2552 HOLLAND AVENUE
BRONX · Allerton · BIN 2051387
💬 Discuss this project
1910Year Built
2Stories
C0Building Class
R6Zoning
3,399 sfGross Floor Area
3Units
Rent Stabilized19 Open Violations ▸FDNY Report ↗
Three families · 2,400 sf lot · 1.42 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR111/15/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281111/15/2024
Building Lifecycle
All (28)Filed (1)Permit Issued (1)Signed Off (1)Violation (20)Special Inspection (5)
04/30/2026
Violation issued (HPD, open)
A
12/15/2025
Signed off — Alteration
X01138593-I1
11/18/2025
Violation issued (HPD, open)
I
06/05/2025
Violation issued (HPD, open)
A
11/25/2024
Permit issued — Solar
X01138593-I1-SL
11/25/2024
Violation issued (HPD, open)
I
11/15/2024
Filed — Alteration
X01138593-I1
11/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
11/06/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
11/06/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
11/06/2024
Special inspection requirement — Final
Mina Makar
11/06/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
04/02/2024
Violation issued (HPD, open)
A
11/16/2023
Violation issued (HPD, open)
I
03/17/2023
Violation issued (HPD, open)
A
11/04/2022
Violation issued (HPD, open)
I
02/17/2022
Violation issued (HPD, open)
I
02/17/2022
Violation issued (HPD, open)
A
04/02/2021
Violation issued (HPD, open)
I
04/02/2021
Violation issued (HPD, open)
A
10/28/2019
Violation issued (HPD, open)
I
10/11/2018
Violation issued (HPD, open)
I
11/13/2017
Violation issued (HPD, open)
I
10/31/2016
Violation issued (HPD, open)
I
10/05/2015
Violation issued (HPD, open)
I
02/04/2015
Violation issued (HPD, open)
I
12/30/2007
Violation issued (HPD, open)
B
01/20/1982
Violation issued (HPD, closed)
A
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR11/25/2024
1 project · most recent 07/17/2025
FiledStatusContractorScope
07/17/2025CompleteISLAND ELECTRIC CORP3 meters
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
11/06/2024Fire-Resistant Penetrations and JointsMina Makarspecial
11/06/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
11/06/2024Energy Code Compliance InspectionsMina Makarprogress
11/06/2024FinalMina Makarprogress
11/06/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026X01138593-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026X01138593-I1Open ↗
08/24/2026X01138593-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026X01138593-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/24/2026X01138593-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X01138593-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01138593-I1Open ↗