← Back
Four families
256 DEAN STREET
BROOKLYN · BIN 3001423
💬 Discuss this project
1920Year Built
3Stories
C3Building Class
R6BZoning
3,520 sfGross Floor Area
4Units
Rent Stabilized21 Open Violations ▸FDNY Report ↗
Four families · Owner of record: 1 STAGED PLACE LLC · 1,700 sf lot · 2.07 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalFire ProtectionOther
Roof2p · 1 filing · 18 docs
Floor 11p · 1 filing · 18 docs
Cellar1p · 1 filing · 18 docs
Basement2p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GOLAN MANAGEMENT903/22/2026
1 STAGED PLACE LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/28/2022$2.2M—— → —$625/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DOYUN KIM; RA507/17/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC BUILDING SOLUTIONS503/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYC BUILDING SOLUTIONS COGeneral Contractor603/21/2026
HORBRIDGE PLUMBING & HEATINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOYUN KIM; RA7415507/17/2023
Building Lifecycle
All (80)Filed (5)Permit Issued (3)Signed Off (2)Violation (27)Inspection (5)Objection (8)Special Inspection (30)
05/04/2026
Violation issued (HPD, open)
A
11/19/2025
Violation issued (HPD, open)
I
06/09/2025
Violation issued (HPD, open)
A
11/27/2024
Violation issued (HPD, open)
I
04/09/2024
Violation issued (HPD, open)
A
11/20/2023
Violation issued (HPD, open)
I
07/27/2023
Signed off — Alteration
HEREWITH FILING TO INSTALL PLUMBING SYSTEM AS PER PLANS. IN CONJUNCTION WITH DOB #B07998187.
B00777059-I1
07/26/2023
Signed off — Alteration
HEREWITH TO PROPOSE ALTERATION WORK AS PER PLANS, UPDATE WINDOWS AND EXISTING FINISHES,NEW GYP BOARD TO EXISTING 4 UNIT DWELLING, NO CHANGE IN USE, OCCUPANCY, OR EGERSS.
B07998187-I1
07/25/2023
Special inspection requirement — Mechanical Systems
DOYUN KIM
07/25/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
DOYUN KIM
07/25/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
DOYUN KIM
07/25/2023
Special inspection requirement — Fire-Resistance Rated Construction
DOYUN KIM
07/25/2023
Special inspection requirement — Final
DOYUN KIM
07/25/2023
Special inspection requirement — Energy Code Compliance Inspections
DOYUN KIM
07/25/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
DOYUN KIM
07/25/2023
Special inspection requirement — Fenestration air leakage
DOYUN KIM
07/25/2023
Special inspection requirement — Air barrier - visual inspection
DOYUN KIM
07/25/2023
Special inspection requirement — Fenestration areas
DOYUN KIM
07/25/2023
Special inspection requirement — HVAC-R and service water heating equipment
DOYUN KIM
07/25/2023
Special inspection requirement — Insulation placement and R values
DOYUN KIM
07/25/2023
Special inspection requirement — Permanent certificate
DOYUN KIM
07/25/2023
Special inspection requirement — HVAC-R and service water heating system controls
DOYUN KIM
07/25/2023
Special inspection requirement — Interior lighting power
DOYUN KIM
07/25/2023
Special inspection requirement — Lighting in dwelling units
DOYUN KIM
07/25/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
DOYUN KIM
07/25/2023
Special inspection requirement — Maintenance information
DOYUN KIM
07/25/2023
Special inspection requirement — Lighting controls
DOYUN KIM
07/17/2023
Filed — Alteration
HEREWITH TO PROPOSE ALTERATION WORK AS PER PLANS, UPDATE WINDOWS AND EXISTING FINISHES,NEW GYP BOARD TO EXISTING 4 UNIT DWELLING, NO CHANGE IN USE, OCCUPANCY, OR EGERSS.
B07998187-P2
06/16/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
06/15/2023
Special inspection requirement — Energy Code Compliance Inspections
DOYUN KIM
06/15/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
DOYUN KIM
06/12/2023
Filed — Alteration
HEREWITH FILING TO INSTALL PLUMBING SYSTEM AS PER PLANS. IN CONJUNCTION WITH DOB #B07998187.
