← Back
One story - permanent living quarter
257-04 87 ROAD
QUEENS · BIN 4180763
💬 Discuss this project
1945Year Built
1.5Stories
A2Building Class
R2AZoning
1,063 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.27 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/28/2016$505K—— → —$475/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC105/13/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN SOLAR ELECTL CORPElectrical103/22/2026
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272105/13/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
05/14/2026
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01222338-I1
05/19/2025
Permit issued — Solar
Q01222338-I1-SL
05/13/2025
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01222338-I1
05/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
05/07/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
05/07/2025
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
05/07/2025
Special inspection requirement — Final
Walid Abdulla
05/07/2025
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC05/19/2025
1 project · most recent 06/26/2025
General Wiring
FiledStatusContractorScope
06/26/2025CompleteSUNRUN SOLAR ELECTL CORPGeneral Wiring
1 project · most recent 05/13/2025
FiledStatusContractorScope
05/13/2025Signed-offSUNRUN INSTALLATION SVC9 panels, 3.64 kw, 189.2 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
05/07/2025Fire-Resistant Penetrations and JointsWalid Abdullaspecial
05/07/2025Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
05/07/2025Energy Code Compliance InspectionsWalid Abdullaprogress
05/07/2025FinalWalid Abdullaprogress
05/07/2025Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01222338-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026Q01222338-I1Open ↗
08/28/2026Q01222338-I1Open ↗
08/28/2026Q01222338-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q01222338-I1Open ↗
08/28/2026Q01222338-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01222338-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01222338-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01222338-I1Open ↗