← Back
Office only, 1 story
258-10 HILLSIDE AVENUE
QUEENS · BIN 4624107
💬 Discuss this project
1973Year Built
1Stories
O1Building Class
R3-2Zoning
3,750 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Office only, 1 story · Owner of record: RAI KRUPA LLC · 7,325 sf lot · 0.51 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire Protection
Roof5p · 2 filings · 20 docs
Floor 126p · 5 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/28/2021$5.1M—Private party → RAI KRUPA LLC$1,350/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
M.S. SAVANI ARCHITECT, PC503/13/2023
ALL CITY ENGINEERING PC510/27/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
M.S. SAVANI ARCHITECT,P.C.803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
M I T BROTHERS CONSTRUCTIGeneral Contractor1307/08/2026
WHITESTONE PLUMBING CORPFire Protection107/08/2026
WHITESTONE PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IP CONCRETE TESTING AND I6252803/13/2023
Building Lifecycle
All (69)Filed (10)Permit Issued (7)Signed Off (4)Inspection (8)Objection (10)Special Inspection (30)
03/13/2023
Filed — Alteration CO
Application filed for new C of O. Proposed Community Hall (Adult Day Care Center- 4A) with exterior & interior renovation. Change in Metes and Bounds
Q00610022-P2
03/13/2023
Special inspection requirement — Air barrier — testing
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Energy Code Compliance Inspections
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fenestration air leakage
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Exterior lighting power
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Interior lighting power
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Final
NAVEEN KUMAR
03/13/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Lighting controls
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Insulation placement and R values
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fenestration areas
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Fire-Resistance Rated Construction
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Air barrier - visual inspection
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
INDARDEO PARBHUNATH
03/13/2023
Special inspection requirement — Masonry
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Energy Code Compliance Inspections
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Final
NAVEEN KUMAR
03/03/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Fire-Resistance Rated Construction
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Masonry
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Fenestration air leakage
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Lighting controls
INDARDEO PARBHUNATH
03/03/2023
Special inspection requirement — Insulation placement and R values
INDARDEO PARBHUNATH
02/06/2023
Signed off — Alteration
Mechanical work for fire suppression in the kitchen. Installation of HVAC system. No change in use, egress, or occupancy.
Q00616094-I1
02/03/2023
Signed off — Alteration
Install plumbing fixtures, no change of use, occupancy and egress
Q00616095-I1
12/12/2022
Signed off — Alteration
HEREWITH TO PROPOSE TEMPORARY 8' HIGH WOOD CONSTRUCTION FENCE. NO CHANGES IN OCCUPANCY, USE, GROUP OR EGRESS UNDER THIS APPLICATION.
Q00652311-I1
12/10/2022
Permit issued — Mechanical Systems
Q00616094-I1-MS
12/09/2022
Permit issued — Construction Fence
Q00652311-I1-FN
11/29/2022
Signed off — Alteration
Remove of existing sprinkler for open kitchen, no change of use, occupancy and egress
Q00616096-I1
10/27/2022
Filed — Alteration
Install plumbing fixtures, no change of use, occupancy and egress
Q00616095-P1
10/18/2022
Permit issued — General Construction
Q00610022-I1-GC-CX
10/14/2022
Filed — Alteration
Mechanical work for fire suppression in the kitchen. Installation of HVAC system. No change in use, egress, or occupancy.
