← Back
Police Department
257 ALEXANDER AVENUE
BRONX · BIN 2000700
💬 Discuss this project
1924Year Built
3Stories
Y2Building Class
R6Zoning
—Gross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Police Department · Owner of record: NYC POLICE DEPARTMENT · 1.37 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction10p · 1 filing · 20 docs
Floor 4Under Construction27p · 1 filing · 20 docs
Floor 3Under Construction29p · 1 filing · 20 docs
Floor 2Under Construction29p · 1 filing · 20 docs
Floor 1Under Construction30p · 1 filing · 20 docs
CellarUnder Construction29p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYPD808/29/2026
NYC POLICE DEPARTMENT103/22/2026
NYCHA103/21/2026
CITY OF N Y - DDC203/21/2026
NEW YORK POLICE DEPARTMENT303/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NYPD406/17/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYPD103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SIENIA CONSTRUCTION INCGeneral Contractor407/25/2026
PEREIRA, EURIPEDESElectrical203/21/2026
THORNE, LAWRENCEElectrical203/21/2026
INPRO PLUMBING CORPPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOMINICK R. PILLA1300406/17/2026
Building Lifecycle
All (43)Filed (4)Permit Issued (5)Violation (19)Objection (2)Special Inspection (13)
07/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dominick Pilla
07/28/2026
Special inspection requirement — Post-installed Anchors
Dominick Pilla
07/24/2026
Permit issued — Mechanical Systems
X01358989-S1-MS
07/23/2026
Permit issued — General Construction
X01358989-I1-GC
07/13/2026
Objection resolved — Addressed
07/10/2026
Objection raised — Other
06/17/2026
Filed — Alteration
Demolition of existing partitions and plumbing fixtures. Installation of new partitions, doors and plumbing fixtures, Demolition, relocation and installation of new lighting fixtures.
X01358989-P1
05/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dominick Pilla
05/20/2026
Special inspection requirement — Post-installed Anchors
Dominick Pilla
04/24/2026
Permit issued — Mechanical Systems
X01358989-S1-MS
04/24/2026
Permit issued — General Construction
X01358989-I1-GC
04/23/2026
Permit issued — Plumbing
X01358989-S2-PL
03/26/2026
Filed — Alteration
Demolition of existing partitions and plumbing fixtures. Installation of new partitions, doors and plumbing fixtures, Demolition, relocation and installation of new lighting fixtures.
X01358989-S2
03/11/2026
Filed — Alteration
Demolition of existing partitions and plumbing fixtures. Installation of new partitions, doors and plumbing fixtures, Demolition, relocation and installation of new lighting fixtures.
X01358989-S1
03/09/2026
Filed — Alteration
Demolition of existing partitions and plumbing fixtures. Installation of new partitions, doors and plumbing fixtures, Demolition, relocation and installation of new lighting fixtures.
