← Back
Two family frame
257-35 145 AVENUE
QUEENS · Rosedale · BIN 4535951
💬 Discuss this project
2003Year Built
2Stories
B2Building Class
R3XZoning
—Gross Floor Area
2Units
1 Open Violation ▸FDNY Report ↗
Two family frame · 0.6 FAR built · Flood zone X500
Locations of Work
Plumbing
Cellar1p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
JUNARD903/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MCCRAY ARCHITECT P.C.210/12/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHVISION DESIGN STUDIO203/21/2026
D W G SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DWG SERVICES INCGeneral Contractor303/21/2026
GARLAND, DONALDElectrical103/21/2026
PAUL ZACHERElectrical103/21/2026
PROMO-PRO. LTDElectrical103/21/2026
CAPE PLUMBING INCPlumbing107/08/2026
Building Lifecycle
All (11)Filed (2)Permit Issued (2)Signed Off (1)Violation (5)Special Inspection (1)
08/14/2025
Violation issued (HPD, closed)
A
06/17/2024
Violation issued (ECB, open)
Construction
01/29/2024
Signed off — Alteration
PLANS FILED TO CREATE NEW FINISHED CELLAR NEW THREE PIECE BATHROOM NEW LAUNDRY ROOM ENCLOSED BOILER ROOM AND FINISHED PERIMETER WALL ALL AS PER PLAN NO CHANGE TO USE EGRESS OR OCCUPANCY.
Q00945962-I1
10/23/2023
Permit issued — Plumbing
Q00946006-I1-PL
10/18/2023
Permit issued — General Construction
Q00945962-I1-GC
10/12/2023
Filed — Alteration
PLANS FILED TO CREATE NEW FINISHED CELLAR NEW THREE PIECE BATHROOM NEW LAUNDRY ROOM ENCLOSED BOILER ROOM AND FINISHED PERIMETER WALL ALL AS PER PLAN NO CHANGE TO USE EGRESS OR OCCUPANCY.
Q00945962-I1
10/12/2023
Filed — Alteration
PLANS FILE TO INSTALL NEW 3 PIECE BATHROOM NEW WASHER MACHINE NEW DRYER MACHINE NEW LAUNDRY SINK ALL AS PER PLAN NO CHANGE TO USE EGRESS OR OCCUPANCY
Q00946006-I1
10/10/2023
Special inspection requirement — Final
Kevin McCray
09/22/2023
Violation issued (HPD, closed)
B
09/22/2023
Violation issued (HPD, closed)
B
09/22/2023
Violation issued (HPD, closed)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedCAPE PLUMBING INC10/23/2023
DOB NOWGeneral ConstructionSigned-offDWG SERVICES INC10/18/2023
BISOTISSUEDSOLARCITY ELECTRICAL NEW04/25/2017
BIS—ISSUEDJUNARD CO08/01/2003
BISEQISSUEDJUNARD CO07/15/2003
BIS—ISSUEDJUNARD CORP07/15/2003
BISPLISSUEDTHE PLBG COMPANY INC.07/02/2003
BISEQISSUEDJUNARD CO04/08/2003
BIS—ISSUEDJUNARD CO04/08/2003
BIS—ISSUEDJUNARD CORP04/03/2003
1 project · most recent 10/12/2023
Gas Water/Sanitary
FiledStatusContractorScope
10/12/2023Permit IssuedCAPE PLUMBING INCGas, Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
10/10/2023FinalKevin McCrayprogress
▾Documents — 26 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/24/2026Q00945962-I1Request digital key ↗
08/24/2026Q00946006-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
04/24/2017440398017Open ↗
▸BISWORK PERMIT APPLICATION1
04/24/2017440398017Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q00946006-I1Open ↗
08/13/2026Q00945962-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
04/24/2017440398017Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/24/2017440398017Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
04/24/2017440398017Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/29/2026Q00945962-I1Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
04/24/2017440398017Open ↗
▸Energy Compliance8
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
09/14/2017440398017Open ↗
04/24/2017440398017Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
09/14/2017440398017Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
09/14/2017440398017Open ↗
▸BISNYCECC ANALYSIS1
04/24/2017440398017Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
04/24/2017440398017Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
09/25/2017440398017Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
04/24/2017440398017Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
09/14/2017440398017Open ↗
04/24/2017440398017Open ↗
▸Approvals, Objections & Sign-offs2
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
09/25/2017440398017Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
09/14/2017440398017Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
09/14/2017440398017Open ↗
04/24/2017440398017Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
04/24/2017440398017Open ↗