Q00616094-P1
10/07/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/03/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/13/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/12/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/22/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/22/2022
Objection resolved — Addressed
07/21/2022
Objection raised — Accessibility
07/14/2022
Filed — Alteration CO
Application filed for new C of O. Proposed Community Hall (Adult Day Care Center- 4A) with exterior & interior renovation. Change in Metes and Bounds
Q00610022-P1
06/30/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/29/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/29/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/12/2022
Objection raised — Fire_Protection
04/12/2022
Objection resolved — Addressed
04/12/2022
Objection raised — Fire_Protection
04/12/2022
Objection resolved — Addressed
04/12/2022
Objection raised — Fire_Protection
04/12/2022
Objection resolved — Addressed
04/12/2022
Objection raised — Scope
04/12/2022
Objection resolved — Addressed
04/07/2022
Permit issued — General Construction
Q00610022-I1-GC-CX
Latest 60 of 69 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offM I T BROTHERS CONSTRUCTI12/10/2022
DOB NOWConstruction FenceSigned-offM I T BROTHERS CONSTRUCTI12/09/2022
DOB NOWGeneral ConstructionPermit IssuedM I T BROTHERS CONSTRUCTI10/18/2022
DOB NOWGeneral ConstructionPermit IssuedM I T BROTHERS CONSTRUCTI04/07/2022
DOB NOWSprinklersSigned-offTEMPERINI MECHANICAL INC03/21/2022
DOB NOWPlumbingSigned-offWHITESTONE PLUMBING CORP03/21/2022
DOB NOWGeneral ConstructionPermit IssuedM I T BROTHERS CONSTRUCTI03/04/2022
1 project · most recent 03/24/2022
General Wiring
FiledStatusContractorScope
03/24/2022CompleteNELSON & TOM MAINT INC DBGeneral Wiring
1 project · most recent 03/13/2023
Masonry Wood
FiledStatusContractorScope
03/13/2023Permit IssuedM I T BROTHERS CONSTRUCTIMasonry, Wood
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
10/07/2022Pass-Final CND-Occupancy InspectionPassView ↗
10/03/2022Pass-Final CND-Occupancy InspectionPassView ↗
09/13/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/12/2022Pass-Final CND-Occupancy InspectionPassView ↗
07/22/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/30/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/29/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/29/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 77
DateRequirementInspectorRole
03/13/2023Mastic and Intumescent Fire-resistant CoatingsINDARDEO PARBHUNATHspecial
03/13/2023Insulation placement and R valuesINDARDEO PARBHUNATHenergy_progress
03/13/2023Exterior lighting powerINDARDEO PARBHUNATHenergy_progress
03/13/2023Air barrier - visual inspectionINDARDEO PARBHUNATHenergy_progress
03/13/2023Lighting controlsINDARDEO PARBHUNATHenergy_progress
03/13/2023Air barrier — testing INDARDEO PARBHUNATHenergy_progress
03/13/2023Fenestration air leakageINDARDEO PARBHUNATHenergy_progress
03/13/2023Fenestration areasINDARDEO PARBHUNATHenergy_progress
03/13/2023Fenestration and door U-factor and product ratingsINDARDEO PARBHUNATHenergy_progress
03/13/2023Interior lighting powerINDARDEO PARBHUNATHenergy_progress
03/13/2023Fire-Resistance Rated ConstructionINDARDEO PARBHUNATHprogress
03/13/2023Energy Code Compliance InspectionsINDARDEO PARBHUNATHprogress
03/13/2023FinalNAVEEN KUMARprogress
03/13/2023Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
03/13/2023MasonryINDARDEO PARBHUNATHspecial
03/13/2023Structural Stability – Alterations of existing buildingsINDARDEO PARBHUNATHspecial
03/13/2023Exterior Insulation and Finish Systems (EIFS)INDARDEO PARBHUNATHspecial
03/13/2023Wall Panels, Curtain Walls, and VeneersINDARDEO PARBHUNATHspecial
03/03/2023Exterior Insulation and Finish Systems (EIFS)INDARDEO PARBHUNATHspecial
03/03/2023Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
03/03/2023MasonryINDARDEO PARBHUNATHspecial
03/03/2023Mastic and Intumescent Fire-resistant CoatingsINDARDEO PARBHUNATHspecial
03/03/2023Structural Stability – Alterations of existing buildingsINDARDEO PARBHUNATHspecial
03/03/2023Wall Panels, Curtain Walls, and VeneersINDARDEO PARBHUNATHspecial
03/03/2023Energy Code Compliance InspectionsINDARDEO PARBHUNATHprogress
Latest 25 of 77.
▾Documents — 123 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch9
08/26/2026Q00652311-I1Request digital key ↗
08/26/2026Q00616096-I1Request digital key ↗
08/26/2026Q00616094-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly1
08/15/2026Q00705459-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00610022-I1Open ↗
▸Seals & Professional Certifications87
▸DOB NOWProgress Inspector Seal & Signature53
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
Showing 3 of 53 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature24
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
09/01/2026Q00610022-P2Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/26/2026Q00652311-I1Open ↗
08/26/2026Q00705459-I1Open ↗
08/25/2026Q00610022-P1Open ↗
Showing 3 of 10 on file for this type
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist3
08/13/2026Q00610022-P2Open ↗
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00610022-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00610022-I1Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/25/2026Q00610022-P2Open ↗
08/25/2026Q00610022-I1Open ↗
08/15/2026Q00610022-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWOER: Notice of Satisfaction3
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00616094-I1Open ↗
08/13/2026Q00616095-I1Open ↗
▸DOB NOWOER: Notice to Proceed3
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00616094-I1Open ↗
08/13/2026Q00616095-I1Open ↗
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00610022-I1Open ↗
08/13/2026Q00616094-I1Open ↗
▸Other Documents5
▸DOB NOWProperty Ownership Certification3
08/25/2026Q00610022-P2Open ↗
08/25/2026Q00610022-I1Open ↗
08/15/2026Q00610022-P1Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026Q00610022-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00610022-I1Open ↗