← Back
BuildNYC
Two family frame
256 ESSEX STREET
BROOKLYN · Cypress Hills · BIN 3088379
💬 Discuss this project
1901Year Built
2Stories
B2Building Class
R6BZoning
2,082 sfGross Floor Area
2Units
0 Active ViolationsFDNY Report ↗
Two family frame · Owner of record: 256 Essex Street · 5,283 sf lot · 0.39 FAR built · Flood zone X
Locations of Work
StructuralEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof2p · 1 filing · 14 docs
Penthouse1 filing · 20 docs
Floor 22p · 1 filing · 14 docs
Floor 12p · 2 filings · 20 docs
Cellar1 filing · 20 docs
Site & exteriorConstruction fence and sidewalk shed9p · 2 filings · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Class Iron Designs2210/04/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/11/2023$725K—Private party → 256 ESSEX STREET LLC$348/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
David Reyhan308/18/2026
S. Wieder Architect502/11/2026
Adroit Engineering212/28/2023
AP Professional Engineering112/22/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Advanced Builders Services503/21/2026
Sandeep Kaur103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Star CompaniessGeneral Contractor303/21/2026
Parsons ConstructionScaffold303/21/2026
Star CompaniessScaffold303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Regional Testing394708/18/2026
Adroit Engineering8885110/25/2023
Building Lifecycle
09/24/2026
Objection resolved — Addressed
09/21/2026
Objection resolved — Addressed
08/31/2026
Objection raised — Admin
08/31/2026
Objection raised — Structural
08/31/2026
Objection raised — Other
79 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFull DemolitionSigned-offStar Companiess02/16/2024
DOB NOWConstruction FenceSigned-offStar Companiess12/29/2023
DOB NOWSidewalk ShedPermit IssuedParsons Construction12/22/2023
1 project · most recent 12/22/2023
Sidewalk Shed
FiledStatusContractorScope
12/22/2023Permit IssuedParsons ConstructionSidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 42
DateRequirementInspectorRole
06/03/2026Concrete - Cast-In-PlacePaul Raymondspecial
06/03/2026Subsurface Investigations (Borings/Test Pits)—special
06/03/2026Subgrade InspectionsPaul Raymondspecial
04/30/2026Excavations - Sheeting, Shoring, and BracingPaul Raymondspecial
04/30/2026Excavations - Sheeting, Shoring, and BracingPaul Raymondspecial
04/30/2026Subsurface Investigations (Borings/Test Pits)—special
04/30/2026Subsurface Conditions – Fill Placement & In-Place DensityPaul Raymondspecial
04/30/2026Subgrade InspectionsPaul Raymondspecial
04/30/2026Concrete - Cast-In-PlacePaul Raymondspecial
04/30/2026Post-installed AnchorsPaul Raymondspecial
04/30/2026MasonryPaul Raymondspecial
04/30/2026Concrete - Cast-In-PlacePaul Raymondspecial
04/27/2026Structural Cold-Formed SteelPaul Raymondspecial
02/19/2026Structural Steel - DetailsPaul Raymondspecial
01/13/2026Post-installed AnchorsPaul Raymondspecial
01/13/2026Fire-Resistant Penetrations and JointsPaul Raymondspecial
09/22/2025FinalPaul Raymondprogress
09/22/2025FinalPaul Raymondprogress
09/22/2025Footing and FoundationPaul Raymondprogress
09/22/2025Sprinkler SystemsPaul Raymondspecial
08/19/2025Air barrier continuity plan testingPaul Raymondenergy_progress
07/14/2025Exterior Insulation and Finish Systems (EIFS)Paul Raymondspecial
07/14/2025VestibulesPaul Raymondenergy_progress
07/14/2025Protection of exposed foundation insulationPaul Raymondenergy_progress
07/14/2025Exterior lighting powerPaul Raymondenergy_progress
Latest 25 of 42.
55 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account