| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/23/2025 | $695K | — | Private party → Private party | $434/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SYNERGIC DESIGN ARCHITECTS | 2 | 04/06/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACCORD POWER INC | General Contractor | 2 | 04/09/2026 |
| ACCORD POWER ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SYNERGIC DESIGN LLC | 8561 | 2 | 04/06/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 03/04/2026 |
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 11/20/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Complete | ACCORD POWER ELECTRIC LLC | General Wiring |
| 11/20/2025 | Complete | ACCORD POWER ELECTRIC LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/06/2026 | Signed-off | ACCORD POWER INC | 16 panels, 6.56 kw, 864.4 roof_area_sqft |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/06/2026 | Signed-off | ACCORD POWER INC | Tenant Protection Plan 72 Hour |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/06/2026 | Fire-Resistant Penetrations and Joints | Malathi Ananthakrishnan | special |
| 04/06/2026 | Structural Stability – Alterations of existing buildings | Malathi Ananthakrishnan | special |
| 04/06/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Malathi Ananthakrishnan | special |
| 04/06/2026 | Energy Code Compliance Inspections | Malathi Ananthakrishnan | progress |
| 04/06/2026 | Final | Malathi Ananthakrishnan | progress |
| 04/06/2026 | Air barrier - visual inspection | Malathi Ananthakrishnan | energy_progress |
| 04/02/2026 | Fire-Resistant Penetrations and Joints | Malathi Ananthakrishnan | special |
| 04/02/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Malathi Ananthakrishnan | special |
| 04/02/2026 | Structural Stability – Alterations of existing buildings | Malathi Ananthakrishnan | special |
| 04/02/2026 | Energy Code Compliance Inspections | Malathi Ananthakrishnan | progress |
| 04/02/2026 | Final | Malathi Ananthakrishnan | progress |
| 04/02/2026 | Air barrier - visual inspection | Malathi Ananthakrishnan | energy_progress |