| Firm | Filings | Most Recent |
|---|---|---|
| J&R DESIGN AND INSPECTION CORP. | 6 | 12/18/2023 |
| NYX ENGINEERING, PLLC | 2 | 07/11/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| HIGH QUALITY 338 | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HIGH QUALITY CONSTRUCTION | General Contractor | 4 | 07/08/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| J&R DESIGN AND INSPECTION | 6637 | 7 | 12/18/2023 |
| NKM ENGINEERING PLLC | 6244 | 1 | 12/18/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | HIGH QUALITY CONSTRUCTION | 12/20/2023 |
| DOB NOW | General Construction | Signed-off | HIGH QUALITY CONSTRUCTION | 11/15/2023 |
| DOB NOW | Mechanical Systems | Signed-off | HIGH QUALITY CONSTRUCTION | 11/15/2023 |
| DOB NOW | Plumbing | Permit Issued | AMERICAN STANDARD P&H CORORP. | 11/14/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/11/2023 | — | — | Air Conditioning Systems | Cooling Gree 3VIR09HP230V1AO 9,000 BTU · Condensing Unit ×1 3VIR12HP230V1AO 12,000 BTU · Condensing Unit ×1 3VIR18HP230V1AO 18,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/14/2023 | Permit Issued | AMERICAN STANDARD P&H COR | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/28/2023 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/15/2023 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 12/15/2023 | Structural Steel - High Strength Bolting | NARESH MAHANGU | special |
| 12/15/2023 | Tenant Protection Plan Compliance | Robert Truskosky | special |
| 12/15/2023 | Concrete - Cast-In-Place | Robert Truskosky | special |
| 12/15/2023 | Structural Cold-Formed Steel | NARESH MAHANGU | special |
| 12/15/2023 | Structural Steel - Details | NARESH MAHANGU | special |
| 12/15/2023 | Final | Robert Truskosky | progress |
| 12/14/2023 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 12/14/2023 | Air barrier - visual inspection | Robert Truskosky | energy_progress |
| 12/14/2023 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 12/14/2023 | Insulation placement and R values | Robert Truskosky | energy_progress |
| 12/14/2023 | Mechanical Systems | Robert Truskosky | special |
| 12/14/2023 | Duct leakage testing, insulation and design | Robert Truskosky | energy_progress |
| 12/14/2023 | Fenestration areas | Robert Truskosky | energy_progress |
| 12/14/2023 | Interior lighting power | Robert Truskosky | energy_progress |
| 12/14/2023 | Fenestration air leakage | Robert Truskosky | energy_progress |
| 12/14/2023 | Fenestration and door U-factor and product ratings | Robert Truskosky | energy_progress |
| 12/14/2023 | Concrete - Cast-In-Place | Robert Truskosky | special |
| 12/14/2023 | Masonry | Robert Truskosky | special |
| 12/14/2023 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 12/14/2023 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 12/14/2023 | Final | Robert Truskosky | progress |
| 12/14/2023 | Fire-Resistance Rated Construction | Robert Truskosky | progress |
| 12/08/2023 | Mechanical Systems | Robert Truskosky | special |
| 12/08/2023 | Concrete - Cast-In-Place | Robert Truskosky | special |