B00777059-P1
06/07/2023
Special inspection requirement — Maintenance information
DOYUN KIM
06/07/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
DOYUN KIM
06/07/2023
Special inspection requirement — Mechanical Systems
DOYUN KIM
06/07/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
DOYUN KIM
06/07/2023
Special inspection requirement — Energy Code Compliance Inspections
DOYUN KIM
06/07/2023
Special inspection requirement — Final
DOYUN KIM
06/07/2023
Special inspection requirement — Fire-Resistance Rated Construction
DOYUN KIM
06/07/2023
Special inspection requirement — Air barrier - visual inspection
DOYUN KIM
06/07/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
DOYUN KIM
05/26/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
03/22/2023
Violation issued (HPD, open)
A
02/03/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
02/03/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/03/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/03/2023
Permit issued — Mechanical Systems
B07998187-I1-GC-CX
12/14/2022
Permit issued — Plumbing
B00777059-I1-PL
12/09/2022
Objection resolved — Addressed
12/09/2022
Objection resolved — Addressed
12/09/2022
Objection resolved — Addressed
12/09/2022
Objection resolved — Addressed
12/05/2022
Objection raised — Admin
12/05/2022
Objection raised — Admin
12/05/2022
Objection raised — Admin
12/05/2022
Objection raised — Other
11/28/2022
Filed — Alteration
HEREWITH FILING TO INSTALL PLUMBING SYSTEM AS PER PLANS. IN CONJUNCTION WITH DOB #B07998187.
B00777059-I1
11/09/2022
Violation issued (HPD, open)
I
10/25/2022
Permit issued — Mechanical Systems
B07998187-I1-GC-CX
10/17/2022
Filed — Alteration
HEREWITH TO PROPOSE ALTERATION WORK AS PER PLANS, UPDATE WINDOWS AND EXISTING FINISHES,NEW GYP BOARD TO EXISTING 4 UNIT DWELLING, NO CHANGE IN USE, OCCUPANCY, OR EGERSS.
B07998187-P1
Latest 60 of 80 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offNYC BUILDING SOLUTIONS CO01/03/2023
DOB NOWPlumbingSigned-offHORBRIDGE PLUMBING & HEAT12/14/2022
DOB NOWMechanical SystemsSigned-offNYC BUILDING SOLUTIONS CO10/25/2022
1 job · most recent 12/14/2022
FiledStatusContractorScope
12/14/2022Permit IssuedJECO ELEC'L SERVICE CORP.5 meters, 5 new_meters
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
06/16/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
05/26/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
02/03/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/03/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/03/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 59
DateRequirementInspectorRole
07/25/2023Mechanical SystemsDOYUN KIMspecial
07/25/2023Structural Stability – Alterations of existing buildingsDOYUN KIMspecial
07/25/2023Fire-Resistant Penetrations and JointsDOYUN KIMspecial
07/25/2023Fire-Resistance Rated ConstructionDOYUN KIMprogress
07/25/2023FinalDOYUN KIMprogress
07/25/2023Energy Code Compliance InspectionsDOYUN KIMprogress
07/25/2023Fenestration and door U-factor and product ratingsDOYUN KIMenergy_progress
07/25/2023Fenestration air leakageDOYUN KIMenergy_progress
07/25/2023Air barrier - visual inspectionDOYUN KIMenergy_progress
07/25/2023Fenestration areasDOYUN KIMenergy_progress
07/25/2023HVAC-R and service water heating equipmentDOYUN KIMenergy_progress
07/25/2023Insulation placement and R valuesDOYUN KIMenergy_progress
07/25/2023Permanent certificateDOYUN KIMenergy_progress
07/25/2023HVAC-R and service water heating system controlsDOYUN KIMenergy_progress
07/25/2023Interior lighting powerDOYUN KIMenergy_progress
07/25/2023Lighting in dwelling unitsDOYUN KIMenergy_progress
07/25/2023HVAC-R and service water piping design and insulationDOYUN KIMenergy_progress
07/25/2023Maintenance informationDOYUN KIMenergy_progress
07/25/2023Lighting controlsDOYUN KIMenergy_progress
06/15/2023Energy Code Compliance InspectionsDOYUN KIMprogress
06/15/2023Fire-Resistant Penetrations and JointsDOYUN KIMspecial
06/07/2023Maintenance informationDOYUN KIMenergy_progress
06/07/2023Fire-Resistant Penetrations and JointsDOYUN KIMspecial
06/07/2023Mechanical SystemsDOYUN KIMspecial
06/07/2023Structural Stability – Alterations of existing buildingsDOYUN KIMspecial
Latest 25 of 59.
▾Documents — 26 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/28/2026B07998187-P2Request digital key ↗
08/28/2026B07998187-I1Request digital key ↗
08/28/2026B07998187-P1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature7
09/02/2026B07998187-P2Open ↗
09/02/2026B07998187-P2Open ↗
08/25/2026B07998187-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/28/2026B07998187-I1Open ↗
08/28/2026B07998187-P1Open ↗
08/28/2026B07998187-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026B07998187-P2Open ↗
08/25/2026B00777059-I1Open ↗
08/25/2026B07998187-P1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/28/2026B07998187-P1Open ↗
08/28/2026B07998187-I1Open ↗
08/28/2026B07998187-P2Open ↗
Showing 3 of 5 on file for this type