Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof8p · 1 filing · 15 docs
Mechanical
Issued Permit Scope
Mechanical Systems
INSTALLATION OF HVAC SYSTEM AND ROOFTOP UNIT FOR APT. #5A . NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
15 documents · 1 drawing sheet
Floor 6Structure reinforcement for conduit pipe run15p · 3 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
INSTALLATION OF HVAC SYSTEM AND ROOFTOP UNIT FOR APT. #5A . NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
15 documents
HEREWITH FILE FOR STRUCTURAL REINFORCEMENT FOR ELECTRICAL CONDUIT RUN THROUGH AS PLANS SHOWN, AND FIRE-STOPPING TO BE PROVIDED. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
On file for this project
17 documents · 1 drawing sheet
Installation of two electrical risers from the cellar to the 6th floor running through the public hallways at the south end of the building with fire-stopping provided. No change in use, egress, and occupancy
On file for this project
8 documents
Floor 5Unit 5A36p · 6 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
INSTALLATION OF HVAC SYSTEM AND ROOFTOP UNIT FOR APT. #5A . NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
15 documents · 2 drawing sheets
STRUCTURAL WORK: NEW SLAB PENETRATIONS AS INDICATED FOR RISER OFFSETS AND KITCHEN EXHAUST. REINFORCEMENT OF PRIMARY BATHROOM FLOOR FRAMING TO SUPPORT BATHTUB NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Renovation of Apartment #5A including removal and installation of interior partitions to relocate kitchen and bathroom on the 5th floor. Replacement of existing lot line windows and infill masonry opening. No change to use, egress, or occupancy,
On file for this project
9 documents
Latest 3 of 6 filings on this floor.
Floor 4Structure reinforcement for conduit pipe run9p · 2 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Structural
HEREWITH FILE FOR STRUCTURAL REINFORCEMENT FOR ELECTRICAL CONDUIT RUN THROUGH AS PLANS SHOWN, AND FIRE-STOPPING TO BE PROVIDED. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
On file for this project
17 documents · 1 drawing sheet
Installation of two electrical risers from the cellar to the 6th floor running through the public hallways at the south end of the building with fire-stopping provided. No change in use, egress, and occupancy
On file for this project
8 documents · 1 drawing sheet
Floor 3Unit 3A, Unit 3C, Unit 3N11p · 6 filings · 20 docs
ArchitectureGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Structural
Interior replacement of plumbing fixtures for two bathrooms
On file for this project
11 documents
HEREWITH FILE FOR STRUCTURAL REINFORCEMENT FOR ELECTRICAL CONDUIT RUN THROUGH AS PLANS SHOWN, AND FIRE-STOPPING TO BE PROVIDED. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
On file for this project
17 documents
Installation of two electrical risers from the cellar to the 6th floor running through the public hallways at the south end of the building with fire-stopping provided. No change in use, egress, and occupancy
On file for this project
8 documents
Latest 3 of 6 filings on this floor.
Floor 2Structure reinforcement for conduit pipe run7p · 2 filings · 20 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural
HEREWITH FILE FOR STRUCTURAL REINFORCEMENT FOR ELECTRICAL CONDUIT RUN THROUGH AS PLANS SHOWN, AND FIRE-STOPPING TO BE PROVIDED. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
On file for this project
17 documents
Installation of two electrical risers from the cellar to the 6th floor running through the public hallways at the south end of the building with fire-stopping provided. No change in use, egress, and occupancy
On file for this project
8 documents
Floor 1Unit 1A, Unit 1B, Unit 1C +215p · 4 filings · 20 docs
ArchitectureDMGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Structural
HEREWITH FILE FOR STRUCTURAL REINFORCEMENT FOR ELECTRICAL CONDUIT RUN THROUGH AS PLANS SHOWN, AND FIRE-STOPPING TO BE PROVIDED. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
On file for this project
17 documents
Installation of two electrical risers from the cellar to the 6th floor running through the public hallways at the south end of the building with fire-stopping provided. No change in use, egress, and occupancy
On file for this project
8 documents
CONVERT ELECTRIC DRYERS IN LAUNDRY ROOM TO GAS IN CELLAR. REPLACE GAS FIREPLACE UNIT IN APARTMENT 1S ON FIRST FLOOR. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
17 documents
Latest 3 of 4 filings on this floor.
MezzanineStructure reinforcement for conduit pipe run7p · 2 filings · 20 docs
ArchitectureStructural
Issued Permit Scope
General Construction · Structural
HEREWITH FILE FOR STRUCTURAL REINFORCEMENT FOR ELECTRICAL CONDUIT RUN THROUGH AS PLANS SHOWN, AND FIRE-STOPPING TO BE PROVIDED. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
On file for this project
17 documents
Installation of two electrical risers from the cellar to the 6th floor running through the public hallways at the south end of the building with fire-stopping provided. No change in use, egress, and occupancy
On file for this project
8 documents
CellarStructure reinforcement for conduit pipe run14p · 4 filings · 20 docs
ArchitecturePlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Structural
HEREWITH FILE FOR STRUCTURAL REINFORCEMENT FOR ELECTRICAL CONDUIT RUN THROUGH AS PLANS SHOWN, AND FIRE-STOPPING TO BE PROVIDED. NO CHANGE IN USE, EGRESS, AND OCCUPANCY.
On file for this project
17 documents
Installation of two electrical risers from the cellar to the 6th floor running through the public hallways at the south end of the building with fire-stopping provided. No change in use, egress, and occupancy
On file for this project
8 documents
Interior renovation of existing residential accessory use in the cellar area that is part of the 1st floor unit . Architectural / construction work only.
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Site & exteriorExterior yard lighting and timber work6p · 1 filing · 13 docs
Architecture
Issued Permit Scope
General Construction
Proposed renovation of the ext'g yard area of an residential building. Work involves new pavings, masonry steps, renovation of ext'g planters, timber curbs, new exterior landscape lighting and minor landscaping. No change in use, egress or occupancy.
On file for this project
13 documents · 8 drawing sheets