← Back
Two family frame
257-39 148 ROAD
QUEENS · BIN 4290577
💬 Discuss this project
1965Year Built
2Stories
B2Building Class
R3XZoning
2,250 sfGross Floor Area
2Units
Two family frame · 5,000 sf lot · 0.45 FAR built · Flood zone X500
Locations of Work
ArchitecturePlumbing
Roof1p · 2 filings · 8 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/23/2017$690K—Private party → Private party$307/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC209/27/2024
M.INT'L ENGINEERING PLLC103/14/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CBA CONSULTANTS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MP CONSTRUCTION D INCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272109/27/2024
THOMAS PETERSEN ARCHITECT7854105/31/2024
Building Lifecycle
All (16)Filed (3)Permit Issued (3)Signed Off (3)Inspection (1)Objection (4)Special Inspection (2)
03/04/2025
Signed off — Alteration
Q01108882-I1
03/04/2025
Signed off — Alteration
Q01059498-I1
10/08/2024
Permit issued — Solar
Q01108882-I1-SL
09/27/2024
Filed — Alteration
Q01108882-I1
08/22/2024
Permit issued — Solar
Q01059498-I1-SL
05/31/2024
Filed — Alteration
Q01059498-I1
12/12/2022
Signed off — Alteration
Fire Repair as needed, Minor plastering and tile floor repairs, plumbing fixture replacement on existing roughing, no structural work. no change in use egress or occupancy.
Q00694904-I1
12/08/2022
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/08/2022
Permit issued — General Construction
Q00694904-I1-GC
03/24/2022
Special inspection requirement — Lighting in dwelling units
NANIK MASSAND
03/20/2022
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
03/16/2022
Objection raised — Inspections
03/16/2022
Objection resolved — Addressed
03/16/2022
Objection raised — Scope
03/16/2022
Objection resolved — Addressed
03/14/2022
Filed — Alteration
Fire Repair as needed, Minor plastering and tile floor repairs, plumbing fixture replacement on existing roughing, no structural work. no change in use egress or occupancy.
Q00694904-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTOM PETERSEN ARCHITECT, LLC10/08/2024
DOB NOWSolarSigned-offTOM PETERSEN ARCHITECT, LLC08/22/2024
DOB NOWGeneral ConstructionSigned-offMP CONSTRUCTION D INC04/08/2022
BISOTISSUEDVENTURE HOME SOLAR LLC03/28/2018
3 projects · most recent 11/07/2024
General Wiring
FiledStatusContractorScope
11/07/2024CompleteVENTURE HOME SOLAR LLC—
05/30/2024CompleteVENTURE HOME SOLAR LLC—
04/23/2018CompleteVENTURE HOME SOLAR LLCGeneral Wiring
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
12/08/2022Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
03/24/2022Lighting in dwelling unitsNANIK MASSANDenergy_progress
03/20/2022Energy Code Compliance InspectionsNANIK MASSANDprogress
▾Documents — 40 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/22/2026Q01059498-I1Request digital key ↗
08/21/2026Q01108882-I1Request digital key ↗
08/15/2026Q00694904-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
03/27/2018440472882Open ↗
▸BISWORK PERMIT APPLICATION1
03/27/2018440472882Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISFLOOD ZONE DESIGN CERTIFICATION1
03/27/2018440472882Open ↗
▸Seals & Professional Certifications8
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/21/2026Q01108882-I1Open ↗
08/13/2026Q01059498-I1Open ↗
08/13/2026Q00694904-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/31/2026Q00694904-I1Open ↗
08/31/2026Q00694904-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
03/27/2018440472882Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
03/27/2018440472882Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/27/2018440472882Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
03/27/2018440472882Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/21/2026Q01108882-I1Open ↗
08/13/2026Q00694904-I1Open ↗
08/13/2026Q01059498-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/27/2018440472882Open ↗
▸Energy Compliance8
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
03/12/2019440472882Open ↗
03/27/2018440472882Open ↗
03/27/2018440472882Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
03/27/2018440472882Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
03/12/2019440472882Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
03/27/2018440472882Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
03/12/2019440472882Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026Q00694904-I1Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
03/12/2019440472882Open ↗
03/12/2019440472882Open ↗
03/27/2018440472882Open ↗
Showing 3 of 4 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
03/27/2018440472882Open ↗
▸Approvals, Objections & Sign-offs4
▸DOB NOWUtility Company Final Acceptance Letter2
08/13/2026Q01108882-I1Open ↗
08/13/2026Q01059498-I1Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
03/12/2019440472882Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
03/12/2019440472882Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
03/12/2019440472882Open ↗
03/27/2018440472882Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
03/27/2018440472882Open ↗
▸Other Documents1
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
03/27/2018440472882Open ↗