X01358989-I1
02/18/2026
Special inspection requirement — Post-installed Anchors
Dominick Pilla
02/18/2026
Special inspection requirement — Mechanical Systems
Dominick Pilla
02/18/2026
Special inspection requirement — Final
Dominick Pilla
02/18/2026
Special inspection requirement — Duct leakage testing, insulation and design
Dominick Pilla
02/18/2026
Special inspection requirement — Permanent certificate
Dominick Pilla
02/18/2026
Special inspection requirement — Ventilation and air distribution system
Dominick Pilla
02/18/2026
Special inspection requirement — Maintenance information
Dominick Pilla
02/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dominick Pilla
02/18/2026
Special inspection requirement — Exhaust and Vent Systems in Plenums and Ducts
Dominick Pilla
09/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/25/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/08/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/08/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/03/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/03/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/15/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/15/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/06/2006
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/31/2005
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/13/2004
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/26/2002
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/07/2000
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/12/1990
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedSIENIA CONSTRUCTION INC07/24/2026
DOB NOWGeneral ConstructionPermit IssuedSIENIA CONSTRUCTION INC07/23/2026
DOB NOWMechanical SystemsPermit IssuedSIENIA CONSTRUCTION INC04/24/2026
DOB NOWGeneral ConstructionPermit IssuedSIENIA CONSTRUCTION INC04/24/2026
DOB NOWPlumbingPermit IssuedINPRO PLUMBING CORP04/23/2026
BISFBISSUEDDYNAMIC CONTRACTING CORP.04/30/2007
BISPLISSUEDDYNAMIC CONTRACTING CORP04/24/2007
BISOTISSUEDDYNAMIC CONTRACTING CORP.03/27/2007
BISPLISSUEDDYNAMIC CONTRACTING CORP09/01/2006
BISBLISSUEDDYNAMIC CONTRACTING CORP.09/01/2006
BISOTISSUEDJCH DELTA CONTRACTING08/10/2006
BISEQRE-ISSUEDL & B CONSTRUCTION NY, INC.01/10/2006
BISEQISSUEDL & B CONSTRUCTION NY, INC.01/10/2006
BISOTISSUEDJCH DELTA CONTRACTING08/05/2005
BISMHISSUEDAJ CONTRACTING COMPANY INC.07/30/1998
BISPLISSUEDGEORGE BRESLAW & SONS, INC.06/27/1995
BISOTISSUEDVIJAY CONSTRUCTION CORP.INC.06/15/1995
1 project · most recent 06/17/2026
Gas Water/Sanitary
FiledStatusContractorScope
06/17/2026Permit IssuedINPRO PLUMBING CORPGas, Water/Sanitary
1 project · most recent 07/30/2026
General Wiring
FiledStatusContractorScope
07/30/2026Permit IssuedAZTECA LIGHTING & ELEC INGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
07/28/2026Fire-Resistant Penetrations and JointsDominick Pillaspecial
07/28/2026Post-installed AnchorsDominick Pillaspecial
05/20/2026Fire-Resistant Penetrations and JointsDominick Pillaspecial
05/20/2026Post-installed AnchorsDominick Pillaspecial
02/18/2026Post-installed AnchorsDominick Pillaspecial
02/18/2026Mechanical SystemsDominick Pillaspecial
02/18/2026FinalDominick Pillaprogress
02/18/2026Duct leakage testing, insulation and designDominick Pillaenergy_progress
02/18/2026Permanent certificateDominick Pillaenergy_progress
02/18/2026Ventilation and air distribution systemDominick Pillaenergy_progress
02/18/2026Maintenance informationDominick Pillaenergy_progress
02/18/2026Fire-Resistant Penetrations and JointsDominick Pillaspecial
02/18/2026Exhaust and Vent Systems in Plenums and DuctsDominick Pillaspecial
▾Documents — 32 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/17/2026X01358989-S2Request digital key ↗
08/17/2026X01358989-S1Request digital key ↗
08/17/2026X01358989-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits5
▸DOB NOWLPC Approval/Permit4
08/14/2026X01358989-P1Open ↗
08/13/2026X01358989-I1Open ↗
08/13/2026X01358989-S1Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION1
12/24/2008210078226Open ↗
▸Seals & Professional Certifications12
▸DOB NOWSpecial Inspector Seal & Signature5
09/23/2026X01358989-S1Open ↗
08/29/2026X01358989-S2Open ↗
08/29/2026X01358989-S2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/17/2026X01358989-S1Open ↗
08/17/2026X01358989-I1Open ↗
08/17/2026X01358989-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026X01358989-S1Open ↗
09/23/2026X01358989-S1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
12/24/2008210078226Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/17/2026X01358989-S2Open ↗
08/17/2026X01358989-S1Open ↗
08/17/2026X01358989-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
12/24/2008210078226Open ↗
▸Approvals, Objections & Sign-offs5
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
08/14/2026X01358989-P1Open ↗
08/13/2026X01358989-S2Open ↗
08/13/2026X01358989-S1Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS1
11/14/2008210078226Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
12/24/2008210078226Open ↗