISSUED | RICI CORP | 01/18/2019 |
| BIS | OT | ISSUED | D & K CONSTRUCTION CO INC | 11/23/2018 |
| BIS | OT | ISSUED | RICI CORP | 06/01/2018 |
| BIS | EQ | ISSUED | RICI CORP | 06/01/2018 |
| BIS | EQ | ISSUED | RICI CORP | 04/18/2018 |
| BIS | EQ | ISSUED | RICI CORP | 04/18/2018 |
| BIS | OT | ISSUED | TECHNICO CONSTRUCTION | 02/26/2016 |
| BIS | PL | ISSUED | EAGLE 1 MECHANICAL, INC | 02/23/2016 |
| BIS | OT | ISSUED | STANCO SYSTEMS ELECTRICAL | 01/26/2016 |
| BIS | OT | ISSUED | MARIC MECHANICAL INC | 12/15/2015 |
| BIS | OT | ISSUED | TECHNICO CONSTRUCTION | 09/03/2015 |
| BIS | OT | ISSUED | STANCO SYSTEMS ELECTRICAL | 03/20/2015 |
| BIS | OT | ISSUED | STANCO SYSTEMS ELECTRICAL | 03/19/2015 |
| BIS | OT | ISSUED | TECHNICO CONSTRUCTION | 02/18/2015 |
| BIS | OT | ISSUED | STANCO SYSTEMS ELECTRICAL | 10/03/2014 |
| BIS | MH | ISSUED | MARIC MECHANICAL INC | 09/05/2014 |
| BIS | OT | ISSUED | MARIC MECHANICAL INC | 08/25/2014 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/10/2025 | Lighting controls | JAMES WILSON | energy_progress |
| 04/10/2025 | Maintenance information | JAMES WILSON | energy_progress |
| 04/10/2025 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 04/10/2025 | Energy Code Compliance Inspections | JAMES WILSON | progress |
| 04/10/2025 | Interior lighting power | JAMES WILSON | energy_progress |
| 01/23/2025 | Fire-Resistance Rated Construction | GEORGE GHEBRYAL | progress |
| 10/04/2024 | Energy Code Compliance Inspections | JAMES WILSON | progress |
| 07/10/2024 | Mechanical Systems | JAMES WILSON | special |
| 07/10/2024 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 07/10/2024 | Heating Systems | JAMES WILSON | special |
| 07/10/2024 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 07/10/2024 | Final | GEORGE GHEBRYAL | progress |
| 07/10/2024 | HVAC-R and service water heating system controls | JAMES WILSON | energy_progress |
| 07/10/2024 | HVAC-R and service water piping design and insulation | JAMES WILSON | energy_progress |
| 07/10/2024 | HVAC-R and service water heating equipment | JAMES WILSON | energy_progress |
| 07/10/2024 | Maintenance information | JAMES WILSON | energy_progress |
| 07/10/2024 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 07/10/2024 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 07/10/2024 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 07/10/2024 | Energy Code Compliance Inspections | JAMES WILSON | progress |
| 07/10/2024 | HVAC-R and service water piping design and insulation | JAMES WILSON | energy_progress |
| 07/10/2024 | Maintenance information | JAMES WILSON | energy_progress |